13.11.2014 Views

TR Circular E-C058_9th LRT Conference_2003.pdf - Florida ...

TR Circular E-C058_9th LRT Conference_2003.pdf - Florida ...

TR Circular E-C058_9th LRT Conference_2003.pdf - Florida ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

544 Transportation Research <strong>Circular</strong> E-<strong>C058</strong>: <strong>9th</strong> National Light Rail Transit <strong>Conference</strong><br />

selected based upon negotiations with local GSA representatives, the Chicago GSA put together<br />

a team to provide the HPO with input for the design of the parking garage to be situated on their<br />

property.<br />

Before September 11, 2001 (9/11), the worst case of domestic terrorism was the bombing<br />

of the Murrow Federal Building in Oklahoma City. For this reason, the design of the parking<br />

garage became a topic of intense discussion. The Federal Protective Service in charge of<br />

protecting the Whipple Federal Building was concerned about a similar event occurring in<br />

Minneapolis. Working with the GSA design team, several unique features were added to the<br />

parking garage to increase the security of the facility:<br />

1. The upper levels of the garage had to be stepped back to allow for blast deflection.<br />

2. Entry/exit ramps and stairs for the park-and-ride users had to be physically separate<br />

from the portion if the parking structure was reserved for building employees.<br />

3. Extensive security camera coverage and other security elements had to be included.<br />

The parking ramp design criteria developed by GSA were included in the bid package<br />

issued in early 2000 for the solicitation of design-build construction teams. Although the designbuild<br />

package was bid on a lump sum basis, this garage was included as an add-alternate<br />

allowing the reviewers of the proposals to know what this particular element was going to cost.<br />

After the proposals were received, it was clear that the construction of a parking ramp was not<br />

cost effective. The parking ramp concept was dropped and the park and ride moved to a surface<br />

lot on nearby land.<br />

Renewed negotiations with GSA focused on developing a concept design and design<br />

criteria for the federal building parking lot, which was to be reconstructed to prevent rail users<br />

from parking in the lot illegally. This process began in early 2001. A package of design criteria<br />

was completed in May 2001 and forwarded to the design build contractor. The design criteria<br />

completed by GSA with the assistance of HPO were very detailed. This detail was necessary to<br />

ensure that the design met GSA’s needs. It also became valuable later to ensure that no<br />

additional work was requested by GSA.<br />

Design of the lot proceeded through the latter half of 2001, but the completion of a<br />

property exchange agreement was not possible until a final design was presented to the GSA.<br />

Design of the lot was complicated by the fact that the design build contractor was doing the<br />

design in conjunction with the design of the rest of the project. GSA was forced to work within<br />

the design review procedures established in the DB contract. This was difficult to coordinate and<br />

required that GSA respond to plans that they were presented with within 10 days of receiving the<br />

plans. To their credit, GSA always responded to the plan review in the time allotted.<br />

But completing the agreement was also complicated by an underlying mistrust of HPO by<br />

Chicago GSA. GSA wanted assurances that once they signed over an easement to the Council<br />

that they would in fact receive the construction for which they had bargained. GSA requested a<br />

performance bond, but the Council could not secure that type of instrument because the Council<br />

was not the contractor doing the work. The contractor was under contract to MnDOT, so the<br />

GSA did not have recourse to the contractor’s performance bond. Eventually, it was decided that<br />

the Council would put into escrow an amount equal to the estimated cost of the work that was<br />

being performed on GSA property.<br />

The escrow agreement was executed simultaneously with the property exchange<br />

agreement. At this time, an easement was granted to the Council for the property used to build

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!