EVENT SPECIFIC GUIDELINES 7 (ESG-7)<br />

POWER OUTAGE<br />

3.2.21. PREPAREDNESS / MITIGATION<br />

The Technical Services Department is responsible for ensuring all emergency<br />

generators are in good working order <strong>and</strong> ready for activation <strong>and</strong>/or deployment at<br />

all times.<br />

3.2.22. RESPONSE<br />

Classify the incident in accordance with Section 1.6 of the Basic <strong>Plan</strong>.<br />

Notify Safety Manager for any incident classified as Level 2 or higher.<br />

Implement appropriate levels of Incident Management / Incident Comm<strong>and</strong>.<br />

ISF-12, Wastewater Collections is primarily responsible for deploying mobile<br />

emergency generators to Wastewater Pump Stations as needed.<br />

ISF-13, Electrical & <strong>Emergency</strong> Power will provide support <strong>and</strong> assistance as<br />

required by the incident.<br />

3.2.23. FOLLOW-UP<br />

Safety Manager shall conduct a Critique of all incidents classified as Level 2 or<br />

higher, <strong>and</strong> shall properly document <strong>and</strong> follow-up on all findings <strong>and</strong> resulting<br />

corrective actions <strong>and</strong>/or recommendations.<br />

<strong>Gr<strong>and</strong></strong> <strong>Str<strong>and</strong></strong> <strong>Water</strong> & <strong>Sewer</strong> <strong>Authority</strong> 113 CONFIDENTIAL MATERIALS<br />

<strong>Emergency</strong> Management <strong>Plan</strong><br />

SECURITY SENSITIVE<br />

June 7, 2013<br />

NOT FOR PUBLIC<br />

DISCLOSURE

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!