75. Hemingway – Summer Lake<br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Location:<br />

Definition:<br />

Transfer Limit:<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

When:<br />

Southwest Idaho and eastern Oregon<br />

Hemingway-Summer Lake 500 kV metered at the Hemingway 500 kV.<br />

Note: The path is also within <strong>Path</strong> 14 Idaho-Northwest.<br />

East to West: 1500 MW<br />

West to East: 550 MW<br />

East to West: Thermal overload on the Walla Walla 230 kV series capacitor<br />

following the loss of the Hemmingway – Summer Lake 500 kV line.<br />

West to East: The thermal overload of the Lolo-Oxbow 230 kV line is the<br />

limiting condition for an outage of the Hemingway-Summer Lake 500 kV<br />

line. The path is also limited by a reactive margin in the northwest for a<br />

double Palo Verde unit outage.<br />

The east to west rating is limited by thermal ratings of Midpoint 345/500 kV<br />

transformer and series capacitor in the line. It was established along with the<br />

2400 MW east to west rating of Idaho to Northwest path in August, 1989 with<br />

the publication of Idaho Power Company to Pacific Northwest Intertie<br />

Capacity Study. The WECC Notification Procedures for Changes in Facility<br />

<strong>Rating</strong> and/or Operating Procedures was followed.<br />

The east to west rating was conducted jointly by:<br />

Bonneville Power Administration (BPA)<br />

Idaho Power Company (IPCO)<br />

PacifiCorp (PAC)<br />

Avista Corp. (AVA)<br />

The 550 west to east rating is based on path studies completed in 2009. Phase<br />

3 status was granted on July 22, 2009<br />

Midpoint-Summer Lake was redefined to Hemingway-Summer Lake in 2010<br />

due to addition of the Hemingway 500/230 kV substation.<br />

PART VI Item 1-189