Path Rating Catalog 2013 - Western Electricity Coordinating Council

Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council

12.11.2014 Views

55. Brownlee East Revised January 2013 PART VI Item 1-152

55. Brownlee East Revised January 2013 Accepted Rating Existing Rating Other Location: Definition: Transfer Limit: Southwest Idaho The transfer path is comprised of the following lines: Line Brownlee-Boise Bench #1 230 kV Brownlee-Boise Bench #2 230 kV Brownlee-Boise Bench #3 230 kV Brownlee-Horse Flat #4 230 kV Brownlee-Ontario 230 kV Oxbow-Starkey 138 kV Quartz-Ontario 138 kV West to East: 1915 MW Metered End Brownlee Brownlee Brownlee Brownlee Brownlee Oxbow Quartz Critical Disturbance that limits the transfer capability: When: System Conditions: East to West: Not defined. However, this transfer path does not restrict east to west transfers through Idaho. Post transient reactive margin at the Boise Bench 230 kV following the loss of the Midpoint-Summer Lake 500 kV line, or the loss of two Jim Bridger 345 kV lines with tripping of two Jim Bridger units, or the loss of two Brownlee-Boise Bench 230 kV lines. Thermal limits on the remaining two Brownlee-Boise Bench 230 kV lines for loss of the other two lines. In 1983, the Brownlee East transfer limit was established by Idaho Power Company and was revised in 1986 when the Northwest to Idaho transfer limit was restudied. After the July 2 and 3, 1996 disturbances, the Brownlee East transfer limit was restricted to 1560 MW. After the completion of the Brownlee-Boise Bench 230kV Project in 2001, the Brownlee East transmission path attained an Accepted Rating of 1750 MW West to East. The accepted rating was increased to 1850 MW West to East for the summer of 2004 when the final phase of the project, which included the 2 nd Brownlee- Oxbow 230 kV circuit, was completed. Due to the addition of the Elkhorn Wind Generation Project, the Brownlee East transmission path rating was modestly increased again in 2008 to 1915 MW with the facility additions of Brownlee C232 75 Mvar 230 kV shunt capacitor bank and increasing the ampacity rating of Ontario C231 series capacitor in the Brownlee-Ontario 230 kV line. To support -550 MW Hemingway-Summer Lake 500 kV line (Path 75) transfer rating simultaneous with Brownlee East at 1915 MW, the Brownlee C232 230 kV shunt capacitor bank was increased to 112.5 Mvar. The Brownlee East transfer limit was studied with simultaneous high imports of -1200 MW on Idaho-Northwest (Path 14) with -550 MW on the Midpoint- Summer Lake 500 kV line (Path 75), and with high T E Roach Complex generation at peak summer load conditions. The total West-to-East flow on Brownlee East and Hemingway –Summer Lake 500 kV was studied with flows ranging from 2425 to 2465 MW. PART VI Item 1-153

55. Brownlee East<br />

Revised January <strong>2013</strong><br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Location:<br />

Definition:<br />

Transfer Limit:<br />

Southwest Idaho<br />

The transfer path is comprised of the following lines:<br />

Line<br />

Brownlee-Boise Bench #1 230 kV<br />

Brownlee-Boise Bench #2 230 kV<br />

Brownlee-Boise Bench #3 230 kV<br />

Brownlee-Horse Flat #4 230 kV<br />

Brownlee-Ontario 230 kV<br />

Oxbow-Starkey 138 kV<br />

Quartz-Ontario 138 kV<br />

West to East: 1915 MW<br />

Metered End<br />

Brownlee<br />

Brownlee<br />

Brownlee<br />

Brownlee<br />

Brownlee<br />

Oxbow<br />

Quartz<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

When:<br />

System<br />

Conditions:<br />

East to West: Not defined. However, this transfer path does not restrict east<br />

to west transfers through Idaho.<br />

Post transient reactive margin at the Boise Bench 230 kV following the loss<br />

of the Midpoint-Summer Lake 500 kV line, or the loss of two Jim Bridger<br />

345 kV lines with tripping of two Jim Bridger units, or the loss of two<br />

Brownlee-Boise Bench 230 kV lines. Thermal limits on the remaining two<br />

Brownlee-Boise Bench 230 kV lines for loss of the other two lines.<br />

In 1983, the Brownlee East transfer limit was established by Idaho Power<br />

Company and was revised in 1986 when the Northwest to Idaho transfer limit<br />

was restudied. After the July 2 and 3, 1996 disturbances, the Brownlee East<br />

transfer limit was restricted to 1560 MW. After the completion of the<br />

Brownlee-Boise Bench 230kV Project in 2001, the Brownlee East<br />

transmission path attained an Accepted <strong>Rating</strong> of 1750 MW West to East.<br />

The accepted rating was increased to 1850 MW West to East for the summer<br />

of 2004 when the final phase of the project, which included the 2 nd Brownlee-<br />

Oxbow 230 kV circuit, was completed.<br />

Due to the addition of the Elkhorn Wind Generation Project, the Brownlee<br />

East transmission path rating was modestly increased again in 2008 to 1915<br />

MW with the facility additions of Brownlee C232 75 Mvar 230 kV shunt<br />

capacitor bank and increasing the ampacity rating of Ontario C231 series<br />

capacitor in the Brownlee-Ontario 230 kV line. To support -550 MW<br />

Hemingway-Summer Lake 500 kV line (<strong>Path</strong> 75) transfer rating simultaneous<br />

with Brownlee East at 1915 MW, the Brownlee C232 230 kV shunt capacitor<br />

bank was increased to 112.5 Mvar.<br />

The Brownlee East transfer limit was studied with simultaneous high imports<br />

of -1200 MW on Idaho-Northwest (<strong>Path</strong> 14) with -550 MW on the Midpoint-<br />

Summer Lake 500 kV line (<strong>Path</strong> 75), and with high T E Roach Complex<br />

generation at peak summer load conditions. The total West-to-East flow on<br />

Brownlee East and Hemingway –Summer Lake 500 kV was studied with<br />

flows ranging from 2425 to 2465 MW.<br />

PART VI Item 1-153

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!