Board of Regents Meeting<br />
August 5-6, 2010<br />
Item #26<br />
EXECUTIVE SUMMARY Page 8 of 9<br />
Capital <strong>Project</strong> Cost Estimate<br />
University: Northern Arizona University<br />
<strong>Project</strong>:<br />
<strong>Native</strong> <strong>American</strong> <strong>Cultural</strong> <strong>Center</strong><br />
Capital<br />
<strong>Project</strong><br />
Development <strong>Implementation</strong> <strong>Project</strong><br />
Plan Approval Approval<br />
Capital Costs<br />
1. L<strong>and</strong> Acquisition $ - $ - $<br />
-<br />
2. Construction Cost - - -<br />
A. New Construction 4,794,907 4,794,907<br />
B. Renovation - -<br />
C. Fixed Equipment (Owner Furnished) - - -<br />
D. Site Development (excl. 2.E.) - - -<br />
E. Parking <strong>and</strong> L<strong>and</strong>scaping - - -<br />
F. Utilities Extensions - - -<br />
G. Other (Asbestos) - 30,000 30,000<br />
G. Inflation <strong>and</strong> Market Adjustment (0.0%) - - -<br />
Subtotal Construction Cost $ - $ 4,824,907 $ 4,824,907<br />
3. Fees<br />
A. Construction Mgr (3%) $ - $ 152,000 $ 152,000<br />
B. Architect/Engineer (15%) - 729,585 729,585<br />
C. Other (2%) - 116,885 116,885<br />
Subtotal Consultant Fees $ - $ 998,470 $ 998,470<br />
4. FF&E Movable $ - $ 316,000 $ 316,000<br />
5. Contingency, Design Phase (0.0%) - - -<br />
6. Contingency, Construction Phase (8%) - 386,458 386,458<br />
7. Parking Reserve - 5,000 5,000<br />
8. Telecommunications Equipment - 35,000 35,000<br />
Subtotal Items 4-8 $ - $ 742,458 $ 742,458<br />
9. Additional University Costs<br />
A. Surveys, Tests, Inspections, etc. $ - $ 162,452 $ 162,452<br />
B. Move-in Costs - 12,000 12,000<br />
C. Printing Advertisement - 1,600 1,600<br />
D. 3rd Party Estimate, UA Review, Audit - 62,000 62,000<br />
E. <strong>Project</strong> Management Cost (2.5%) 175,000 175,000<br />
F. State Risk Mgmt Insurance (.0034%) - 21,113 21,113<br />
Subtotal Additional University Costs $ - $ 434,165 $ 434,165<br />
TOTAL CAPITAL COST $ 6,000,000 $ 7,000,000 $ 7,000,000