13.11.2014 Views

Native American Cultural Center Project Implementation and Project

Native American Cultural Center Project Implementation and Project

Native American Cultural Center Project Implementation and Project

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Board of Regents Meeting<br />

August 5-6, 2010<br />

Item #26<br />

EXECUTIVE SUMMARY Page 8 of 9<br />

Capital <strong>Project</strong> Cost Estimate<br />

University: Northern Arizona University<br />

<strong>Project</strong>:<br />

<strong>Native</strong> <strong>American</strong> <strong>Cultural</strong> <strong>Center</strong><br />

Capital<br />

<strong>Project</strong><br />

Development <strong>Implementation</strong> <strong>Project</strong><br />

Plan Approval Approval<br />

Capital Costs<br />

1. L<strong>and</strong> Acquisition $ - $ - $<br />

-<br />

2. Construction Cost - - -<br />

A. New Construction 4,794,907 4,794,907<br />

B. Renovation - -<br />

C. Fixed Equipment (Owner Furnished) - - -<br />

D. Site Development (excl. 2.E.) - - -<br />

E. Parking <strong>and</strong> L<strong>and</strong>scaping - - -<br />

F. Utilities Extensions - - -<br />

G. Other (Asbestos) - 30,000 30,000<br />

G. Inflation <strong>and</strong> Market Adjustment (0.0%) - - -<br />

Subtotal Construction Cost $ - $ 4,824,907 $ 4,824,907<br />

3. Fees<br />

A. Construction Mgr (3%) $ - $ 152,000 $ 152,000<br />

B. Architect/Engineer (15%) - 729,585 729,585<br />

C. Other (2%) - 116,885 116,885<br />

Subtotal Consultant Fees $ - $ 998,470 $ 998,470<br />

4. FF&E Movable $ - $ 316,000 $ 316,000<br />

5. Contingency, Design Phase (0.0%) - - -<br />

6. Contingency, Construction Phase (8%) - 386,458 386,458<br />

7. Parking Reserve - 5,000 5,000<br />

8. Telecommunications Equipment - 35,000 35,000<br />

Subtotal Items 4-8 $ - $ 742,458 $ 742,458<br />

9. Additional University Costs<br />

A. Surveys, Tests, Inspections, etc. $ - $ 162,452 $ 162,452<br />

B. Move-in Costs - 12,000 12,000<br />

C. Printing Advertisement - 1,600 1,600<br />

D. 3rd Party Estimate, UA Review, Audit - 62,000 62,000<br />

E. <strong>Project</strong> Management Cost (2.5%) 175,000 175,000<br />

F. State Risk Mgmt Insurance (.0034%) - 21,113 21,113<br />

Subtotal Additional University Costs $ - $ 434,165 $ 434,165<br />

TOTAL CAPITAL COST $ 6,000,000 $ 7,000,000 $ 7,000,000

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!