20. <strong>Path</strong> C (Pre Gateway)<br />

Revised January <strong>2013</strong><br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Location:<br />

Definition:<br />

Transfer Limit:<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

Northern Utah/Southern Idaho<br />

Sum of the flows on the following transmission lines:<br />

Line<br />

Malad-American Falls* 138 kV<br />

Ben Lomond-Populus* #1 345 kV<br />

Ben Lomond-Populus* #2 345 kV<br />

Terminal-Populus * 345 kV<br />

Treasureton-SunBeam-Brady* 345 kV<br />

FishCreek-Goshen* 161 kV<br />

Threemile Knoll 138/345 * kV transformer<br />

Threemile Knoll 138*/115 kV transformer (Future)<br />

North to South: 1600 MW (nominal)<br />

South to North: 1250 MW (nominal)<br />

Operating limits are based on System Operating Limit (SOL) studies.<br />

Southbound: Post disturbance voltages on <strong>Path</strong> 18 limit southbound capacity<br />

to 1600 MW following an N-2 <strong>Path</strong> 19 outage which causes two Bridger units<br />

to trip due to Bridger RAS operation.<br />

Northbound: Post disturbance flows following N-1 or N-2 outages on the<br />

remaining line west of Populus limit the Northbound capacity to 1250 MW or<br />

less based on a simultaneous nomogram (Figure 1) with Bridger West. Up to<br />

two Bridger units may trip due to Bridger RAS operation to reduce Populus<br />

west flow.<br />

When: Phase 3 status granted November 20, 2008<br />

System<br />

Conditions:<br />

Study Criteria:<br />

Remedial<br />

Actions<br />

Required:<br />

Formal<br />

Operating<br />

Procedure:<br />

Northbound capacity is determined under light load conditions when thermal<br />

resources in Utah are being transferred to the NW, and Southbound capacity<br />

is determined under heavy summer loading conditions. Due to the interaction<br />

with the Bridger West <strong>Path</strong>, a nomogram between <strong>Path</strong> C (Northbound) and<br />

Bridger West has been established. (See Figure 1)<br />

• Steady state pre disturbance voltages between .95 p.u. and 1.05 p.u.<br />

• Post-disturbance voltages between .90 p.u. and 1.10 p.u.<br />

• Post-disturbance line loadings less than “emergency ratings.”<br />

• First-swing transient voltage dips not to exceed .80 p.u.<br />

Bridger RAS operation may trip up to two units as discussed above.<br />

Yes<br />

Allocation:<br />

100% PacifiCorp<br />

PART VI Item 1-56