Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ... Powerline Plan and Environ. Assessment Jan. 2013 - Flood Control ...

fcd.maricopa.gov
from fcd.maricopa.gov More from this publisher
06.11.2014 Views

Powerline Flood Retarding Structure Pinal County, AZ Draft Supplemental Watershed Plan and Environmental Assessment 4.2.1.2. INSTALLATION OF CENTRAL FILTERS As a result of these findings, a phased approach was developed to further evaluate the existing condition of the dams, to design remedial measures to mitigate the cracking, and to repair the dams. Evaluations of the dams were performed by the NRCS and several geotechnical consulting firms between 1979 and 1986 and, based on the results of these investigations central filters were constructed in the three structures between 1978 and 1991. The central filters are designed to create a filter cake at the upstream interface between the filter and the embankment to prevent piping (internal erosion) along cracks that have developed in the embankment. The Powerline and Vineyard Road FRSs have filters that typically extend through the embankments and into native soils, except in a few isolated areas. In general, the central filters do not extend below the elevation of the upstream cutoff trenches. The Rittenhouse FRS filter generally does not extend through the embankment and into native soils or extend below the elevation of the upstream cutoff trench. Additionally, a central filter is not present in the southern end of the Rittenhouse FRS from Station 30+00 (the left abutment) to Station 80+00, a distance of 5,000 feet. It is the opinion of the project geotechnical engineer that the filters should extend into soils that possess Stage II cementation (or greater) and/or soils that are essentially incompressible and not susceptible to internal seepage erosion. 4.2.1.3. PRESENCE OF COLLAPSIBLE HOLOCENE SOILS The FRSs are underlain by low-density alluvial fan soils, which were deposited during the Holocene (during the last approximately 11,000 years). These soils have a high potential for collapse settlement and typically experience from 2 to 6 percent of vertical strain upon wetting under self-weight or low superimposed loads. The Holocene soils are underlain by Late Pleistocene alluvium consisting of dense or hard, highly stratified deposits. Unlike the Holocene soils, which are uncemented or exhibit discontinuous Stage I calcareous cementation, the Late Pleistocene soils typically possess Stage II or III cementation (the reader is referred to the “Final Geotechnical Summary Report” for a presentation of the cementation stages) and are essentially incompressible from the viewpoint of contributing to settlement of low embankments. It appears that the thickness of the Holocene soils varies considerably over short distances, suggesting that the top of the Pleistocene alluvium was an erosional surface with varying topography. The orientation of drainage channels during deposition of the Late Pleistocene and Holocene deposits may have differed from the orientation of the present-day drainage system. Based on these profiles, it appears that not all of the soils that are susceptible to collapse and internal erosion were removed from beneath the embankments or from the upstream cutoff trenches during construction of the dams, nor do the existing central filters in the embankments extend all the way through these soils and into incompressible soils that are not susceptible to internal erosion. Compression (collapse) of the softer, uncemented soils beneath the embankments may have resulted in differential settlement and cracking of the dams. Cracks that extend to the bottom of the embankments may be in contact with erodible soils, resulting in the potential presence of internal erosion pathways along the embankment-foundation interface below the central filters. USDA- NRCS January 2013 Kimley-Horn and Associates, Inc. Page 21

Powerline Flood Retarding Structure Pinal County, AZ Draft Supplemental Watershed Plan and Environmental Assessment 4.2.2. Foundation Excavations and Central Filter Construction 4.2.2.1. UPSTREAM CUTOFF TRENCH The three dams were constructed almost entirely of soils derived from upstream borrow areas, including the upstream cutoff trench, and from excavation of foundation soils below the footprint of the embankment. Excavation of the upstream cutoff trenches and excavation of the dam foundations resulted in the presence of “shelves” that generally extend 2 to 4 feet below original natural grades. It is thought that the upstream cutoff trench was designed to extend through the contact between the softer, collapse-prone soils (typically referred to as Holocene soils) and the underlying competent, cemented soils (typically referred to as Late Pleistocene soils) along the entire length of the dam alignment; however, only limited portions of the upstream cutoff trenches extend to this contact at the PVR FRSs. Central Filters Central filters were installed along the centerline of all three dams. The central filters in the Powerline and Vineyard Road FRS are 3 feet wide, whereas the central filter in the Rittenhouse FRS has a nominal width of 2.6 feet. Unlike the central filters in the Powerline and Vineyard Road FRSs, the filter in the Rittenhouse FRS is not continuous over the entire length of the dam nor was it designed to extend through the entire embankment into the underlying soils. Outlet drains were installed in the Rittenhouse FRS, but not at the Powerline or Vineyard Road FRSs. The outlet drains (40 in total) were constructed between Stations 80+00 and 200+00 of the Rittenhouse FRS at approximately 1,000-foot intervals along the dam or as directed by the Engineer. The outlet drains slope toward the downstream toe of the dam and are designed to provide positive drainage from the central filter. In a May 8, 2008 ADWR Inspection Report for the Powerline FRS, it was noted that during a recent geotechnical investigation that involved excavation of a shallow trench that exposed the upper portion of the central filter, there were similarities between the filter materials and the compacted embankment soils. Photo-documentation of this condition is presented in Appendix E of the report entitled “Earth Fissure/Ground Subsidence Instrumentation Installation Report and Monitoring Plan” (AMEC 2007), Noted similarities included “soil stiffness that supported vertical trench walls and cracking that extended into the central filter material.” ADWR notes that this observation is contrary to the standard of practice for granular filter design wherein the filter should be free-flowing and self-healing. Powerline FRS The central filter installed in the Powerline FRS in 1991 extends along the entire length of the embankment (from Stations 17+83 to 150+70). The filter has an average depth of 18 feet and a maximum depth of 42 feet. The depth of the filter was established by the NRCS on the basis of its 1986 crack location investigation. Vineyard Road FRS The central filter installed in the Vineyard Road FRS in 1983 extends along the entire length of the embankment (from Stations 85+00 to 360+00). As indicated on as-built plans of the filter installation, the central filter extends to depths of between 19 and 21 feet below the crest of the dam along most of its alignment, corresponding to depths of between 2.5 to 4.5 feet below the original ground surface (SCS 1983). USDA- NRCS January 2013 Kimley-Horn and Associates, Inc. Page 22

<strong>Powerline</strong> <strong>Flood</strong> Retarding Structure<br />

Pinal County, AZ<br />

Draft Supplemental Watershed <strong>Plan</strong><br />

<strong>and</strong> <strong>Environ</strong>mental <strong>Assessment</strong><br />

4.2.1.2. INSTALLATION OF CENTRAL FILTERS<br />

As a result of these findings, a phased approach was developed to further evaluate the existing<br />

condition of the dams, to design remedial measures to mitigate the cracking, <strong>and</strong> to repair the<br />

dams. Evaluations of the dams were performed by the NRCS <strong>and</strong> several geotechnical consulting<br />

firms between 1979 <strong>and</strong> 1986 <strong>and</strong>, based on the results of these investigations central filters were<br />

constructed in the three structures between 1978 <strong>and</strong> 1991. The central filters are designed to<br />

create a filter cake at the upstream interface between the filter <strong>and</strong> the embankment to prevent<br />

piping (internal erosion) along cracks that have developed in the embankment. The <strong>Powerline</strong><br />

<strong>and</strong> Vineyard Road FRSs have filters that typically extend through the embankments <strong>and</strong> into<br />

native soils, except in a few isolated areas. In general, the central filters do not extend below the<br />

elevation of the upstream cutoff trenches. The Rittenhouse FRS filter generally does not extend<br />

through the embankment <strong>and</strong> into native soils or extend below the elevation of the upstream<br />

cutoff trench. Additionally, a central filter is not present in the southern end of the Rittenhouse<br />

FRS from Station 30+00 (the left abutment) to Station 80+00, a distance of 5,000 feet. It is the<br />

opinion of the project geotechnical engineer that the filters should extend into soils that possess<br />

Stage II cementation (or greater) <strong>and</strong>/or soils that are essentially incompressible <strong>and</strong> not<br />

susceptible to internal seepage erosion.<br />

4.2.1.3. PRESENCE OF COLLAPSIBLE HOLOCENE SOILS<br />

The FRSs are underlain by low-density alluvial fan soils, which were deposited during the<br />

Holocene (during the last approximately 11,000 years). These soils have a high potential for<br />

collapse settlement <strong>and</strong> typically experience from 2 to 6 percent of vertical strain upon wetting<br />

under self-weight or low superimposed loads. The Holocene soils are underlain by Late<br />

Pleistocene alluvium consisting of dense or hard, highly stratified deposits. Unlike the Holocene<br />

soils, which are uncemented or exhibit discontinuous Stage I calcareous cementation, the Late<br />

Pleistocene soils typically possess Stage II or III cementation (the reader is referred to the “Final<br />

Geotechnical Summary Report” for a presentation of the cementation stages) <strong>and</strong> are essentially<br />

incompressible from the viewpoint of contributing to settlement of low embankments. It appears<br />

that the thickness of the Holocene soils varies considerably over short distances, suggesting that<br />

the top of the Pleistocene alluvium was an erosional surface with varying topography. The<br />

orientation of drainage channels during deposition of the Late Pleistocene <strong>and</strong> Holocene deposits<br />

may have differed from the orientation of the present-day drainage system.<br />

Based on these profiles, it appears that not all of the soils that are susceptible to collapse <strong>and</strong><br />

internal erosion were removed from beneath the embankments or from the upstream cutoff<br />

trenches during construction of the dams, nor do the existing central filters in the embankments<br />

extend all the way through these soils <strong>and</strong> into incompressible soils that are not susceptible to<br />

internal erosion. Compression (collapse) of the softer, uncemented soils beneath the<br />

embankments may have resulted in differential settlement <strong>and</strong> cracking of the dams. Cracks that<br />

extend to the bottom of the embankments may be in contact with erodible soils, resulting in the<br />

potential presence of internal erosion pathways along the embankment-foundation interface<br />

below the central filters.<br />

USDA- NRCS <strong>Jan</strong>uary <strong>2013</strong><br />

Kimley-Horn <strong>and</strong> Associates, Inc. Page 21

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!