Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council
Remedial Actions Required: Formal Operating Procedure: None Operating procedures developed jointly by Nevada Power Company, Western Area Power Administration and the Mead-Phoenix Participants for interconnection of Harry Allen-Mead 500kV line (HAM). Included defining of the HAM System Operating Limit (SOL) and mitigations to maintain it: usage of Crystal and Perkins PST and tripping of the HAM line Allocation: Nevada Power Company: 100%. Interaction w/Other Transfer Paths: Contact Person: Alex Fratkin Nevada Power Company, MS S3B40 6100 Neil Road Reno, NV 89511 (775) 834-4897 (775) 834-3047 – fax e-mail address: afratkin@nvenergy.com PART VI Item 1-204
82. TotBeast Revised January 2013 PART VI Item 1-205
- Page 163 and 164: 55. Brownlee East Revised January 2
- Page 165 and 166: 56. Deleted February 1999 INTENTION
- Page 167 and 168: Revised February 2003 58. Eldorado
- Page 169 and 170: Revised February 2003 59. WALC Blyt
- Page 171 and 172: Revised February 2003 60. Inyo - Co
- Page 173 and 174: Revised February 2003 61. Lugo - Vi
- Page 175 and 176: 62. Eldorado - McCullough 500 kV Li
- Page 177 and 178: 63. Deleted January 2011 INTENTIONA
- Page 179 and 180: Revised February 1998 65. Pacific D
- Page 181 and 182: Revised February 1998 Study Criteri
- Page 183 and 184: 66. COI Revised January 2013 PART V
- Page 185 and 186: Revised January 2013 Remedial Actio
- Page 187 and 188: 68. Deleted February 1999 INTENTION
- Page 189 and 190: 70. Deleted February 1999 INTENTION
- Page 191 and 192: 71. South of Allston Revised Januar
- Page 193 and 194: 72. Deleted February 1999 INTENTION
- Page 195 and 196: 73. North of John Day Revised Decem
- Page 197 and 198: 74. Deleted February 1999 INTENTION
- Page 199 and 200: Revised January 2013 75. Hemingway
- Page 201 and 202: 76. Alturas Project Revised Februar
- Page 203 and 204: Revised February 2002 Contact Perso
- Page 205 and 206: 77. Crystal - Harry Allen Revised N
- Page 207 and 208: 78. TOT 2B1 Revised January 2013 Ac
- Page 209 and 210: 79. TOT 2B2 Revised January 2013 Ac
- Page 211 and 212: 80. Montana Southeast Revised Janua
- Page 213: 81. Centennial Revised November 200
- Page 217 and 218: Revised January 2013 Formal Operati
- Page 219 and 220: III-1. Devers-Palo Verde #2 Path 49
- Page 221 and 222: Revised November 2007 System Condit
- Page 223 and 224: Revised November 2007 III-2. Palo V
- Page 225 and 226: Updated November 2007 III-3. Montan
- Page 227 and 228: simultaneous analysis, only heavy s
- Page 229 and 230: III-4. Path C (Post Gateway) Revise
- Page 231 and 232: Revised January 2011 Interaction w/
- Page 233 and 234: III-5. Aeolus South Project Added J
- Page 235 and 236: Added January 2013 III-6. Aeolus We
- Page 237 and 238: Added January 2013 III-7. Bridger/A
- Page 239 and 240: III-9. TOT 4A (Pre-Gateway) Revised
- Page 241 and 242: Contact Person: Craig Quist PacifiC
- Page 243 and 244: Added January 2013 III-10. TOT 4A (
- Page 245 and 246: III-11. TOT 4B (Pre-Gateway) Revise
- Page 247 and 248: Operating operating agent and uses
- Page 249 and 250: III-12. SunZia Southwest Transmissi
- Page 251 and 252: Contact Person Mark L. Etherton, P.
- Page 253 and 254: Revised January 2013 Formal Operati
- Page 255 and 256: Revised January 2013 Allocation: In
- Page 257 and 258: January 2013 III-15. TotBeast with
- Page 259 and 260: January 2013 III-16. Idaho to North
- Page 261 and 262: January 2013 Study Criteria: Remedi
- Page 263 and 264: Revised January 2013 III-17. TOT3 A
Remedial<br />
Actions<br />
Required:<br />
Formal<br />
Operating<br />
Procedure:<br />
None<br />
Operating procedures developed jointly by Nevada Power Company, <strong>Western</strong><br />
Area Power Administration and the Mead-Phoenix Participants for<br />
interconnection of Harry Allen-Mead 500kV line (HAM). Included defining<br />
of the HAM System Operating Limit (SOL) and mitigations to maintain it:<br />
usage of Crystal and Perkins PST and tripping of the HAM line<br />
Allocation: Nevada Power Company: 100%.<br />
Interaction<br />
w/Other<br />
Transfer <strong>Path</strong>s:<br />
Contact Person:<br />
Alex Fratkin<br />
Nevada Power Company, MS S3B40<br />
6100 Neil Road<br />
Reno, NV 89511<br />
(775) 834-4897<br />
(775) 834-3047 – fax<br />
e-mail address:<br />
afratkin@nvenergy.com<br />
PART VI Item 1-204