Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...
Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...
Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />
Pinal County, AZ<br />
Draft Supplemental Watershed <strong>Plan</strong><br />
<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />
8.2 MEASURES TO BE INSTALLED<br />
The features of the Preferred Alternative are summarized below which are based on the results of<br />
the technical investigations <strong>and</strong> analyses, <strong>and</strong> in accordance with the Sponsor <strong>and</strong> NRCS<br />
requirements.<br />
8.2.1 POWERLINE CHANNEL<br />
The concept for the Preferred Alternative includes constructing a new 100-year channel upstream<br />
of <strong>Powerline</strong> FRS <strong>and</strong> removing both the existing FRS <strong>and</strong> IDSM embankments. The proposed<br />
<strong>Powerline</strong> channel was sized using the existing conditions 100-year discharge. Typical cross<br />
sections are provided in Appendix C as Figure C-6. The <strong>Powerline</strong> channel is comprised of two<br />
channels. The first is a collector channel running along the existing FRS alignment to capture<br />
inflow that would otherwise reach the structure. The second channel is specifically for Siphon<br />
Draw, the largest wash within the watershed. The two channels combine before discharging into<br />
the Vineyard Road FRS flood pool.<br />
The channels were initially sized using normal depth routing within HEC-1. The preliminary<br />
channel sizes were then input into the FLO-2D model. Where breakouts occurred from potential<br />
channel overtopping, the channel sizes were increased to provide additional capacity. The resulting<br />
bottom widths <strong>and</strong> geometries of the two proposed channels are summarized in Table 8-1.<br />
Table 8-1 Summary of <strong>Powerline</strong> Channel Geometry <strong>and</strong> Results.<br />
<strong>Powerline</strong> Channel<br />
Design Parameters<br />
Analysis Results<br />
Hydrologic<br />
Segment<br />
Start<br />
Station<br />
End<br />
Station Lining<br />
Channel<br />
Bottom<br />
Width<br />
[ft]<br />
Total<br />
Depth 1<br />
[ft]<br />
Side<br />
Slopes<br />
[ft:ft]<br />
[H:1]<br />
Peak<br />
Discharge 2<br />
[cfs]<br />
Depth<br />
of<br />
Flow 3<br />
[ft]<br />
Velocity 3<br />
[ft/s]<br />
CP25 10+00 27+50 Earthen 60 5.1 6 984 4.0 2.9<br />
CP25<br />
3.0 2 939 2.0 7.2<br />
Hardened 27+50 46+50 Hardened 60<br />
CP9 46+50 61+50 Earthen 150 6.2 6 3,153 4.9 3.6<br />
CP5R<br />
5.8 2 7,746 4.2 11.7<br />
Hardened 61+50 77+50 Hardened 150<br />
Vineyard<br />
5.6 6 8,129 4.4 3.5<br />
CP5R 77+50 <strong>Flood</strong> Pool Earthen 500<br />
CP4 (Siphon<br />
4.1 6 13,444 3.1 4.2<br />
Draw) Earthen 1000<br />
1<br />
Total depth including freeboard<br />
2<br />
Peak discharge reported from FLO-2D results<br />
3<br />
Depth of flow <strong>and</strong> velocity reported from FlowMaster normal depth calculations<br />
Segments of the proposed collector channel will be hardened with concrete as shown in the typical<br />
section in Appendix C. The available earth fissure risk hazard mapping at this level of analysis<br />
does not fully cover the proposed channel limits so existing mapping zones were projected<br />
upstream. A map of Fissure Risk Hazard Zones (FRZs) is provided in Appendix C. The segments<br />
USDA- NRCS Page 8-2 <strong>Jan</strong>uary <strong>2013</strong><br />
Kimley-Horn <strong>and</strong> Associates, Inc.