Path Rating Catalog 2013 - Western Electricity Coordinating Council
Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council
55. Brownlee East Revised January 2013 PART VI Item 1-152
55. Brownlee East Revised January 2013 Accepted Rating Existing Rating Other Location: Definition: Transfer Limit: Southwest Idaho The transfer path is comprised of the following lines: Line Brownlee-Boise Bench #1 230 kV Brownlee-Boise Bench #2 230 kV Brownlee-Boise Bench #3 230 kV Brownlee-Horse Flat #4 230 kV Brownlee-Ontario 230 kV Oxbow-Starkey 138 kV Quartz-Ontario 138 kV West to East: 1915 MW Metered End Brownlee Brownlee Brownlee Brownlee Brownlee Oxbow Quartz Critical Disturbance that limits the transfer capability: When: System Conditions: East to West: Not defined. However, this transfer path does not restrict east to west transfers through Idaho. Post transient reactive margin at the Boise Bench 230 kV following the loss of the Midpoint-Summer Lake 500 kV line, or the loss of two Jim Bridger 345 kV lines with tripping of two Jim Bridger units, or the loss of two Brownlee-Boise Bench 230 kV lines. Thermal limits on the remaining two Brownlee-Boise Bench 230 kV lines for loss of the other two lines. In 1983, the Brownlee East transfer limit was established by Idaho Power Company and was revised in 1986 when the Northwest to Idaho transfer limit was restudied. After the July 2 and 3, 1996 disturbances, the Brownlee East transfer limit was restricted to 1560 MW. After the completion of the Brownlee-Boise Bench 230kV Project in 2001, the Brownlee East transmission path attained an Accepted Rating of 1750 MW West to East. The accepted rating was increased to 1850 MW West to East for the summer of 2004 when the final phase of the project, which included the 2 nd Brownlee- Oxbow 230 kV circuit, was completed. Due to the addition of the Elkhorn Wind Generation Project, the Brownlee East transmission path rating was modestly increased again in 2008 to 1915 MW with the facility additions of Brownlee C232 75 Mvar 230 kV shunt capacitor bank and increasing the ampacity rating of Ontario C231 series capacitor in the Brownlee-Ontario 230 kV line. To support -550 MW Hemingway-Summer Lake 500 kV line (Path 75) transfer rating simultaneous with Brownlee East at 1915 MW, the Brownlee C232 230 kV shunt capacitor bank was increased to 112.5 Mvar. The Brownlee East transfer limit was studied with simultaneous high imports of -1200 MW on Idaho-Northwest (Path 14) with -550 MW on the Midpoint- Summer Lake 500 kV line (Path 75), and with high T E Roach Complex generation at peak summer load conditions. The total West-to-East flow on Brownlee East and Hemingway –Summer Lake 500 kV was studied with flows ranging from 2425 to 2465 MW. PART VI Item 1-153
- Page 111 and 112: Created on 8/10/10 TABLE 1-1A: TOT3
- Page 113 and 114: 37. TOT 4A Revised January 2012 Acc
- Page 115 and 116: PART VI Item 1-105
- Page 117 and 118: 38. TOT 4B Revised January 2012 Acc
- Page 119 and 120: WYOMING SYSTEM OPERATING CURVE SYST
- Page 121 and 122: 39. TOT 5 Revised January 2013 Acce
- Page 123 and 124: 40. TOT 7 Revised February 2003 PAR
- Page 125 and 126: Revised January 2006 Allocation: In
- Page 127 and 128: 41. Sylmar to SCE Revised February
- Page 129 and 130: 42. IID - SCE Revised February 2004
- Page 131 and 132: 43. North of San Onofre Revised Jan
- Page 133 and 134: 44. South of San Onofre Revised Feb
- Page 135 and 136: 45. SDG&E - CFE Revised December 20
- Page 137 and 138: Revised February 2003 46. West of C
- Page 139 and 140: Revised February 2007 Allocation: N
- Page 141 and 142: Revised January 2006 47. Southern N
- Page 143 and 144: Revised February 2007 48. Northern
- Page 145 and 146: Revised January 2010 Allocation: In
- Page 147 and 148: Revised January 2013 49. East of th
- Page 149 and 150: Revised January 2013 Utah Navajo Pa
- Page 151 and 152: 50. Cholla - Pinnacle Peak Revised
- Page 153 and 154: 51. Southern Navajo Revised Februar
- Page 155 and 156: Revised December 2010 Contact Perso
- Page 157 and 158: Revised February 2003 52. Silver Pe
- Page 159 and 160: 53. Deleted March 2007 INTENTIONALL
- Page 161: Revised December 2010 54. Coronado-
- Page 165 and 166: 56. Deleted February 1999 INTENTION
- Page 167 and 168: Revised February 2003 58. Eldorado
- Page 169 and 170: Revised February 2003 59. WALC Blyt
- Page 171 and 172: Revised February 2003 60. Inyo - Co
- Page 173 and 174: Revised February 2003 61. Lugo - Vi
- Page 175 and 176: 62. Eldorado - McCullough 500 kV Li
- Page 177 and 178: 63. Deleted January 2011 INTENTIONA
- Page 179 and 180: Revised February 1998 65. Pacific D
- Page 181 and 182: Revised February 1998 Study Criteri
- Page 183 and 184: 66. COI Revised January 2013 PART V
- Page 185 and 186: Revised January 2013 Remedial Actio
- Page 187 and 188: 68. Deleted February 1999 INTENTION
- Page 189 and 190: 70. Deleted February 1999 INTENTION
- Page 191 and 192: 71. South of Allston Revised Januar
- Page 193 and 194: 72. Deleted February 1999 INTENTION
- Page 195 and 196: 73. North of John Day Revised Decem
- Page 197 and 198: 74. Deleted February 1999 INTENTION
- Page 199 and 200: Revised January 2013 75. Hemingway
- Page 201 and 202: 76. Alturas Project Revised Februar
- Page 203 and 204: Revised February 2002 Contact Perso
- Page 205 and 206: 77. Crystal - Harry Allen Revised N
- Page 207 and 208: 78. TOT 2B1 Revised January 2013 Ac
- Page 209 and 210: 79. TOT 2B2 Revised January 2013 Ac
- Page 211 and 212: 80. Montana Southeast Revised Janua
55. Brownlee East<br />
Revised January <strong>2013</strong><br />
Accepted <strong>Rating</strong><br />
Existing <strong>Rating</strong><br />
Other<br />
Location:<br />
Definition:<br />
Transfer Limit:<br />
Southwest Idaho<br />
The transfer path is comprised of the following lines:<br />
Line<br />
Brownlee-Boise Bench #1 230 kV<br />
Brownlee-Boise Bench #2 230 kV<br />
Brownlee-Boise Bench #3 230 kV<br />
Brownlee-Horse Flat #4 230 kV<br />
Brownlee-Ontario 230 kV<br />
Oxbow-Starkey 138 kV<br />
Quartz-Ontario 138 kV<br />
West to East: 1915 MW<br />
Metered End<br />
Brownlee<br />
Brownlee<br />
Brownlee<br />
Brownlee<br />
Brownlee<br />
Oxbow<br />
Quartz<br />
Critical<br />
Disturbance<br />
that limits the<br />
transfer<br />
capability:<br />
When:<br />
System<br />
Conditions:<br />
East to West: Not defined. However, this transfer path does not restrict east<br />
to west transfers through Idaho.<br />
Post transient reactive margin at the Boise Bench 230 kV following the loss<br />
of the Midpoint-Summer Lake 500 kV line, or the loss of two Jim Bridger<br />
345 kV lines with tripping of two Jim Bridger units, or the loss of two<br />
Brownlee-Boise Bench 230 kV lines. Thermal limits on the remaining two<br />
Brownlee-Boise Bench 230 kV lines for loss of the other two lines.<br />
In 1983, the Brownlee East transfer limit was established by Idaho Power<br />
Company and was revised in 1986 when the Northwest to Idaho transfer limit<br />
was restudied. After the July 2 and 3, 1996 disturbances, the Brownlee East<br />
transfer limit was restricted to 1560 MW. After the completion of the<br />
Brownlee-Boise Bench 230kV Project in 2001, the Brownlee East<br />
transmission path attained an Accepted <strong>Rating</strong> of 1750 MW West to East.<br />
The accepted rating was increased to 1850 MW West to East for the summer<br />
of 2004 when the final phase of the project, which included the 2 nd Brownlee-<br />
Oxbow 230 kV circuit, was completed.<br />
Due to the addition of the Elkhorn Wind Generation Project, the Brownlee<br />
East transmission path rating was modestly increased again in 2008 to 1915<br />
MW with the facility additions of Brownlee C232 75 Mvar 230 kV shunt<br />
capacitor bank and increasing the ampacity rating of Ontario C231 series<br />
capacitor in the Brownlee-Ontario 230 kV line. To support -550 MW<br />
Hemingway-Summer Lake 500 kV line (<strong>Path</strong> 75) transfer rating simultaneous<br />
with Brownlee East at 1915 MW, the Brownlee C232 230 kV shunt capacitor<br />
bank was increased to 112.5 Mvar.<br />
The Brownlee East transfer limit was studied with simultaneous high imports<br />
of -1200 MW on Idaho-Northwest (<strong>Path</strong> 14) with -550 MW on the Midpoint-<br />
Summer Lake 500 kV line (<strong>Path</strong> 75), and with high T E Roach Complex<br />
generation at peak summer load conditions. The total West-to-East flow on<br />
Brownlee East and Hemingway –Summer Lake 500 kV was studied with<br />
flows ranging from 2425 to 2465 MW.<br />
PART VI Item 1-153