Board of Regents Meeting<br />

August 5-6, 2010<br />

Item #26<br />

EXECUTIVE SUMMARY Page 3 of 9<br />

footage. This will result in a net increase of 4,658 square feet in the university’s<br />

total. The parking lot adjoining the site will be removed to provide the outdoor<br />

spaces that are an integral part of this facility.<br />

<br />

<br />

<br />

<br />

The site change, facilitated by master planning discussions, focused on<br />

accessibility <strong>and</strong> visibility to all students <strong>and</strong> the community, as well as its<br />

congruence with the campus civic boundaries which include Cline Library, Ardrey<br />

Auditorium <strong>and</strong> the University Union. The new site will allow for better long term<br />

integration of the facility <strong>and</strong> its programs <strong>and</strong> outreach efforts with the<br />

community.<br />

Relocation preserves space for future development within the science <strong>and</strong> math<br />

academic core. The previous site has been identified as an ideal site for needed<br />

improvements <strong>and</strong> growth in the sciences/math complex. Over 60% of all<br />

incoming students are required to take a science/lab <strong>and</strong> math class. As<br />

enrollments continue to increase the need to address these programs is quickly<br />

becoming more critical. This site is the only available site on the north campus<br />

core available for an academic building of over 100,000 gsf.<br />

The new site also allows for the continued greening of campus, as well as<br />

removal of interior roadways <strong>and</strong> parking lots <strong>and</strong> continued improvements to the<br />

pedestrian spine.<br />

Site work required at the proposed location allows utility connections to be<br />

brought into current code compliance. New electrical service will come from a<br />

switch rather than the adjacent building; water service will have new connections<br />

as well. Connection points for steam <strong>and</strong> chilled water are in close proximity to<br />

the building site, but will require extensions from the North Plant.<br />

o Site costs will be spent by the University eventually, if not for the NACC<br />

then for the next project;<br />

o Demolition cost will be incurred for any building replacement;<br />

o Existing counseling building has a cost to keep open – building is<br />

unattractive <strong>and</strong> inefficient; <strong>and</strong>,<br />

o Utilities upgrades or extensions are needed for any new work.<br />

<br />

Additionally, geotechnical reports on the site indicated poor soil in a small portion<br />

of the site resulting in some redesign of the project’s foundation <strong>and</strong> the footings<br />

to ensure high quality, durable construction.<br />

Additional <strong>Project</strong> Considerations:<br />

<br />

This construction project has been designed in accordance with university<br />

Design Guidelines, <strong>and</strong> will be constructed of high quality, durable, maintainable<br />

materials <strong>and</strong> building systems to maximize energy efficiency <strong>and</strong> minimize<br />

operational, repair <strong>and</strong> replacement costs.