<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />
Pinal County, AZ<br />
Draft Supplemental Watershed <strong>Plan</strong><br />
<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />
NRCS Table 1 - Estimated Installation Cost<br />
<strong>Powerline</strong> FRS<br />
Apache Junction-Gilbert Watershed, Maricopa <strong>and</strong> Pinal Counties, AZ<br />
(Dollars) 1/<br />
Installation Cost Item Unit Number<br />
Federal<br />
Funds<br />
1/, 2/<br />
Estimated Cost<br />
Other Funds<br />
Total<br />
Replacement of<br />
<strong>Powerline</strong> FRS<br />
No. 1 $15,476,200 $8,417,600 $23,893,800<br />
Total Project $15,476,200 $8,417,600 $23,893,800<br />
<strong>Jan</strong>uary <strong>2013</strong><br />
1/ 2012 Prices.<br />
2/ Federal Funds include NRCS Engineering Services <strong>and</strong> Project Administration ($650,000), which are not included when calculating eligible<br />
federal cost share. Permit costs ($434,300) are also not included. Therefore, federal cost share is based on Total Eligible Project Cost of<br />
$22,809,500.<br />
USDA- NRCS Page 8-9 <strong>Jan</strong>uary <strong>2013</strong><br />