06.11.2014 Views

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />

Pinal County, AZ<br />

Draft Supplemental Watershed <strong>Plan</strong><br />

<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />

combined with another alternative, <strong>and</strong>/or did not meet the purpose <strong>and</strong> need for the project. Note<br />

that the alternatives are formulated on a system wide approach (integrated system) such that all<br />

three dams were included in an alternative rather than a separate alternative developed for each<br />

dam. This system approach was taken to maintain the functional <strong>and</strong> operational relationship of the<br />

three PVR structures. Full descriptions of the alternatives noted below are provided in the “Level I<br />

Final Alternatives Summary Report” (KHA, February 2011), the “Level II Final Alternatives<br />

Summary Report” (KHA, June 2012), <strong>and</strong> the (Level III Final Alternatives Summary Report – KHA<br />

September 2012). The alternatives eliminated from further detailed study were screened in the<br />

alternatives workshops <strong>and</strong> documented in the workshop notes (see Appendix C in Level II Final<br />

Report for workshop notes <strong>and</strong> ranking matrices).<br />

The “ Level II Final Alternatives Summary Report” (KHA, June 2012) identified five structural<br />

alternatives for plan formulation based on technical analyses <strong>and</strong> input from the NRCS, the<br />

Sponsor, <strong>and</strong> the Consulting team. These alternatives (alternative numbers are as provided in the<br />

Level II report) are listed below for the PVR project:<br />

• Rehabilitation (Alternative 1): Raise <strong>and</strong> Rehabilitate the <strong>Powerline</strong>, Vineyard Road, <strong>and</strong><br />

Rittenhouse FRS structures<br />

• Combination (Alternative 6): Replace <strong>Powerline</strong> FRS <strong>and</strong> Northern 1/3 of Vineyard Road<br />

FRS with Basins <strong>and</strong> Channels, Raise <strong>and</strong> Rehabilitate the Southern 2/3 of Vineyard Road<br />

FRS <strong>and</strong> Rittenhouse FRS<br />

• Combination (Alternative 6A): Replace <strong>Powerline</strong> FRS <strong>and</strong> Northern 1/3 of Vineyard Road<br />

FRS with Basins <strong>and</strong> Channels, Raise <strong>and</strong> Rehabilitate the Southern 2/3 of Vineyard Road<br />

FRS <strong>and</strong> Convert Rittenhouse FRS to a Levee<br />

• Combination (Alternative 8): Replace <strong>Powerline</strong> <strong>and</strong> Rittenhouse FRSs with Channels,<br />

Raise <strong>and</strong> Rehabilitate Vineyard Road FRS<br />

• Combination (Alternative 8A): Replace <strong>Powerline</strong> FRSs with Channels, Raise <strong>and</strong><br />

Rehabilitate Vineyard Road FRS, <strong>and</strong> Convert Rittenhouse FRS to a Levee<br />

• No Action Alternative: Also known as No Action Alternative/Future Without Project<br />

Rehabilitation is defined as modification <strong>and</strong> improvements of the existing dams to meet current<br />

State <strong>and</strong> Federal dam-safety st<strong>and</strong>ards. Rehabilitation would include raising the dams to safely<br />

pass the inflow design flood (IDF) through the auxiliary spillways, providing new filters to address<br />

potential embankment cracking, providing a hardened dam or channel sections within moderate<br />

earth fissure risk zones, modification of auxiliary spillways, <strong>and</strong> replacing the existing principal<br />

spillways.<br />

A combination alternative combines structural measures to replace an individual dam or dam<br />

segment with a channel or levee with rehabilitation of the remaining dam structures/embankments.<br />

A decommissioning alternative (decommissioning of all three dams) was not selected to be<br />

evaluated <strong>and</strong> nor carried further in the Level II report.<br />

The Level III Analysis included analysis of another alternative – Alternative 8B. Alternatives 8A<br />

<strong>and</strong> 8B were carried forward into the Level III analysis (Level III Final Alternatives Summary<br />

Report – KHA September 2012). The Level III analysis conducted further evaluations of<br />

Alternatives 8A <strong>and</strong> 8B including refined earthwork quantity <strong>and</strong> construction cost estimates. Both<br />

USDA- NRCS Page 5-2 <strong>Jan</strong>uary <strong>2013</strong><br />

Kimley-Horn <strong>and</strong> Associates, Inc.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!