Revised December 2010<br />

22. Southwest of Four Corners<br />

Location:<br />

Northeastern Arizona<br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Definition: Sum of the flows on the following transmission lines (see Fig. 1):<br />

Line<br />

Metered End<br />

Four Corners-Moenkopi 500 kV Four Corners 500 kV<br />

Four Corners-Cholla #1 345 kV Four Corners 345 kV<br />

Four Corners-Cholla #2 345 kV Four Corners 345 kV<br />

Transfer Limit: East-West: 2325 MW<br />

West-East: Undefined<br />

The 2325 MW nominal operating limit is limited by the thermal rating of the<br />

Four Corners-Cholla 345 kV lines and voltage deviation at Pinnacle Peak<br />

following the critical disturbance. The actual rating is defined by the vertical<br />

and horizontal elements of the attached nomogram (Fig 2).<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

When:<br />

The critical disturbance is dependent on the location along the nomogram.<br />

Two critical contingencies for defining the nomorgram are loss of the Four<br />

Corners-Moenkopi line and loss of the Four Corners-Cholla #2 345 kV line.<br />

The TTC rating was established in the mid 1980’s by the Four Corners<br />

Technical Studies Task Force and verified by 2010 System Operating Limit<br />

(SOL) studies. The task force is comprised of members from the following<br />

companies:<br />

• Arizona Public Service Company<br />

• El Paso Electric Company<br />

• Public Service Company of New Mexico<br />

• Salt River Project<br />

• Southern California Edison Company<br />

• Tucson Electric Power Company<br />

System<br />

Conditions:<br />

Study Criteria:<br />

Remedial<br />

Actions<br />

Required:<br />

Formal<br />

Operating<br />

Procedure:<br />

Flows on this transfer path have historically been east to west due to the large<br />

amount of generation located in northwestern New Mexico. This generation<br />

is partly owned by entities west of the Arizona - New Mexico border.<br />

The 2325 MW nominal limit was determined due to voltage deviation and<br />

thermal constraints.<br />

Same as WECC Reliability Criteria and NERC Planning Standards for<br />

Transmission System Planning.<br />

None<br />

None<br />