Path Rating Catalog 2013 - Western Electricity Coordinating Council

Path Rating Catalog 2013 - Western Electricity Coordinating Council Path Rating Catalog 2013 - Western Electricity Coordinating Council

12.11.2014 Views

37. TOT 4A Revised January 2012 PART VI Item 1-102

37. TOT 4A Revised January 2012 Accepted Rating Existing Rating Other Location: Definition: Southwest Wyoming Sum of the flows on the following transmission lines: Line Metered End Riverton-Wyopo 230 kV Riverton Miners-Platte 230 kV Miners Spence-Mustang 230 kV Spence Transfer Limit: Northeast to Southwest: 810 MW (Non-simultaneous) Southwest to Northeast: Not defined Critical Disturbance that limits the transfer capability: When: System Conditions: Study Criteria: Remedial Actions Required: Formal Operating Procedure: Allocation: Interaction w/Other Transfer Paths: Depending on flows on the adjacent TOT 4B path, the real-time rating can range between a minimum of 0 MW and a maximum of 810 MW (Reference attachment). Typically, the real-time rating centers around 650 MW. The critical disturbances and limiting elements vary with the various points on the nomogram. Reference attachment for further information. Phase 1/2 Rating Study Underway This rating is independent of transfer levels between major areas of WECC. Historically, the flows have all been northeast to southwest across the path. (Summary) System intact: • Per unit voltages between 0.95 p.u. and 1.05 p.u. • All lines and transformers loaded to less than continuous rating. Single contingency outage conditions: • Per unit voltages between 0.90 p.u. and 1.10 p.u. • All facilities loaded to less than 100% of emergency ratings. Remedial actions are required to achieve the rated transfer capability. Following an outage, all overloaded lines and transformers must have their loading reduced to continuous ratings within 15 minutes. This is accomplished by reducing schedules and adjusting generation. There is a formal operating procedure TBD. PAC is the operating agent and uses real-time flows to monitor the path. PAC has the entire transfer capability of the path. See attachment PART VI Item 1-103

37. TOT 4A<br />

Revised January 2012<br />

Accepted <strong>Rating</strong><br />

Existing <strong>Rating</strong><br />

Other<br />

Location:<br />

Definition:<br />

Southwest Wyoming<br />

Sum of the flows on the following transmission lines:<br />

Line<br />

Metered End<br />

Riverton-Wyopo 230 kV<br />

Riverton<br />

Miners-Platte 230 kV<br />

Miners<br />

Spence-Mustang 230 kV<br />

Spence<br />

Transfer Limit: Northeast to Southwest: 810 MW (Non-simultaneous)<br />

Southwest to Northeast: Not defined<br />

Critical<br />

Disturbance<br />

that limits the<br />

transfer<br />

capability:<br />

When:<br />

System<br />

Conditions:<br />

Study Criteria:<br />

Remedial<br />

Actions<br />

Required:<br />

Formal<br />

Operating<br />

Procedure:<br />

Allocation:<br />

Interaction<br />

w/Other<br />

Transfer <strong>Path</strong>s:<br />

Depending on flows on the adjacent TOT 4B path, the real-time rating can<br />

range between a minimum of 0 MW and a maximum of 810 MW (Reference<br />

attachment). Typically, the real-time rating centers around 650 MW.<br />

The critical disturbances and limiting elements vary with the various points<br />

on the nomogram. Reference attachment for further information.<br />

Phase 1/2 <strong>Rating</strong> Study Underway<br />

This rating is independent of transfer levels between major areas of WECC.<br />

Historically, the flows have all been northeast to southwest across the path.<br />

(Summary)<br />

System intact:<br />

• Per unit voltages between 0.95 p.u. and 1.05 p.u.<br />

• All lines and transformers loaded to less than continuous rating.<br />

Single contingency outage conditions:<br />

• Per unit voltages between 0.90 p.u. and 1.10 p.u.<br />

• All facilities loaded to less than 100% of emergency ratings.<br />

Remedial actions are required to achieve the rated transfer capability.<br />

Following an outage, all overloaded lines and transformers must have their<br />

loading reduced to continuous ratings within 15 minutes. This is<br />

accomplished by reducing schedules and adjusting generation.<br />

There is a formal operating procedure TBD. PAC is the operating agent and<br />

uses real-time flows to monitor the path.<br />

PAC has the entire transfer capability of the path.<br />

See attachment<br />

PART VI Item 1-103

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!