13.11.2014 Views

Native American Cultural Center Project Implementation and Project

Native American Cultural Center Project Implementation and Project

Native American Cultural Center Project Implementation and Project

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Board of Regents Meeting<br />

August 5-6, 2010<br />

Item #26<br />

EXECUTIVE SUMMARY Page 6 of 9<br />

<strong>Project</strong> Status <strong>and</strong> Schedule:<br />

<br />

<br />

Construction documents for the project are nearing completion. The GMP is<br />

based upon 100% bids from subcontractors for the original scope. New bids for<br />

new site work related to relocation <strong>and</strong> foundation redesign are currently being<br />

evaluated. All bids are within the approved project budget.<br />

General construction is scheduled to begin in September 2010. Construction is<br />

scheduled to be complete in October 2011.<br />

Committee Review <strong>and</strong> Recommendation:<br />

The Capital <strong>and</strong> <strong>Project</strong> Finance Committee reviewed this item at its July 15,<br />

2010 meeting <strong>and</strong> recommended forwarding for Board approval.<br />

<br />

The Committee had a discussion on the potential to model the cultural center<br />

similar to other university cultural centers that serve as regional <strong>and</strong> national<br />

attractions.<br />

Recommendation to the Board<br />

It is recommended the Board grant combined <strong>Project</strong> <strong>Implementation</strong> Approval <strong>and</strong><br />

<strong>Project</strong> Approval for the NAU <strong>Native</strong> <strong>American</strong> <strong>Cultural</strong> <strong>Center</strong> project, as presented in<br />

this Executive Summary.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!