Board of Regents Meeting<br />
August 5-6, 2010<br />
Item #26<br />
EXECUTIVE SUMMARY Page 6 of 9<br />
<strong>Project</strong> Status <strong>and</strong> Schedule:<br />
<br />
<br />
Construction documents for the project are nearing completion. The GMP is<br />
based upon 100% bids from subcontractors for the original scope. New bids for<br />
new site work related to relocation <strong>and</strong> foundation redesign are currently being<br />
evaluated. All bids are within the approved project budget.<br />
General construction is scheduled to begin in September 2010. Construction is<br />
scheduled to be complete in October 2011.<br />
Committee Review <strong>and</strong> Recommendation:<br />
The Capital <strong>and</strong> <strong>Project</strong> Finance Committee reviewed this item at its July 15,<br />
2010 meeting <strong>and</strong> recommended forwarding for Board approval.<br />
<br />
The Committee had a discussion on the potential to model the cultural center<br />
similar to other university cultural centers that serve as regional <strong>and</strong> national<br />
attractions.<br />
Recommendation to the Board<br />
It is recommended the Board grant combined <strong>Project</strong> <strong>Implementation</strong> Approval <strong>and</strong><br />
<strong>Project</strong> Approval for the NAU <strong>Native</strong> <strong>American</strong> <strong>Cultural</strong> <strong>Center</strong> project, as presented in<br />
this Executive Summary.