Path Rating Catalog 2013 - Western Electricity Coordinating Council

Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council

12.11.2014 Views

77. Crystal - Harry Allen Revised November 2007 PART VI Item 1-194

77. Crystal – Harry Allen Revised November 2007 Accepted Rating Existing Rating Other Location: Definition: Southern Nevada Sum of the flows on the two 500/230 kV transformer banks at Crystal switching station, metered at the 500 kV bus. Transfer Limit: Crystal to Harry Allen: 950 MW Harry Allen to Crystal: Not defined Critical Disturbance that limits the transfer capability: When: System Conditions: Study Criteria: Remedial Actions Required: Formal Operating Procedure: Allocation: Interaction w/Other Transfer Paths: Contact Person: Under conditions of maximum transfers from Harry Allen into the Las Vegas Valley (i.e., all resources feeding into the Harry Allen substation at rated capacity - Reid Gardner 1-4, H. Allen 3, Red Butte-Harry Allen 345 kV and Crystal at 950 MW) the Pecos 230/138 kV autotransformers will be loaded to a level where loss of the #3 or #4 bank will load the #1 bank to its emergency rating (275.1 MVA). The Crystal Transmission Project Phase 2 Review Group Report published in February 1999 established the rating for the project. PCC formally approved this rating in April 1999. The Crystal-Allen 950 MW rating has been evaluated under peak summer load conditions under maximum southern Nevada imports, and under heavy autumn conditions with maximum EOR or WOR path flows. WECC and Nevada Power Company Reliability Criteria for System Design None Operating and Clearance Procedures, Nevada Power Company - Crystal Substation 500/230 kV, dated December 7, 1998. The transfer capability is wholly owned by Nevada Power Company. The Crystal progress report identified an interaction between the EOR and WOR transfer paths. There is also an interaction with the Red Butte-H. Allen 345 kV line (TOT2C path) due to the Crystal and H. Allen phase shifter interrelationship. Edi Von Engeln NV Energy 6100 Neil Road, M/S S3B40 Reno, Nevada 89511 (775) 834-4456 (775) 834-3047 - fax evonengeln@nvenergy.com PART VI Item 1-195

77. Crystal – Harry Allen<br />

Revised November 2007<br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Location:<br />

Definition:<br />

Southern Nevada<br />

Sum of the flows on the two 500/230 kV transformer banks at Crystal<br />

switching station, metered at the 500 kV bus.<br />

Transfer Limit: Crystal to Harry Allen: 950 MW<br />

Harry Allen to Crystal: Not defined<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

When:<br />

System<br />

Conditions:<br />

Study Criteria:<br />

Remedial<br />

Actions<br />

Required:<br />

Formal<br />

Operating<br />

Procedure:<br />

Allocation:<br />

Interaction<br />

w/Other<br />

Transfer <strong>Path</strong>s:<br />

Contact Person:<br />

Under conditions of maximum transfers from Harry Allen into the Las Vegas<br />

Valley (i.e., all resources feeding into the Harry Allen substation at rated<br />

capacity - Reid Gardner 1-4, H. Allen 3, Red Butte-Harry Allen 345 kV and<br />

Crystal at 950 MW) the Pecos 230/138 kV autotransformers will be loaded to<br />

a level where loss of the #3 or #4 bank will load the #1 bank to its emergency<br />

rating (275.1 MVA).<br />

The Crystal Transmission Project Phase 2 Review Group Report published in<br />

February 1999 established the rating for the project. PCC formally approved<br />

this rating in April 1999.<br />

The Crystal-Allen 950 MW rating has been evaluated under peak summer<br />

load conditions under maximum southern Nevada imports, and under heavy<br />

autumn conditions with maximum EOR or WOR path flows.<br />

WECC and Nevada Power Company Reliability Criteria for System Design<br />

None<br />

Operating and Clearance Procedures, Nevada Power Company - Crystal<br />

Substation 500/230 kV, dated December 7, 1998.<br />

The transfer capability is wholly owned by Nevada Power Company.<br />

The Crystal progress report identified an interaction between the EOR and<br />

WOR transfer paths. There is also an interaction with the Red Butte-H. Allen<br />

345 kV line (TOT2C path) due to the Crystal and H. Allen phase shifter<br />

interrelationship.<br />

Edi Von Engeln<br />

NV Energy<br />

6100 Neil Road, M/S S3B40<br />

Reno, Nevada 89511<br />

(775) 834-4456<br />

(775) 834-3047 - fax<br />

evonengeln@nvenergy.com<br />

PART VI Item 1-195

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!