Besides one mile roadways, the major existing corridors in this area<br />

consist <strong>of</strong> large transmission line corridors, the BFC and other numerous<br />

smaller irrigation canals. The Durango Regional Conveyance Channel<br />

utilizes the existing transmission line corridor south <strong>of</strong> Lower Buckeye<br />

Road from east <strong>of</strong> 83 rd Avenue to 107 th Avenue. This transmission line<br />

corridor contains <strong>of</strong> a double row <strong>of</strong> metal monopoles.<br />

Durango Regional Conveyance Channel (Photo key location 7)<br />

Transmission Line Corridor<br />

Durango Regional Conveyance Channel (Photo key location 8)<br />

Transmission corridor along the existing BFC.<br />

Design <strong>of</strong> the sections <strong>of</strong> the corridor following the transmission<br />

corridor should create pedestrian scale visual interest and include<br />

mitigation measures to buffer views <strong>of</strong> the power poles and power line<br />

and maintain the desirable views <strong>of</strong> the mountains to the south.<br />

The recommended plan alignment also uses a small portion <strong>of</strong> the BFC<br />

alignment between 99th Avenue and 115th Avenue and then again from<br />

one half mile west <strong>of</strong> 115 th Avenue to just west <strong>of</strong> Dysart Road. The<br />

existing BFC is an elevated, unimproved dirt lined ditch. It’s route is<br />

adjacent to or within existing open agricultural lands and some rural<br />

residences. There are currently planned residential developments along<br />

the BFC from 91st Avenue to 115th Avenue. West <strong>of</strong> Dysart, the route<br />

is also adjacent to the existing Sand and Gravel Pit to the north.<br />

( Looking East) (05/2001)<br />

( Looking East) (05/2001)<br />

( Looking West - Channel and Basin #2 Site) (05/2001)<br />

( Looking West) (05/2001)<br />

DIBBLE & ASSOCIATES 31 DURANGO AREA DRAINAGE MASTER PLAN<br />

August 2002<br />

RECOMMENDED DESIGN REPORT