Path Rating Catalog 2013 - Western Electricity Coordinating Council
Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council
77. Crystal - Harry Allen Revised November 2007 PART VI Item 1-194
77. Crystal – Harry Allen Revised November 2007 Accepted Rating Existing Rating Other Location: Definition: Southern Nevada Sum of the flows on the two 500/230 kV transformer banks at Crystal switching station, metered at the 500 kV bus. Transfer Limit: Crystal to Harry Allen: 950 MW Harry Allen to Crystal: Not defined Critical Disturbance that limits the transfer capability: When: System Conditions: Study Criteria: Remedial Actions Required: Formal Operating Procedure: Allocation: Interaction w/Other Transfer Paths: Contact Person: Under conditions of maximum transfers from Harry Allen into the Las Vegas Valley (i.e., all resources feeding into the Harry Allen substation at rated capacity - Reid Gardner 1-4, H. Allen 3, Red Butte-Harry Allen 345 kV and Crystal at 950 MW) the Pecos 230/138 kV autotransformers will be loaded to a level where loss of the #3 or #4 bank will load the #1 bank to its emergency rating (275.1 MVA). The Crystal Transmission Project Phase 2 Review Group Report published in February 1999 established the rating for the project. PCC formally approved this rating in April 1999. The Crystal-Allen 950 MW rating has been evaluated under peak summer load conditions under maximum southern Nevada imports, and under heavy autumn conditions with maximum EOR or WOR path flows. WECC and Nevada Power Company Reliability Criteria for System Design None Operating and Clearance Procedures, Nevada Power Company - Crystal Substation 500/230 kV, dated December 7, 1998. The transfer capability is wholly owned by Nevada Power Company. The Crystal progress report identified an interaction between the EOR and WOR transfer paths. There is also an interaction with the Red Butte-H. Allen 345 kV line (TOT2C path) due to the Crystal and H. Allen phase shifter interrelationship. Edi Von Engeln NV Energy 6100 Neil Road, M/S S3B40 Reno, Nevada 89511 (775) 834-4456 (775) 834-3047 - fax evonengeln@nvenergy.com PART VI Item 1-195
- Page 153 and 154: 51. Southern Navajo Revised Februar
- Page 155 and 156: Revised December 2010 Contact Perso
- Page 157 and 158: Revised February 2003 52. Silver Pe
- Page 159 and 160: 53. Deleted March 2007 INTENTIONALL
- Page 161 and 162: Revised December 2010 54. Coronado-
- Page 163 and 164: 55. Brownlee East Revised January 2
- Page 165 and 166: 56. Deleted February 1999 INTENTION
- Page 167 and 168: Revised February 2003 58. Eldorado
- Page 169 and 170: Revised February 2003 59. WALC Blyt
- Page 171 and 172: Revised February 2003 60. Inyo - Co
- Page 173 and 174: Revised February 2003 61. Lugo - Vi
- Page 175 and 176: 62. Eldorado - McCullough 500 kV Li
- Page 177 and 178: 63. Deleted January 2011 INTENTIONA
- Page 179 and 180: Revised February 1998 65. Pacific D
- Page 181 and 182: Revised February 1998 Study Criteri
- Page 183 and 184: 66. COI Revised January 2013 PART V
- Page 185 and 186: Revised January 2013 Remedial Actio
- Page 187 and 188: 68. Deleted February 1999 INTENTION
- Page 189 and 190: 70. Deleted February 1999 INTENTION
- Page 191 and 192: 71. South of Allston Revised Januar
- Page 193 and 194: 72. Deleted February 1999 INTENTION
- Page 195 and 196: 73. North of John Day Revised Decem
- Page 197 and 198: 74. Deleted February 1999 INTENTION
- Page 199 and 200: Revised January 2013 75. Hemingway
- Page 201 and 202: 76. Alturas Project Revised Februar
- Page 203: Revised February 2002 Contact Perso
- Page 207 and 208: 78. TOT 2B1 Revised January 2013 Ac
- Page 209 and 210: 79. TOT 2B2 Revised January 2013 Ac
- Page 211 and 212: 80. Montana Southeast Revised Janua
- Page 213 and 214: 81. Centennial Revised November 200
- Page 215 and 216: 82. TotBeast Revised January 2013 P
- Page 217 and 218: Revised January 2013 Formal Operati
- Page 219 and 220: III-1. Devers-Palo Verde #2 Path 49
- Page 221 and 222: Revised November 2007 System Condit
- Page 223 and 224: Revised November 2007 III-2. Palo V
- Page 225 and 226: Updated November 2007 III-3. Montan
- Page 227 and 228: simultaneous analysis, only heavy s
- Page 229 and 230: III-4. Path C (Post Gateway) Revise
- Page 231 and 232: Revised January 2011 Interaction w/
- Page 233 and 234: III-5. Aeolus South Project Added J
- Page 235 and 236: Added January 2013 III-6. Aeolus We
- Page 237 and 238: Added January 2013 III-7. Bridger/A
- Page 239 and 240: III-9. TOT 4A (Pre-Gateway) Revised
- Page 241 and 242: Contact Person: Craig Quist PacifiC
- Page 243 and 244: Added January 2013 III-10. TOT 4A (
- Page 245 and 246: III-11. TOT 4B (Pre-Gateway) Revise
- Page 247 and 248: Operating operating agent and uses
- Page 249 and 250: III-12. SunZia Southwest Transmissi
- Page 251 and 252: Contact Person Mark L. Etherton, P.
- Page 253 and 254: Revised January 2013 Formal Operati
77. Crystal – Harry Allen<br />
Revised November 2007<br />
Accepted <strong>Rating</strong><br />
Existing <strong>Rating</strong><br />
Other<br />
Location:<br />
Definition:<br />
Southern Nevada<br />
Sum of the flows on the two 500/230 kV transformer banks at Crystal<br />
switching station, metered at the 500 kV bus.<br />
Transfer Limit: Crystal to Harry Allen: 950 MW<br />
Harry Allen to Crystal: Not defined<br />
Critical<br />
Disturbance<br />
that limits the<br />
transfer<br />
capability:<br />
When:<br />
System<br />
Conditions:<br />
Study Criteria:<br />
Remedial<br />
Actions<br />
Required:<br />
Formal<br />
Operating<br />
Procedure:<br />
Allocation:<br />
Interaction<br />
w/Other<br />
Transfer <strong>Path</strong>s:<br />
Contact Person:<br />
Under conditions of maximum transfers from Harry Allen into the Las Vegas<br />
Valley (i.e., all resources feeding into the Harry Allen substation at rated<br />
capacity - Reid Gardner 1-4, H. Allen 3, Red Butte-Harry Allen 345 kV and<br />
Crystal at 950 MW) the Pecos 230/138 kV autotransformers will be loaded to<br />
a level where loss of the #3 or #4 bank will load the #1 bank to its emergency<br />
rating (275.1 MVA).<br />
The Crystal Transmission Project Phase 2 Review Group Report published in<br />
February 1999 established the rating for the project. PCC formally approved<br />
this rating in April 1999.<br />
The Crystal-Allen 950 MW rating has been evaluated under peak summer<br />
load conditions under maximum southern Nevada imports, and under heavy<br />
autumn conditions with maximum EOR or WOR path flows.<br />
WECC and Nevada Power Company Reliability Criteria for System Design<br />
None<br />
Operating and Clearance Procedures, Nevada Power Company - Crystal<br />
Substation 500/230 kV, dated December 7, 1998.<br />
The transfer capability is wholly owned by Nevada Power Company.<br />
The Crystal progress report identified an interaction between the EOR and<br />
WOR transfer paths. There is also an interaction with the Red Butte-H. Allen<br />
345 kV line (TOT2C path) due to the Crystal and H. Allen phase shifter<br />
interrelationship.<br />
Edi Von Engeln<br />
NV Energy<br />
6100 Neil Road, M/S S3B40<br />
Reno, Nevada 89511<br />
(775) 834-4456<br />
(775) 834-3047 - fax<br />
evonengeln@nvenergy.com<br />
PART VI Item 1-195