e/;kapy fo|qr forj.k fuxe fyfeVsM<br />
fo|qr forj.k [k.M & izFke] mUuko<br />
vYidkyhu fufonk lwpuk<br />
a<br />
a<br />
fo|qr forj.k [k.M izFke mUuko ds vUrxZr v/kksfyf[kr dk;ksaZ gsrq iathd`r] vuqHkoh] vk;dj ,oa lsokdj iathd`r Bsdsnkjks ls<br />
eqgjcUn fufonk;s vyx&vyx nks Hkkxksa es a] izFke Hkkx es /kjksgj /kujkf’k] vk;dj@lsokdj] iath;u izek.k i= ,oa vuqHko izek.k i= vkfn<br />
rFkk f}rh; Hkkx es fufofnr njsa] rduhdh fooj.k ,oa vU; fu;e o ‘krsZ gksa fufonk ds lEeq[k vafdr fufonk [kqyus dh frfFk dks 15%00<br />
cts rd vkeaf=r dh tkrh gSA fufonk;s mlh fnu 16%00 cts lkoZtfud #i ls mifLFkr fufonknkrkvks@muds izfrfuf/k;ks ds le{k [kksyh<br />
tk;sxhA izR;sd fufonk dk ewY; :0 230-00 ¼ O;kikj dj lfgr½ fu/kkZfjr gS] tks vizfrns; gSA<br />
dz0 fufonk la0 dk;Z dk fooj.k /kjksgj fufonk [kqyus dh frfFk<br />
la0<br />
/kujkf’k #0<br />
1 28@fofo[kizm<br />
@2013&14<br />
2 29@fofo[kizm<br />
@2013&14<br />
3 30@fofo[kizm<br />
@2013&14<br />
4 31@fofo[kizm<br />
@2013&14<br />
33@11 ds0oh0 fo|qr midsUnz flVh ikoj gkml+] mUuko ls fuxZr 11<br />
ds0oh0 iks”kdksa ,oa muls lEcfU/kr ,y0Vh0 ykbuksa rFkk midsUnzksa ds<br />
vuqj{k.k] rFkk ejEer] fo|qr foPNsnu iquZla;kstu ,oa miHkksDrkvksa dh<br />
f’kdk;rksa ds fuLrkj.k dk;Z gsrq dq’ky@vdq’ky Jfedksa dh 4 vnn xSax<br />
miyC/k djkus dk dk;ZA<br />
33@11 ds0oh0 fo|qr midsUnz iqjok+] mUuko ls fuxZr 11 ds0oh0 iks”kdksa<br />
,oa muls lEcfU/kr ,y0Vh0 ykbuksa rFkk midsUnzksa ds vuqj{k.k] rFkk<br />
ejEer] fo|qr foPNsnu iquZla;kstu ,oa miHkksDrkvksa dh f’kdk;rksa ds<br />
fuLrkj.k dk;Z gsrq dq’ky@vdq’ky Jfedksa dh 4 vnn xSax miyC/k djkus<br />
dk dk;ZA<br />
33@11 ds0oh0 fo|qr midsUnz ch?kkiqj+] mUuko ls fuxZr 11 ds0oh0 iks”kdksa<br />
,oa muls lEcfU/kr ,y0Vh0 ykbuksa rFkk midsUnzksa ds vuqj{k.k] rFkk<br />
ejEer] fo|qr foPNsnu iquZla;kstu ,oa miHkksDrkvksa dh f’kdk;rksa ds<br />
fuLrkj.k dk;Z gsrq dq’ky@vdq’ky Jfedksa dh 4 vnn xSax miyC/k djkus<br />
dk dk;ZA<br />
fo|qr forj.k mi[k.M r`rh;] mUuko ds dk;Z{ks= esa 33@11 ds0oh0 fo|qr<br />
midsUnz ch?kkiqj ds vUrZxr {kfrxzLr ifjorZdksa dks Mcy iksy@fIyaFk ls<br />
mrkjus] VªkUlQkjej odZ’kki mUuko rd igqpkus] u;s ifjorZdksa dks fo|qr<br />
Hk.Mkj dsUnz mUuko ls dk;ZLFky rd ys tkus ,oa Mcy iksy@fIyaFk ij<br />
p
Madhyanchal<br />
Vidyut Vitaran<br />
Nigam Limited<br />
Electricity Distribution<br />
Division-I, Unnao.<br />
<strong>Tender</strong> <strong>No</strong>. 28/EDD-IU/2013-14<br />
DATE OF OPENING:-26-08-2013
<strong>Tender</strong> proforma<br />
(to be filled by tenderer)<br />
Important instruction of the tenderer<br />
Your tender shall not be considered if you fail to submit this proforma duly filled up replies should be<br />
completed without ambiguity and should be clearly written against each item.<br />
(Attach extra sheets if the space-left not sufficient)<br />
Sl.<br />
<strong>No</strong><br />
PARTICULARS<br />
1- Specification <strong>No</strong>. against which your are tenderer<br />
2- Receipt <strong>No</strong>. & Date vide which cost of tender specification<br />
fees deposited by you.<br />
3- Name & Address of tenderer<br />
REPLIES<br />
4- Year since when the tenderer has started execution of work<br />
tender.<br />
5- Do you agree to all the conditions of the tender specification<br />
and if not State the modifications clearly which you desire in<br />
general conditions from A/B. it may Please be noted that it<br />
shall be entirely at the desecration of the undersigned to accept<br />
or reject the modification proposed)<br />
6- Account of earn money deposited with full details be<br />
submitted here<br />
7- Please state clearly (Yes/<strong>No</strong>) if you would accept the order of<br />
modification in the form A/B are not acceptable to the<br />
corporation without imposing further conditions form your<br />
side.<br />
8- Give two reference who can certify your financial status and<br />
capability to undertake execution of work/Supply. One of the<br />
reference should be of any scheduled Bank of India.<br />
9- Name & Detailed address of <strong>Tender</strong>er/ Proprietor/<br />
Partners/Director be given.<br />
<strong>10</strong> Statement of past/current experience in similar works in the<br />
following form:-<br />
Sl<br />
no<br />
Name & address of<br />
ordering authority<br />
Order/<br />
Contract<br />
<strong>No</strong>. & Date<br />
Particular of<br />
work<br />
executed<br />
Quantum of work<br />
Ordered Completed Remarks<br />
1 2 3 4 5 6 7<br />
11- What is the validity period of your tender.<br />
12- Place & Date
Signature of <strong>Tender</strong>er<br />
With seal<br />
MADHYANC<strong>HAL</strong> VIDYUT VITARAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
Date of opening:-26-08-2013<br />
<strong>Tender</strong> Specification <strong>No</strong>. 28/EDD-IU/2013-14<br />
SCHEDULE OF RATES & QUANTUM OF WORK FOR PROVIDING MAN POWER (GANG) AT 33/11<br />
KV SUB STATION CITY POWER HOUSE UNNAO.<br />
Sl.<br />
<strong>No</strong>.<br />
Particulars of Work Unit Qty<br />
Rate (Per Day/<br />
Per Labour)<br />
Amount (Per<br />
Day)<br />
Providing man power (gang) for attending break<br />
downs of H.T/L.T. Lines due to broken<br />
conductor, blown fuses, puncture insulators etc.<br />
attending consumers complaints and<br />
disconnection of defaulting consumers every day<br />
for 8 hours including Sunday and holyday as per<br />
detail given below.<br />
1- Skilled labour having I.T.I. Cirtificate in<br />
Electrician/Wireman trade.<br />
2- Unskilled labour having experience for<br />
maintenance of H.T. & L.T. Lines.<br />
Total<br />
For 6 MONTH<br />
<strong>No</strong>s. 4<br />
<strong>No</strong>s. 8<br />
Signature & seal of<br />
Contractor<br />
Executive Engineer<br />
EDD-I Unnao
MADHYANC<strong>HAL</strong> VIDYUT VITRAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
<strong>Tender</strong> <strong>No</strong>. 28 /EDD-IU/2013-14<br />
SPECIAL TERMS & CONDITIONS<br />
1- The works will be carried out by the Contractor during the Agreement period of Six month<br />
from the date of commencement, under Electricity Distribution Division-I, Unnao.<br />
2- The skilled labour to be provided by the Contractor shall have the educational qualification of<br />
intermediate with I.T.I certificate in Electrician trade.<br />
3- The Contractor shall have Registration with Labour Commissioner for Engaging Labour which<br />
should be valid at least for agreement period. The photo copy of registration certificate shall be<br />
produced by the Contractor before taking up the work in hand.<br />
4- The Contractor shall also be registered with E.P.F. Commissioner and he will have to deposit<br />
the amount of E.P.F. deducted by him from the monthly wages of his labour in the office of<br />
E.P.F. Commissioner every month and photocopy of the same will be produce to Executive<br />
Engineer, Electricity Distribution Division-I, Unnao accordingly.<br />
5- Apart from above, the Contactor shall also be required to get registered with concerning<br />
authorities of Central Excise duty and Service Tax in respect of his aforesaid labour.<br />
6- The payment of the Ex-gratia will also be made to his labour by the Contractor, if it is found<br />
payable as per labour Act/Rules.<br />
7- The Skilled and un-skilled labour being engaged by the Contractor shall, in no case, be entitled<br />
for regular service of the Corporation.<br />
8- All T&P required for proper completion of assigned work, shall be arranged and provided to<br />
his labour by the Contractor him self at his own cost. However, all the required stock materials/<br />
component for proper completion of work shall arranged & provided by the Department free of<br />
cost.<br />
9- The Contractor shall be fully responsible for arranging accidental insurance policy for the<br />
compensation of his working personnel, if required as the Corporation shall not be held<br />
responsible for any compensation to his Labour in the event of any accident/mishap<br />
whatsoever.<br />
<strong>10</strong>- The Contractor will be required to pay minimum wages (in shape of A/C payee Cheque) to the<br />
employees engaged by him for the said purpose according to the rates approved by the Labour<br />
Commissioner and also amendment, if any, from time to time and subsequent approval by the<br />
Chief Engineer, M.V.V.N.L Lucknow/works Committee.<br />
11- The Contractor will issue Character Certificate in respect of each Employees provided by him<br />
and he will be responsible for any mischief committed by any of his labour.<br />
12- The Contractor shall have to follow instructions of the Engineer in charge of the Sub-Station or<br />
his representative in respect of proper operation & maintenance of Sub-Station.<br />
13- The log sheet & other requisite registers & stationery as well as stock materials/spares<br />
required for attending break downs/maintenance shall be supplied by the department and the<br />
account of their consumption shall be given by the contractor to Engineer supervising the<br />
work.
14- 90 % payment will be made by concerned Executive Engineer against running bill subject to<br />
the availability of funds and <strong>10</strong>% amount will be detained as security which will be paid after<br />
the completion of works in satisfactory condition and after recommendation of concerned Subdivisional<br />
officer.<br />
15- <strong>No</strong> Experience Certificate will be issued by any Officer of the Corporation to any Employee of<br />
the Contractor.<br />
Cont.
(2)<br />
16- In addition to above all the general terms & conditions of contract for execution of works will<br />
governed as per Form-A.<br />
17- Income tax/other deductions as UPPCL/<strong>MVVNL</strong> rules shall be deducted from the Contractor<br />
bills as per State/Central Government rates prevailing in the Department.<br />
18- The Contractor shall confirm in respect to the requirement of Chief Electrical Inspector to U.P.<br />
Government as and when required by them in respect to Electrical Safety Rules and<br />
Regulation.<br />
19- <strong>No</strong> Compensation for idle labour shall be payable to the Contractor in any circumstances. The<br />
compensation owning to accident/ incident during execution of work shall be paid by the<br />
Contractor at his own without any reference to UPPCL/<strong>MVVNL</strong> and constitutional obligation<br />
for such compensation shall be sole responsibility of the contractor.<br />
20- The damage, if any, caused loss to the department/work/ T&P by the Contractor him self or his<br />
staff shall be recovered in full from the pending bill(s)/ liability of the Contractor.<br />
21- The Superintending Engineer, Electricity Distribution Circle, Unnao will be the principal<br />
employer of the contract and the Concerned Executive Engineer shall function as Engineer-incharge<br />
of the contract. The work shall be carried out as per rules by the Contractor in strict<br />
supervision and to the entire satisfaction of Engineer-in-charge of the Division.<br />
22- All the terms & Conditions of the Labour act will be adhered to strictly by the contractor.<br />
23- The dispute arising, if any, taken into Court, shall be within the Jurisdiction of Unnao.<br />
24- The contract shall have to issue identity card to his employees engaged for the said purpose.<br />
Executive Engineer<br />
Electricity Distribution Division-I<br />
Unnao
Madhyanchal<br />
Vidyut Vitaran<br />
Nigam Limited<br />
Electricity Distribution<br />
Division-I, Unnao.<br />
<strong>Tender</strong> <strong>No</strong>. 29/EDD-IU/2013-14<br />
DATE OF OPENING:-26-08-2013
<strong>Tender</strong> proforma<br />
(to be filled by tenderer)<br />
Important instruction of the tenderer<br />
Your tender shall not be considered if you fail to submit this proforma duly filled up replies should be<br />
completed without ambiguity and should be clearly written against each item.<br />
(Attach extra sheets if the space-left not sufficient)<br />
Sl.<br />
<strong>No</strong><br />
PARTICULARS<br />
1- Specification <strong>No</strong>. against which your are tenderer<br />
2- Receipt <strong>No</strong>. & Date vide which cost of tender specification<br />
fees deposited by you.<br />
3- Name & Address of tenderer<br />
REPLIES<br />
4- Year since when the tenderer has started execution of work<br />
tender.<br />
5- Do you agree to all the conditions of the tender specification<br />
and if not State the modifications clearly which you desire in<br />
general conditions from A/B. it may Please be noted that it<br />
shall be entirely at the desecration of the undersigned to accept<br />
or reject the modification proposed)<br />
6- Account of earn money deposited with full details be<br />
submitted here<br />
7- Please state clearly (Yes/<strong>No</strong>) if you would accept the order of<br />
modification in the form A/B are not acceptable to the<br />
corporation without imposing further conditions form your<br />
side.<br />
8- Give two reference who can certify your financial status and<br />
capability to undertake execution of work/Supply. One of the<br />
reference should be of any scheduled Bank of India.<br />
9- Name & Detailed address of <strong>Tender</strong>er/ Proprietor/<br />
Partners/Director be given.<br />
<strong>10</strong> Statement of past/current experience in similar works in the<br />
following form:-<br />
Sl<br />
no<br />
Name & address of<br />
ordering authority<br />
Order/<br />
Contract<br />
<strong>No</strong>. & Date<br />
Particular of<br />
work<br />
executed<br />
Quantum of work<br />
Ordered Completed Remarks<br />
1 2 3 4 5 6 7<br />
11- What is the validity period of your tender.<br />
12- Place & Date<br />
Signature of <strong>Tender</strong>er<br />
With seal
MADHYANC<strong>HAL</strong> VIDYUT VITARAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
Date of opening:-26-08-2013<br />
<strong>Tender</strong> Specification <strong>No</strong>. 29/EDD-IU/2013-14<br />
SCHEDULE OF RATES & QUANTUM OF WORK FOR PROVIDING MAN POWER (GANG) AT 33/11<br />
KV SUB STATION PURWA, UNNAO .<br />
Sl.<br />
<strong>No</strong>.<br />
Particulars of Work Unit Qty<br />
Rate (Per Day/<br />
Per Labour)<br />
Amount (Per<br />
Day)<br />
Providing man power (gang) for attending break<br />
downs of H.T/L.T. Lines due to broken<br />
conductor, blown fuses, puncture insulators etc.<br />
attending consumers complaints and<br />
disconnection of defaulting consumers every day<br />
for 8 hours including Sunday and holyday as per<br />
detail given below.<br />
1- Skilled labour having I.T.I. Cirtificate in<br />
Electrician/Wireman trade.<br />
2- Unskilled labour having experience for<br />
maintenance of H.T. & L.T. Lines.<br />
Total<br />
For 6 MONTH<br />
<strong>No</strong>s. 4<br />
<strong>No</strong>s. 8<br />
Signature & seal of<br />
Contractor<br />
Executive Engineer<br />
EDD-I Unnao
MADHYANC<strong>HAL</strong> VIDYUT VITRAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
<strong>Tender</strong> <strong>No</strong>. 29 /EDD-IU/2013-14<br />
SPECIAL TERMS & CONDITIONS<br />
1- The works will be carried out by the Contractor during the Agreement period of Six month<br />
from the date of commencement, under Electricity Distribution Division-I, Unnao.<br />
2- The skilled labour to be provided by the Contractor shall have the educational qualification of<br />
intermediate with I.T.I certificate in Electrician trade.<br />
3- The Contractor shall have Registration with Labour Commissioner for Engaging Labour which<br />
should be valid at least for agreement period. The photo copy of registration certificate shall be<br />
produced by the Contractor before taking up the work in hand.<br />
4- The Contractor shall also be registered with E.P.F. Commissioner and he will have to deposit<br />
the amount of E.P.F. deducted by him from the monthly wages of his labour in the office of<br />
E.P.F. Commissioner every month and photocopy of the same will be produce to Executive<br />
Engineer, Electricity Distribution Division-I, Unnao accordingly.<br />
5- Apart from above, the Contactor shall also be required to get registered with concerning<br />
authorities of Central Excise duty and Service Tax in respect of his aforesaid labour.<br />
6- The payment of the Ex-gratia will also be made to his labour by the Contractor, if it is found<br />
payable as per labour Act/Rules.<br />
7- The Skilled and un-skilled labour being engaged by the Contractor shall, in no case, be entitled<br />
for regular service of the Corporation.<br />
8- All T&P required for proper completion of assigned work, shall be arranged and provided to<br />
his labour by the Contractor him self at his own cost. However, all the required stock materials/<br />
component for proper completion of work shall arranged & provided by the Department free of<br />
cost.<br />
9- The Contractor shall be fully responsible for arranging accidental insurance policy for the<br />
compensation of his working personnel, if required as the Corporation shall not be held<br />
responsible for any compensation to his Labour in the event of any accident/mishap<br />
whatsoever.<br />
<strong>10</strong>- The Contractor will be required to pay minimum wages (in shape of A/C payee Cheque) to the<br />
employees engaged by him for the said purpose according to the rates approved by the Labour<br />
Commissioner and also amendment, if any, from time to time and subsequent approval by the<br />
Chief Engineer, M.V.V.N.L Lucknow/works Committee.<br />
11- The Contractor will issue Character Certificate in respect of each Employees provided by him<br />
and he will be responsible for any mischief committed by any of his labour.<br />
12- The Contractor shall have to follow instructions of the Engineer in charge of the Sub-Station or<br />
his representative in respect of proper operation & maintenance of Sub-Station.<br />
13- The log sheet & other requisite registers & stationery as well as stock materials/spares<br />
required for attending break downs/maintenance shall be supplied by the department and the<br />
account of their consumption shall be given by the contractor to Engineer supervising the<br />
work.<br />
14- 90 % payment will be made by concerned Executive Engineer against running bill subject to<br />
the availability of funds and <strong>10</strong>% amount will be detained as security which will be paid after<br />
the completion of works in satisfactory condition and after recommendation of concerned Subdivisional<br />
officer.<br />
15- <strong>No</strong> Experience Certificate will be issued by any Officer of the Corporation to any Employee of<br />
the Contractor.<br />
Cont.
(2)<br />
16- In addition to above all the general terms & conditions of contract for execution of works will<br />
governed as per Form-A.<br />
17- Income tax/other deductions as UPPCL/<strong>MVVNL</strong> rules shall be deducted from the Contractor<br />
bills as per State/Central Government rates prevailing in the Department.<br />
18- The Contractor shall confirm in respect to the requirement of Chief Electrical Inspector to U.P.<br />
Government as and when required by them in respect to Electrical Safety Rules and<br />
Regulation.<br />
19- <strong>No</strong> Compensation for idle labour shall be payable to the Contractor in any circumstances. The<br />
compensation owning to accident/ incident during execution of work shall be paid by the<br />
Contractor at his own without any reference to UPPCL/<strong>MVVNL</strong> and constitutional obligation<br />
for such compensation shall be sole responsibility of the contractor.<br />
20- The damage, if any, caused loss to the department/work/ T&P by the Contractor him self or his<br />
staff shall be recovered in full from the pending bill(s)/ liability of the Contractor.<br />
21- The Superintending Engineer, Electricity Distribution Circle, Unnao will be the principal<br />
employer of the contract and the Concerned Executive Engineer shall function as Engineer-incharge<br />
of the contract. The work shall be carried out as per rules by the Contractor in strict<br />
supervision and to the entire satisfaction of Engineer-in-charge of the Division.<br />
22- All the terms & Conditions of the Labour act will be adhered to strictly by the contractor.<br />
23- The dispute arising, if any, taken into Court, shall be within the Jurisdiction of Unnao.<br />
24- The contract shall have to issue identity card to his employees engaged for the said purpose.<br />
Executive Engineer<br />
Electricity Distribution Division-I<br />
Unnao
Madhyanchal<br />
Vidyut Vitaran<br />
Nigam Limited<br />
Electricity Distribution<br />
Division-I, Unnao.<br />
<strong>Tender</strong> <strong>No</strong>. 30/EDD-IU/2013-14<br />
DATE OF OPENING:-26-08-2013
<strong>Tender</strong> proforma<br />
(to be filled by tenderer)<br />
Important instruction of the tenderer<br />
Your tender shall not be considered if you fail to submit this proforma duly filled up replies should be<br />
completed without ambiguity and should be clearly written against each item.<br />
(Attach extra sheets if the space-left not sufficient)<br />
Sl.<br />
<strong>No</strong><br />
PARTICULARS<br />
1- Specification <strong>No</strong>. against which your are tenderer<br />
2- Receipt <strong>No</strong>. & Date vide which cost of tender specification<br />
fees deposited by you.<br />
3- Name & Address of tenderer<br />
REPLIES<br />
4- Year since when the tenderer has started execution of work<br />
tender.<br />
5- Do you agree to all the conditions of the tender specification<br />
and if not State the modifications clearly which you desire in<br />
general conditions from A/B. it may Please be noted that it<br />
shall be entirely at the desecration of the undersigned to accept<br />
or reject the modification proposed)<br />
6- Account of earn money deposited with full details be<br />
submitted here<br />
7- Please state clearly (Yes/<strong>No</strong>) if you would accept the order of<br />
modification in the form A/B are not acceptable to the<br />
corporation without imposing further conditions form your<br />
side.<br />
8- Give two reference who can certify your financial status and<br />
capability to undertake execution of work/Supply. One of the<br />
reference should be of any scheduled Bank of India.<br />
9- Name & Detailed address of <strong>Tender</strong>er/ Proprietor/<br />
Partners/Director be given.<br />
<strong>10</strong> Statement of past/current experience in similar works in the<br />
following form:-<br />
Sl<br />
no<br />
Name & address of<br />
ordering authority<br />
Order/<br />
Contract<br />
<strong>No</strong>. & Date<br />
Particular of<br />
work<br />
executed<br />
Quantum of work<br />
Ordered Completed Remarks<br />
1 2 3 4 5 6 7<br />
11- What is the validity period of your tender.<br />
12- Place & Date<br />
Signature of <strong>Tender</strong>er<br />
With seal
MADHYANC<strong>HAL</strong> VIDYUT VITARAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
Date of opening:-26-08-2013<br />
<strong>Tender</strong> Specification <strong>No</strong>. 30/EDD-IU/2013-14<br />
SCHEDULE OF RATES & QUANTUM OF WORK FOR PROVIDING MAN POWER (GANG)<br />
AT 33/11 KV SUB STATION BIGHAPUR, UNNAO .<br />
Sl.<br />
<strong>No</strong>.<br />
Particulars of Work Unit Qty<br />
Rate (Per<br />
Day/ Per<br />
Labour)<br />
Amount (Per<br />
Day)<br />
Providing man power (gang) for<br />
attending break downs of H.T/L.T.<br />
Lines due to broken conductor, blown<br />
fuses, puncture insulators etc. attending<br />
consumers complaints and<br />
disconnection of defaulting consumers<br />
every day for 8 hours including Sunday<br />
and holyday as per detail given below.<br />
1- Skilled labour having I.T.I. Cirtificate in<br />
Electrician/Wireman trade.<br />
2- Unskilled labour having experience for<br />
maintenance of H.T. & L.T. Lines.<br />
Total<br />
For 6 MONTH<br />
<strong>No</strong>s. 4<br />
<strong>No</strong>s. 8<br />
Signature & seal of<br />
Contractor<br />
Executive Engineer<br />
EDD-I Unnao
MADHYANC<strong>HAL</strong> VIDYUT VITRAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
<strong>Tender</strong> <strong>No</strong>. 30 /EDD-IU/2013-14<br />
SPECIAL TERMS & CONDITIONS<br />
1- The works will be carried out by the Contractor during the Agreement period of Six month<br />
from the date of commencement, under Electricity Distribution Division-I, Unnao.<br />
2- The skilled labour to be provided by the Contractor shall have the educational qualification of<br />
intermediate with I.T.I certificate in Electrician trade.<br />
3- The Contractor shall have Registration with Labour Commissioner for Engaging Labour which<br />
should be valid at least for agreement period. The photo copy of registration certificate shall be<br />
produced by the Contractor before taking up the work in hand.<br />
4- The Contractor shall also be registered with E.P.F. Commissioner and he will have to deposit<br />
the amount of E.P.F. deducted by him from the monthly wages of his labour in the office of<br />
E.P.F. Commissioner every month and photocopy of the same will be produce to Executive<br />
Engineer, Electricity Distribution Division-I, Unnao accordingly.<br />
5- Apart from above, the Contactor shall also be required to get registered with concerning<br />
authorities of Central Excise duty and Service Tax in respect of his aforesaid labour.<br />
6- The payment of the Ex-gratia will also be made to his labour by the Contractor, if it is found<br />
payable as per labour Act/Rules.<br />
7- The Skilled and un-skilled labour being engaged by the Contractor shall, in no case, be entitled<br />
for regular service of the Corporation.<br />
8- All T&P required for proper completion of assigned work, shall be arranged and provided to<br />
his labour by the Contractor him self at his own cost. However, all the required stock materials/<br />
component for proper completion of work shall arranged & provided by the Department free of<br />
cost.<br />
9- The Contractor shall be fully responsible for arranging accidental insurance policy for the<br />
compensation of his working personnel, if required as the Corporation shall not be held<br />
responsible for any compensation to his Labour in the event of any accident/mishap<br />
whatsoever.<br />
<strong>10</strong>- The Contractor will be required to pay minimum wages (in shape of A/C payee Cheque) to the<br />
employees engaged by him for the said purpose according to the rates approved by the Labour<br />
Commissioner and also amendment, if any, from time to time and subsequent approval by the<br />
Chief Engineer, M.V.V.N.L Lucknow/works Committee.<br />
11- The Contractor will issue Character Certificate in respect of each Employees provided by him<br />
and he will be responsible for any mischief committed by any of his labour.<br />
12- The Contractor shall have to follow instructions of the Engineer in charge of the Sub-Station or<br />
his representative in respect of proper operation & maintenance of Sub-Station.<br />
13- The log sheet & other requisite registers & stationery as well as stock materials/spares<br />
required for attending break downs/maintenance shall be supplied by the department and the<br />
account of their consumption shall be given by the contractor to Engineer supervising the<br />
work.<br />
14- 90 % payment will be made by concerned Executive Engineer against running bill subject to<br />
the availability of funds and <strong>10</strong>% amount will be detained as security which will be paid after<br />
the completion of works in satisfactory condition and after recommendation of concerned Subdivisional<br />
officer.<br />
15- <strong>No</strong> Experience Certificate will be issued by any Officer of the Corporation to any Employee of<br />
the Contractor.<br />
Cont.
(2)<br />
16- In addition to above all the general terms & conditions of contract for execution of works will<br />
governed as per Form-A.<br />
17- Income tax/other deductions as UPPCL/<strong>MVVNL</strong> rules shall be deducted from the Contractor<br />
bills as per State/Central Government rates prevailing in the Department.<br />
18- The Contractor shall confirm in respect to the requirement of Chief Electrical Inspector to U.P.<br />
Government as and when required by them in respect to Electrical Safety Rules and<br />
Regulation.<br />
19- <strong>No</strong> Compensation for idle labour shall be payable to the Contractor in any circumstances. The<br />
compensation owning to accident/ incident during execution of work shall be paid by the<br />
Contractor at his own without any reference to UPPCL/<strong>MVVNL</strong> and constitutional obligation<br />
for such compensation shall be sole responsibility of the contractor.<br />
20- The damage, if any, caused loss to the department/work/ T&P by the Contractor him self or his<br />
staff shall be recovered in full from the pending bill(s)/ liability of the Contractor.<br />
21- The Superintending Engineer, Electricity Distribution Circle, Unnao will be the principal<br />
employer of the contract and the Concerned Executive Engineer shall function as Engineer-incharge<br />
of the contract. The work shall be carried out as per rules by the Contractor in strict<br />
supervision and to the entire satisfaction of Engineer-in-charge of the Division.<br />
22- All the terms & Conditions of the Labour act will be adhered to strictly by the contractor.<br />
23- The dispute arising, if any, taken into Court, shall be within the Jurisdiction of Unnao.<br />
24- The contract shall have to issue identity card to his employees engaged for the said purpose.<br />
Executive Engineer<br />
Electricity Distribution Division-I<br />
Unnao
Madhyanchal<br />
Vidyut Vitaran<br />
Nigam Limited<br />
Electricity Distribution<br />
Division-I, Unnao.<br />
<strong>Tender</strong> <strong>No</strong>. 31/EDD-IU/2013-14<br />
DATE OF OPENING:-26-08-2013
<strong>Tender</strong> proforma<br />
(to be filled by tenderer)<br />
Important instruction of the tenderer<br />
Your tender shall not be considered if you fail to submit this proforma duly filled up replies should be<br />
completed without ambiguity and should be clearly written against each item.<br />
(Attach extra sheets if the space-left not sufficient)<br />
Sl.<br />
<strong>No</strong><br />
PARTICULARS<br />
1- Specification <strong>No</strong>. against which your are tenderer<br />
2- Receipt <strong>No</strong>. & Date vide which cost of tender specification<br />
fees deposited by you.<br />
3- Name & Address of tenderer<br />
REPLIES<br />
4- Year since when the tenderer has started execution of work<br />
tender.<br />
5- Do you agree to all the conditions of the tender specification<br />
and if not State the modifications clearly which you desire in<br />
general conditions from A/B. it may Please be noted that it<br />
shall be entirely at the desecration of the undersigned to accept<br />
or reject the modification proposed)<br />
6- Account of earn money deposited with full details be<br />
submitted here<br />
7- Please state clearly (Yes/<strong>No</strong>) if you would accept the order of<br />
modification in the form A/B are not acceptable to the<br />
corporation without imposing further conditions form your<br />
side.<br />
8- Give two reference who can certify your financial status and<br />
capability to undertake execution of work/Supply. One of the<br />
reference should be of any scheduled Bank of India.<br />
9- Name & Detailed address of <strong>Tender</strong>er/ Proprietor/<br />
Partners/Director be given.<br />
<strong>10</strong> Statement of past/current experience in similar works in the<br />
following form:-<br />
Sl<br />
no<br />
Name & address of<br />
ordering authority<br />
Order/<br />
Contract<br />
<strong>No</strong>. & Date<br />
Particular of<br />
work<br />
executed<br />
Quantum of work<br />
Ordered Completed Remarks<br />
1 2 3 4 5 6 7<br />
11- What is the validity period of your tender.<br />
12- Place & Date<br />
Signature of <strong>Tender</strong>er<br />
With seal
MADHYNC<strong>HAL</strong> VIDYUT VITARAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I UNNAO<br />
TENDER SPECIFICATION NO. 31/ EDDIU/2013-14<br />
Date Of Opening: 26-08-2013<br />
Shedule of rates & works for dismantling of damaged transformer from D/P / Plinth, safe carriage<br />
including loading , unloading and proper placing of the same Under the area of 33/11 KV S/S Bighapur<br />
Unnao of Electricity Distribution Sub-Division-IIIrd, Unnao. to workshop/ store center at Unnao.<br />
Thereafter mounting of new/ repaired. T/Fs on D/P/ Plinth including loading, Unloading and safe<br />
carriage of the same from store center Unnao to work site distance above 30 Km.<br />
Sl. <strong>No</strong>.<br />
Transformer<br />
Capacity<br />
1 250 KVA<br />
Quantity in <strong>No</strong>.<br />
Damaged 4<br />
New/ Repaired 4<br />
Rate Per<br />
Transfarmer<br />
Amount<br />
2 <strong>10</strong>0 KVA<br />
Damaged 5<br />
New/ Repaired 5<br />
3<br />
63 KVA Damaged 20<br />
New/ Repaired 20<br />
4 25 KVA<br />
5 16 KVA<br />
5 <strong>10</strong> KVA<br />
Damaged 65<br />
New/ Repaired 65<br />
Damaged 5<br />
New/ Repaired 5<br />
Damaged 20<br />
New/ Repaired 20<br />
Total<br />
Signature & seal of<br />
Contractor<br />
ExecutiveEngineer<br />
EDD-I Unnao
MADHYANC<strong>HAL</strong> VIDYUT VITRAN NIGAM LIMITED<br />
ELECTRICITY DISTRIBUTION DIVISION-I, UNNAO<br />
<strong>Tender</strong> <strong>No</strong>. 31/ EDD-IU/2013-14<br />
SPECIAL TERMS & CONDITIONS<br />
1. The work shall be completed within one year( <strong>No</strong>. of T/F as per work schedule are<br />
agreemented value) from the date agreement/date of handing over material by the deptt.<br />
2. Variation shall be admissible only with the approval of the committee.<br />
3. The work shall be carried out in accordance with Indian Electricity Act and Rules & as per<br />
Construction Manual of U.P. Power Corporation Ltd. And RESSPO Schedule.<br />
4. All the material of standard quality associated with the work shall be provided by the<br />
Contractor as per tender specification.<br />
5. Any loss & damage shall be recovered from the contractor account.<br />
6. <strong>No</strong> T & P shall be supplied by the department at any cost. The transportation arrangement for<br />
safe carriage of materials shall be made by the Contractor. at his own risk.<br />
7. All general conditions of contract for execution of work will be governed as per from ‘A’<br />
(General conditions for the supply of plant and the execution of work in the U.P. Power<br />
Corporation Ltd.)<br />
8. The work shall be carried out under the direct supervision of Junior Engineer and Sub-<br />
Divisional Officer concerned.<br />
9. Department will not be responsible for any accident, casualties and loss occurred at the time of<br />
execution of work. The contractor shall be fully responsible for the same.<br />
<strong>10</strong>. The necessary permit for shutdown etc. will be given to the contractor by the representative of<br />
the department as and when required for completion of work in a planned way.<br />
11. The 90% payment shall be made on receipt bill against the works completed subject to<br />
availability of fund and remaining <strong>10</strong>% will be detained as security which will be paid after 6<br />
month from the date of completion of full work.<br />
12. The Income Tax and other taxes will be deducted from the bill, if and as applicable.<br />
13. Penalty @ ½% per week subject to maximum of <strong>10</strong>% of the total value of the contract will be<br />
levied and deducted if the work is not completed within the stipulated period.<br />
Executive Engineer<br />
Electricity Distribution Division-I<br />
Unnao