Path Rating Catalog 2013 - Western Electricity Coordinating Council

Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council

12.11.2014 Views

Added February 2011 II-7. Path 3 S-N Rerating (Thermal Upgrade) Project Accepted Rating Existing Rating Other Location: Washington and southern British Columbia Definition: (Path 3) Transfer Limit: Critical Disturbance that limits the transfer capability: BC Hydro, operates, and manages all transmission equipment owned by BC Hydro in British Columbia. Line Owner Metered End Custer (BPA)-Ingledow (BCH) 500 kV lines 1&2 (Westside Intertie) Joint Ingledow(North end) Boundary (BPA)-Waneta (TECK) 230 kV (Eastside Intertie, Normally Open) Joint Boundary (South end) Boundary (BPA)-Nelway (BCH) 230 kV (Eastside Intertie, Normally Close) Joint Boundary (South end) Comprehensive Progress Report indicates that Path 3 Northwest - British Columbia South to North is capable of 3000 MW. Path 3 has been accepted into Phase 2 of the Path Rating Process with a South to North Planned Rating of 3000 MW. Under system normal configuration and realistic, favourable system conditions, applying single and double contingencies in BPA, Columbia Grid & BC hydro systems, the steady state power flow and transient stability studies have shown that with proper mitigation, the Northwest-British Columbia Path rating (South to North) can be increased to 3000 MW from the current rating of 2000 MW. The study also shows that loss of one of two Custer (BPA)-Ingledow (BCH) 500 kV lines would overload the remaining 500 kV line if S-N transfer is more than 3000 MW. See Phase 1 report at Path3_S-N3000 When: Planned Rating confirmed by letter from TSS Chair dated February 15, 2011. System See Phase 1 report at Path3_S-N3000 Conditions: Study Criteria: See Phase 1 report at Path3_S-N3000 Remedial Actions Required: Formal Operating Procedure: Allocation: None required at this time To be developed. 2750 MW: Custer (BPA)-Ingledow (BCH) 500 kV lines 1&2 (Westside Intertie) 250 MW: Boundary (BPA)-Waneta (TECK) 230 kV (Eastside Intertie, Normally Open) and Boundary (BPA)-Nelway (BCH) 230 kV (Eastside PART VI Item 1-268

Intertie, Normally Close) Interaction w/Other Transfer Paths: Contact Person: Note that the S-N maximum transfer limit on Eastside Intertie is still 400 MW, which means that when the transfer on Westside Intertie is 2600 MW, the S-N transfer on East Intertie can be 400 MW. To be determined in Phase 2 Studies. Stephen Tran Transmission Contracts Manager Phone: 604 623 3907 stephen.tran@bchydro.com PART VI Item 1-269

Added February 2011<br />

II-7. <strong>Path</strong> 3 S-N Rerating (Thermal<br />

Upgrade) Project<br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Location:<br />

Washington and southern British Columbia<br />

Definition:<br />

(<strong>Path</strong> 3)<br />

Transfer Limit:<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

BC Hydro, operates, and manages all transmission equipment owned by BC<br />

Hydro in British Columbia.<br />

Line Owner Metered End<br />

Custer (BPA)-Ingledow (BCH)<br />

500 kV lines 1&2 (Westside Intertie) Joint Ingledow(North end)<br />

Boundary (BPA)-Waneta (TECK)<br />

230 kV (Eastside Intertie,<br />

Normally Open) Joint Boundary (South end)<br />

Boundary (BPA)-Nelway (BCH)<br />

230 kV (Eastside Intertie,<br />

Normally Close) Joint Boundary (South end)<br />

Comprehensive Progress Report indicates that <strong>Path</strong> 3 Northwest - British<br />

Columbia South to North is capable of 3000 MW. <strong>Path</strong> 3 has been accepted<br />

into Phase 2 of the <strong>Path</strong> <strong>Rating</strong> Process with a South to North Planned <strong>Rating</strong><br />

of 3000 MW.<br />

Under system normal configuration and realistic, favourable system<br />

conditions, applying single and double contingencies in BPA, Columbia Grid<br />

& BC hydro systems, the steady state power flow and transient stability<br />

studies have shown that with proper mitigation, the Northwest-British<br />

Columbia <strong>Path</strong> rating (South to North) can be increased to 3000 MW from the<br />

current rating of 2000 MW. The study also shows that loss of one of two<br />

Custer (BPA)-Ingledow (BCH) 500 kV lines would overload the remaining<br />

500 kV line if S-N transfer is more than 3000 MW. See Phase 1 report at<br />

<strong>Path</strong>3_S-N3000<br />

When: Planned <strong>Rating</strong> confirmed by letter from TSS Chair dated February 15, 2011.<br />

System<br />

See Phase 1 report at <strong>Path</strong>3_S-N3000<br />

Conditions:<br />

Study Criteria: See Phase 1 report at <strong>Path</strong>3_S-N3000<br />

Remedial<br />

Actions<br />

Required:<br />

Formal<br />

Operating<br />

Procedure:<br />

Allocation:<br />

None required at this time<br />

To be developed.<br />

2750 MW: Custer (BPA)-Ingledow (BCH) 500 kV lines 1&2 (Westside<br />

Intertie)<br />

250 MW: Boundary (BPA)-Waneta (TECK) 230 kV (Eastside Intertie,<br />

Normally Open) and Boundary (BPA)-Nelway (BCH) 230 kV (Eastside<br />

PART VI Item 1-268

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!