<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />
Pinal County, AZ<br />
Draft Supplemental Watershed <strong>Plan</strong><br />
<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />
The concept for Alternative 2 included reducing the existing structures to non-jurisdictional (by<br />
ADWR definition) size with auxiliary spillway heights of six feet. The <strong>Powerline</strong> IDSM alignment<br />
will be maintained for the reduced height <strong>Powerline</strong> structure. Upstream of the reduced structures,<br />
detention basins sized for the 100-year event would be constructed outside of the mesquite bosques<br />
to help preserve <strong>and</strong> protect the bosques. The basins would drain through the bosques <strong>and</strong> the basin<br />
bottom depth will be controlled by the existing principal outlet location. The existing conditions<br />
100-year 24-hour storage volume from the existing conditions 100-year HEC-1 models was used to<br />
size each of the basins, in addition to the 100-year sediment volume. No FRS rehabilitation is<br />
included.<br />
To evaluate the required excavation volume, the existing flood volume behind the FRS up to the<br />
spillway crest height of six feet was used as flood storage <strong>and</strong> was not included in the volume<br />
required for basin excavation. The remaining required storage volume would be provided in the<br />
excavated basins where the bottom depth of each basin is controlled by the existing principal outlet<br />
location. The basins were sized such that the footprint of each basin was contained within the<br />
existing modified easement. The estimated required basin areas <strong>and</strong> depths without freeboard are<br />
289 acres <strong>and</strong> ten feet for <strong>Powerline</strong>, 385 acres <strong>and</strong> six feet for Vineyard Road, <strong>and</strong> 538 acres <strong>and</strong><br />
seven feet for Rittenhouse FRS. The basins will be excavated an additional three feet each in depth<br />
to include the 100-year sediment storage.<br />
The opinion of probable cost for converting each FRS to a basin <strong>and</strong> reducing the dam heights to<br />
non-jurisdictional dams (as considered in the Level I analysis) is $190,690,000. This alternative<br />
was eliminated from further detailed study in the workshop conducted on April 26, 2011 due to<br />
high costs, operational complexity, lower flood protection level (100-year), <strong>and</strong> h<strong>and</strong>ling <strong>and</strong><br />
storage of excess earthwork spoils.<br />
Decommissioning <strong>Powerline</strong>, Vineyard Road, <strong>and</strong> Rittenhouse FRS by Converting all Three Dams<br />
to Levees that Drain south to a Basin that Outlets to Queen Creek (Alternative 3).<br />
The concept for Alternative 3 included converting <strong>Powerline</strong> <strong>and</strong> Vineyard Road FRSs to levees to<br />
meet FEMA <strong>and</strong> District criteria. Additionally, Rittenhouse FRS would be removed <strong>and</strong> a levee<br />
would be constructed further west <strong>and</strong> adjacent to the CAP canal. A 100-year detention basin<br />
would be constructed at the south end of the project with a gated outlet to Queen Creek Wash.<br />
A new gated at-grade outlet would be constructed at the south end of the 100-year basin to drain the<br />
basin to Queen Creek Wash. A new drainage channel would be constructed between the basin<br />
outlet <strong>and</strong> a new CAP overchute near Queen Creek Wash. A gated trash rack would be provided at<br />
the new outlet of the basin, <strong>and</strong> a new basin overflow spillway would be constructed to discharge<br />
flow in the same general flowpath as the existing Rittenhouse auxiliary spillway. The <strong>Powerline</strong><br />
<strong>Flood</strong>way would not be used under this alternative, but may be utilized as an alternative outlet.<br />
The invert elevation of the CAP overchutes at Queen Creek Wash is approximately 1,566 feet. In<br />
comparison, the inverts of the principal spillway outlets at <strong>Powerline</strong> <strong>and</strong> Vineyard Road FRSs are<br />
1,563.6 feet <strong>and</strong> 1,563.8 feet, respectively, lower than the invert elevation of the CAP overchutes at<br />
Queen Creek Wash. The low point of the PVR system <strong>and</strong> the existing CAP overchutes at Queen<br />
Creek Wash are separated by approximately 8.5 miles, so even if the overchutes were lowered three<br />
feet, the flowpath south to Queen Creek Wash would be effectively flat. The primary constraint of<br />
Alternative 3 is achieving positive drainage along the existing structure alignments to drain south to<br />
USDA- NRCS Page 5-4 <strong>Jan</strong>uary <strong>2013</strong><br />
Kimley-Horn <strong>and</strong> Associates, Inc.