13.11.2014 Views

TR Circular E-C058_9th LRT Conference_2003.pdf - Florida ...

TR Circular E-C058_9th LRT Conference_2003.pdf - Florida ...

TR Circular E-C058_9th LRT Conference_2003.pdf - Florida ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Loetterle 549<br />

SPECIAL CHALLENGES<br />

There were many special challenges faced when implementing the property exchange<br />

agreements.<br />

To some degree or another, the DB contractor had to perform some of the services<br />

promised to the agency because the work needed to be coordinated with track construction.<br />

Having the DB contractor do any work for a federal agency is difficult to coordinate. The federal<br />

property owners had to work within the review procedures established in the contract with the<br />

DB contractor. This usually meant that the agency had to review plans within the 15-day review<br />

period that the HPO had to work with. In the future it is recommended that separate review<br />

procedures be established whenever work is to be performed on private property.<br />

Another significant challenge was working on military bases during the recent military<br />

actions overseas. On 9/11, a Council contractor was working on the USAR base constructing the<br />

office building. That afternoon, the contractor was forced to vacate the site and was not allowed<br />

to resume work for a week. Once allowed back on, what had been a relatively relaxed<br />

atmosphere had turned into a situation with armed guards and searches. At first, the contractors<br />

were not allowed to bring their trucks on site, which was challenging for the workers. After a<br />

couple of weeks working in this environment, a fence was erected around the work zone and a<br />

separate entrance provided for the contractor. The site was secured at night but it was no longer<br />

necessary to pass armed guards every day. When work on the Air Guard base began, the same<br />

technique was used to segregate the construction of the building from the rest of the base.<br />

However, some of the work still had to be performed in the secure area and this required that<br />

security personnel escort workers.<br />

LESSONS LEARNED<br />

The experience with federal agencies described is necessarily in summary form. It would be<br />

impossible to provide a complete history in such a short paper. But there are important lessons<br />

that can be learned from the Minneapolis experience.<br />

Avoid Federal Land if Possible<br />

Attempting to acquire federal land introduces both schedule and financial risks to the project.<br />

Unless pushed energetically, the process can be slow, tedious, and frustrating. Until negotiations<br />

are complete, costs are difficult to predict. If possible, federal land should be avoided.<br />

There are cases however, when using federal land can clearly benefit a project and the<br />

federal landowner. For example, serving a Veterans Hospital is clearly beneficial to the project<br />

and to the public good. In these cases, the federal agency is much more likely to do what is<br />

necessary to bring about the project. In the case of Fort Snelling, all of the agencies involved<br />

were cognizant of the benefits of having a station near their bases.<br />

Learn About the Agency<br />

Each federal agency is different, with different personalities and different rules. It is important to<br />

take the time to understand the structure of an agency, the agency’s mission, and the decision-

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!