Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...
Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...
Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />
Pinal County, AZ<br />
Draft Supplemental Watershed <strong>Plan</strong><br />
<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />
point of the modified easement near Rittenhouse FRS. A new 100-year basin at the southern end of<br />
the channel near Rittenhouse FRS would detain the 100-year runoff volume, <strong>and</strong> drain to Queen<br />
Creek Wash through a gated outlet.<br />
A new at-grade principal spillway <strong>and</strong> a new basin overflow spillway would be constructed at the<br />
southern end of the 100-year basin replacing Rittenhouse FRS. The principal spillway would drain<br />
south to Queen Creek in a new channel to a new overchute at the CAP canal near the existing outlet<br />
of the Sonoqui Detention Dike. An inlet <strong>and</strong> outlet structure, conduit <strong>and</strong> trash rack on the inlet<br />
would be provided at the new principal spillway. A new basin overflow spillway would be<br />
constructed <strong>and</strong> would drain in the same general flow path as the existing Rittenhouse facility. The<br />
<strong>Powerline</strong> <strong>Flood</strong>way would not be used under this alternative but could be utilized under a revised<br />
alternative scenario.<br />
The upstream invert of the channel is limited by the modified easement boundary in the vicinity of<br />
<strong>Powerline</strong> FRS. The downstream constraint is the elevation of the tie-in with Queen Creek Wash.<br />
The upstream <strong>and</strong> downstream elevation constraints result in an insufficient slope of 0.0006 ft/ft.<br />
The combined 100-year, 24-hour discharge for <strong>Powerline</strong>, Vineyard Road <strong>and</strong> Rittenhouse is<br />
41,756 cfs, which would require an earthen channel five feet deep with 6:1 side slopes to be over<br />
3,500 feet wide. Given this constraint, further evaluation of this alternative was not considered.<br />
This alternative was eliminated from further consideration in the workshop held on December 8,<br />
2010 due to noted technical constraints.<br />
Decommissioning the <strong>Powerline</strong>, Vineyard Road, <strong>and</strong> Rittenhouse FRSs with Stabilized Breaches<br />
(Alternative 10)<br />
The concept for Alternative 10 calls for decommissioning <strong>Powerline</strong>, Vineyard Road <strong>and</strong><br />
Rittenhouse FRSs by constructing stabilized breaches at selected locations at each dam. The<br />
structures will be decommissioned by constructing multiple breaches in each structure. The<br />
breaches will be designed for the 100-year event <strong>and</strong> will be located along natural drainage paths in<br />
natural washes where existing FEMA 100-year floodplains intersect the structures.<br />
The flow depth <strong>and</strong> velocities were analyzed at each breach location. Peak flows used in breach<br />
analysis were obtained from appropriate combination points in the 100-year, 24-hour existing<br />
conditions HEC-1 models. The breaches were analyzed for both concrete <strong>and</strong> riprap lining. The<br />
concrete lining results in high velocities that will require scour protection in the form of riprap or<br />
energy dissipaters. Riprap lining results lower-scour exit velocities.<br />
All existing principal spillway <strong>and</strong> emergency spillway structures would be removed. New 100-<br />
year CAP overchutes would be constructed for each breach location. The number of overchute<br />
pipes required to pass the 100-year peak discharge over the canal were estimated assuming full<br />
flow capacity of the pipes. A pipe diameter of 72-inches was used for overchutes requiring six<br />
barrels or less, <strong>and</strong> concrete rectangular channel overchutes were sized for those requiring more<br />
than six barrels.<br />
The opinion of probable cost for decommissioning all three FRSs (as considered in the Level I<br />
analysis) is $9,943,000. This alternative was eliminated from further consideration in the workshop<br />
held on December 8, 2010 as the alternative did not meet the project purpose <strong>and</strong> need for<br />
continued flood protection.<br />
USDA- NRCS Page 5-9 <strong>Jan</strong>uary <strong>2013</strong><br />
Kimley-Horn <strong>and</strong> Associates, Inc.