06.11.2014 Views

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />

Pinal County, AZ<br />

Draft Supplemental Watershed <strong>Plan</strong><br />

<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />

8.2 MEASURES TO BE INSTALLED<br />

The features of the Preferred Alternative are summarized below which are based on the results of<br />

the technical investigations <strong>and</strong> analyses, <strong>and</strong> in accordance with the Sponsor <strong>and</strong> NRCS<br />

requirements.<br />

8.2.1 POWERLINE CHANNEL<br />

The concept for the Preferred Alternative includes constructing a new 100-year channel upstream<br />

of <strong>Powerline</strong> FRS <strong>and</strong> removing both the existing FRS <strong>and</strong> IDSM embankments. The proposed<br />

<strong>Powerline</strong> channel was sized using the existing conditions 100-year discharge. Typical cross<br />

sections are provided in Appendix C as Figure C-6. The <strong>Powerline</strong> channel is comprised of two<br />

channels. The first is a collector channel running along the existing FRS alignment to capture<br />

inflow that would otherwise reach the structure. The second channel is specifically for Siphon<br />

Draw, the largest wash within the watershed. The two channels combine before discharging into<br />

the Vineyard Road FRS flood pool.<br />

The channels were initially sized using normal depth routing within HEC-1. The preliminary<br />

channel sizes were then input into the FLO-2D model. Where breakouts occurred from potential<br />

channel overtopping, the channel sizes were increased to provide additional capacity. The resulting<br />

bottom widths <strong>and</strong> geometries of the two proposed channels are summarized in Table 8-1.<br />

Table 8-1 Summary of <strong>Powerline</strong> Channel Geometry <strong>and</strong> Results.<br />

<strong>Powerline</strong> Channel<br />

Design Parameters<br />

Analysis Results<br />

Hydrologic<br />

Segment<br />

Start<br />

Station<br />

End<br />

Station Lining<br />

Channel<br />

Bottom<br />

Width<br />

[ft]<br />

Total<br />

Depth 1<br />

[ft]<br />

Side<br />

Slopes<br />

[ft:ft]<br />

[H:1]<br />

Peak<br />

Discharge 2<br />

[cfs]<br />

Depth<br />

of<br />

Flow 3<br />

[ft]<br />

Velocity 3<br />

[ft/s]<br />

CP25 10+00 27+50 Earthen 60 5.1 6 984 4.0 2.9<br />

CP25<br />

3.0 2 939 2.0 7.2<br />

Hardened 27+50 46+50 Hardened 60<br />

CP9 46+50 61+50 Earthen 150 6.2 6 3,153 4.9 3.6<br />

CP5R<br />

5.8 2 7,746 4.2 11.7<br />

Hardened 61+50 77+50 Hardened 150<br />

Vineyard<br />

5.6 6 8,129 4.4 3.5<br />

CP5R 77+50 <strong>Flood</strong> Pool Earthen 500<br />

CP4 (Siphon<br />

4.1 6 13,444 3.1 4.2<br />

Draw) Earthen 1000<br />

1<br />

Total depth including freeboard<br />

2<br />

Peak discharge reported from FLO-2D results<br />

3<br />

Depth of flow <strong>and</strong> velocity reported from FlowMaster normal depth calculations<br />

Segments of the proposed collector channel will be hardened with concrete as shown in the typical<br />

section in Appendix C. The available earth fissure risk hazard mapping at this level of analysis<br />

does not fully cover the proposed channel limits so existing mapping zones were projected<br />

upstream. A map of Fissure Risk Hazard Zones (FRZs) is provided in Appendix C. The segments<br />

USDA- NRCS Page 8-2 <strong>Jan</strong>uary <strong>2013</strong><br />

Kimley-Horn <strong>and</strong> Associates, Inc.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!