Path Rating Catalog 2013 - Western Electricity Coordinating Council
Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council
82. TotBeast Revised January 2013 Accepted Rating Existing Rating Other Location: Definition: Transfer Limit: Critical Disturbance that limits the transfer capability: When: System Conditions: Study Criteria: Remedial Actions Required: Southwest Idaho and Eastern Oregon/Washington and Northern Idaho Sum of the flows on the following lines: Line Metered End Summer Lake - Hemingway 500 kV Hemingway Brownlee-Boise Bench #1 230 kV Brownlee Brownlee-Boise Bench #2 230 kV Brownlee Brownlee-Boise Bench #3 230 kV Brownlee Brownlee-Horse Flat #4 230 kV Brownlee Brownlee-Ontario 230kV Brownlee Oxbow-Starkey 138kV Oxbow Quartz-Ontario 138kV Quartz West to East: 2465 MW 1915 MW Brownlee East (Path 55) 550 MW Hemingway-Summer Lake 500 kV (Path 75) Post transient reactive margin at the Boise Bench 230kV following the loss of the Hemingway-Summer Lake 500kV line, or the loss of two Jim Bridger lines with tripping of two Jim Bridger Units, or the loss of two Brownlee- Boise Bench 230kV lines. Thermal limits on the remaining two Brownlee- Boise Bench 230kV lines for loss of the other two lines. The thermal overload of the Lolo-Oxbow 230kV line is the limiting condition for an outage of the Hemingway-Summer Lake 500kV line. This is an expanded version of the Brownlee East path (#55) that now also includes the Hemingway-Summer Lake path (#75) in its West to East direction. As this is only a combined rating of the other two paths which already have “accepted” ratings; study results supporting this path’s “other” rating are based on rating / OTC studies performed on the two component paths. A description of the rating history of each of the two paths can be found in the corresponding section for each path in this path catalog. The 2465 MW west to east transfer rating on TotBeast was studied with high imports on Idaho-Northwest (Path 14) , Brownlee East (Path 55) flows (1915MW) simultaneous with -550MW on the Hemingway-Summer Lake 500kV line (Path 75), high T E Roach Complex generation at peak summer load conditions. This generally coincides with high hydro conditions in the Northwest with low to moderate eastern thermal resources. NERC/WECC Reliability Criteria For Transmission System Planning At high flows east of Brownlee, the loss of two Brownlee-Boise Bench 230kV lines requires overload mitigation measure of bypassing ½ series compensation in the remaining two Brownlee-Boise Bench 230kV lines. PART VI Item 1-206
Revised January 2013 Formal Operating Procedure: Allocation: Interaction w/Other Transfer Paths: Contact Person: None With Path 55 at 1915MW simultaneous with Path 75 (Hemingway-Summer lake 500kV) at 550MW (W-E), post-transient reactive margin at Brownlee/Boise Bench 230kV buses is constraining/limiting for loss of the Hemingway-Summer Lake 500kV line. Mark D. Hanson Idaho Power Company 1221 W. Idaho P. O. Box 70 Boise, ID 83707-0070 (208) 388-2253 (208) 388-6647 - fax mhanson@idahopower.com Larry Frick PacifiCorp, Transmission Planning Lloyd Center Room 1800 825 NE Multnomah Portland, OR 97232 (503) 813-6236 (503) 813-6508 - fax Larry.Frick@PacifiCorp.com PART VI Item 1-207
- Page 165 and 166: 56. Deleted February 1999 INTENTION
- Page 167 and 168: Revised February 2003 58. Eldorado
- Page 169 and 170: Revised February 2003 59. WALC Blyt
- Page 171 and 172: Revised February 2003 60. Inyo - Co
- Page 173 and 174: Revised February 2003 61. Lugo - Vi
- Page 175 and 176: 62. Eldorado - McCullough 500 kV Li
- Page 177 and 178: 63. Deleted January 2011 INTENTIONA
- Page 179 and 180: Revised February 1998 65. Pacific D
- Page 181 and 182: Revised February 1998 Study Criteri
- Page 183 and 184: 66. COI Revised January 2013 PART V
- Page 185 and 186: Revised January 2013 Remedial Actio
- Page 187 and 188: 68. Deleted February 1999 INTENTION
- Page 189 and 190: 70. Deleted February 1999 INTENTION
- Page 191 and 192: 71. South of Allston Revised Januar
- Page 193 and 194: 72. Deleted February 1999 INTENTION
- Page 195 and 196: 73. North of John Day Revised Decem
- Page 197 and 198: 74. Deleted February 1999 INTENTION
- Page 199 and 200: Revised January 2013 75. Hemingway
- Page 201 and 202: 76. Alturas Project Revised Februar
- Page 203 and 204: Revised February 2002 Contact Perso
- Page 205 and 206: 77. Crystal - Harry Allen Revised N
- Page 207 and 208: 78. TOT 2B1 Revised January 2013 Ac
- Page 209 and 210: 79. TOT 2B2 Revised January 2013 Ac
- Page 211 and 212: 80. Montana Southeast Revised Janua
- Page 213 and 214: 81. Centennial Revised November 200
- Page 215: 82. TotBeast Revised January 2013 P
- Page 219 and 220: III-1. Devers-Palo Verde #2 Path 49
- Page 221 and 222: Revised November 2007 System Condit
- Page 223 and 224: Revised November 2007 III-2. Palo V
- Page 225 and 226: Updated November 2007 III-3. Montan
- Page 227 and 228: simultaneous analysis, only heavy s
- Page 229 and 230: III-4. Path C (Post Gateway) Revise
- Page 231 and 232: Revised January 2011 Interaction w/
- Page 233 and 234: III-5. Aeolus South Project Added J
- Page 235 and 236: Added January 2013 III-6. Aeolus We
- Page 237 and 238: Added January 2013 III-7. Bridger/A
- Page 239 and 240: III-9. TOT 4A (Pre-Gateway) Revised
- Page 241 and 242: Contact Person: Craig Quist PacifiC
- Page 243 and 244: Added January 2013 III-10. TOT 4A (
- Page 245 and 246: III-11. TOT 4B (Pre-Gateway) Revise
- Page 247 and 248: Operating operating agent and uses
- Page 249 and 250: III-12. SunZia Southwest Transmissi
- Page 251 and 252: Contact Person Mark L. Etherton, P.
- Page 253 and 254: Revised January 2013 Formal Operati
- Page 255 and 256: Revised January 2013 Allocation: In
- Page 257 and 258: January 2013 III-15. TotBeast with
- Page 259 and 260: January 2013 III-16. Idaho to North
- Page 261 and 262: January 2013 Study Criteria: Remedi
- Page 263 and 264: Revised January 2013 III-17. TOT3 A
- Page 265 and 266: Remedial Actions Required: Formal O
82. TotBeast<br />
Revised January <strong>2013</strong><br />
Accepted <strong>Rating</strong><br />
Existing <strong>Rating</strong><br />
Other<br />
Location:<br />
Definition:<br />
Transfer Limit:<br />
Critical<br />
Disturbance<br />
that limits the<br />
transfer<br />
capability:<br />
When:<br />
System<br />
Conditions:<br />
Study Criteria:<br />
Remedial<br />
Actions<br />
Required:<br />
Southwest Idaho and Eastern Oregon/Washington and Northern Idaho<br />
Sum of the flows on the following lines:<br />
Line<br />
Metered End<br />
Summer Lake - Hemingway 500 kV<br />
Hemingway<br />
Brownlee-Boise Bench #1 230 kV<br />
Brownlee<br />
Brownlee-Boise Bench #2 230 kV<br />
Brownlee<br />
Brownlee-Boise Bench #3 230 kV<br />
Brownlee<br />
Brownlee-Horse Flat #4 230 kV<br />
Brownlee<br />
Brownlee-Ontario 230kV<br />
Brownlee<br />
Oxbow-Starkey 138kV<br />
Oxbow<br />
Quartz-Ontario 138kV<br />
Quartz<br />
West to East: 2465 MW<br />
1915 MW Brownlee East (<strong>Path</strong> 55)<br />
550 MW Hemingway-Summer Lake 500 kV (<strong>Path</strong> 75)<br />
Post transient reactive margin at the Boise Bench 230kV following the loss of<br />
the Hemingway-Summer Lake 500kV line, or the loss of two Jim Bridger<br />
lines with tripping of two Jim Bridger Units, or the loss of two Brownlee-<br />
Boise Bench 230kV lines. Thermal limits on the remaining two Brownlee-<br />
Boise Bench 230kV lines for loss of the other two lines.<br />
The thermal overload of the Lolo-Oxbow 230kV line is the limiting condition<br />
for an outage of the Hemingway-Summer Lake 500kV line.<br />
This is an expanded version of the Brownlee East path (#55) that now also<br />
includes the Hemingway-Summer Lake path (#75) in its West to East<br />
direction.<br />
As this is only a combined rating of the other two paths which already have<br />
“accepted” ratings; study results supporting this path’s “other” rating are<br />
based on rating / OTC studies performed on the two component paths.<br />
A description of the rating history of each of the two paths can be found in<br />
the corresponding section for each path in this path catalog.<br />
The 2465 MW west to east transfer rating on TotBeast was studied with high<br />
imports on Idaho-Northwest (<strong>Path</strong> 14) , Brownlee East (<strong>Path</strong> 55) flows<br />
(1915MW) simultaneous with -550MW on the Hemingway-Summer Lake<br />
500kV line (<strong>Path</strong> 75), high T E Roach Complex generation at peak summer<br />
load conditions. This generally coincides with high hydro conditions in the<br />
Northwest with low to moderate eastern thermal resources.<br />
NERC/WECC Reliability Criteria For Transmission System Planning<br />
At high flows east of Brownlee, the loss of two Brownlee-Boise Bench<br />
230kV lines requires overload mitigation measure of bypassing ½ series<br />
compensation in the remaining two Brownlee-Boise Bench 230kV lines.<br />
PART VI Item 1-206