Bruce Heavy Water Plant Decommissioning<br />

Environmental Assessment Study Report<br />

Ontario Power Generation<br />

Final Submission to CNSC<br />

• identify those members of the project staff with specific EH&S responsibilities and describe<br />

the responsibility, authority and accountability of each;<br />

• identify the safety training required by workers engaged in various aspects of the work;<br />

• describe the procedures used to identify, report and control hazards in the workplace;<br />

• describe the procedures used to investigate accidents or injuries and eliminate the causes of<br />

those events;<br />

• describe the procedures used to perform hazardous work;<br />

• describe the procedures established to provide a safe work environment within the<br />

Construction Islands; and<br />

• describe the procedures that will be implemented to prepare for any accident, fire, flood, spill<br />

or other emergency situation that might occur during the course of the work.<br />

OPG will review the EH&S Management Plan prepared by the GDC who will not be permitted<br />

to begin work in any Construction Island until a plan acceptable to the OPG is in place. The<br />

GDC will be responsible for ensuring that all work in the Construction Islands, including work<br />

performed by subcontractors, is performed in accordance with the EH&S Management Plan.<br />

3.4.2.3 Construction Safety<br />

It is recognized that the demolition of the buildings, structures and pipe racks presents hazards to<br />

the safety of workers and visitors to the Construction Island. The GDC will be required to take<br />

all of the actions that are reasonably required to maintain a safe work environment within the<br />

Construction Islands, and must include Construction Safety procedures in the EH&S<br />

Management Plan. This may include procedures controlling:<br />

• the distribution, use, maintenance and testing of personal protective equipment;<br />

• work with power tools;<br />

• work at heights and fall protection;<br />

• work in confined spaces;<br />

• work in inclement weather;<br />

• hot work such as welding or cutting metals;<br />

• asbestos removal;<br />

• the operation and maintenance of heavy machinery;<br />

• the operation of cranes and the lifting of heavy loads; and<br />

• housekeeping.<br />

OPG will be entitled to audit the GDC’s compliance with the EH&S Management Plan. This<br />

may include inspecting the Construction Islands or observing work being performed. In the<br />

3-25 December 2002