71. South of Allston<br />
Revised January <strong>2013</strong><br />
Accepted <strong>Rating</strong><br />
Existing <strong>Rating</strong><br />
Other<br />
Location:<br />
Definition:<br />
Transfer Limit:<br />
Critical<br />
Disturbance<br />
that limits the<br />
transfer<br />
capability:<br />
When:<br />
System<br />
Conditions:<br />
Study Criteria:<br />
Remedial<br />
Actions<br />
Required:<br />
Formal<br />
Operating<br />
Procedure:<br />
Allocation:<br />
Interaction<br />
w/Other<br />
Transfer <strong>Path</strong>s:<br />
Southwestern Washington/Northwestern Oregon<br />
Sum of the flows on the following lines:<br />
Line Owner Metered End<br />
Clatsop 230/115 kV BPA Clatsop<br />
Allston-Keeler 500 kV BPA Allston<br />
Allston-Rainier 115 kV BPA Allston<br />
Astoria Tap-Seaside 115 kV PAC Astoria Tap<br />
Merwin-View 115 kV PAC Merwin<br />
Trojan-Rivergate 230 kV PGE Trojan<br />
Trojan-St Marys 230 kV PGE Trojan<br />
Woodland Tap-Ross 230 kV BPA Ross<br />
Currently, per DSO 309, the SOL in the north to south direction is a dynamic<br />
limit and varies between 2935 and 3980 MW.<br />
The SOL in the south to north direction is a dynamic limit that adjusts in real<br />
time and the limit is 1115 MW.<br />
Allston-Keeler 500 kV line<br />
Keeler-Pearl 500 kV line<br />
Trojan-Rivergate 230 kV and Trojan-St Marys 230 kV line<br />
Allston-Trojan #1 and #2 230 kV lines<br />
Trojan –St Marys 230 kV and St Marys-Keeler 230 kV lines<br />
The path is limited for outages that cause thermal overloads<br />
SOL studies are completed on an annual basis.<br />
Heavy summer loadings<br />
Canada - NW – high north to south flow<br />
California - Oregon Intertie – high north to south flow<br />
Pacific DC Intertie – high north to south flow<br />
Upper Columbia generation high<br />
Lower Columbia generation low<br />
I-5 Corridor generation high<br />
BPA, PGE, PAC and WECC/NERC<br />
Generation dropping on available I-5 corridor thermal generation (Chehalis,<br />
Big Hanaford, and Fredrickson. Grays Harbor, Mint Farm, and Beaver)<br />
Generation ramping on Lewis River (Swift and Yale)<br />
Generation dropping in B.C. Hydro<br />
Generation dropping on Upper Columbia (Coulee and Chief Joseph)<br />
BPA Dispatcher Standing Order No. 309 (updated seasonally)<br />
All of the Capacity is allocated to BPA, PAC and PGE.<br />
None<br />