NYRIP ADDENDUM.pdf - Yap State Government
NYRIP ADDENDUM.pdf - Yap State Government
NYRIP ADDENDUM.pdf - Yap State Government
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Department of Public Works & Transportation<br />
Contracts & Engineering Management Division<br />
<strong>Yap</strong> <strong>State</strong> <strong>Government</strong>, Federated <strong>State</strong>s of Micronesia<br />
P.O. Box 327 Colonia, <strong>Yap</strong> FM 96943<br />
Tel. no: (691)350-4131, 350-3776 or 3877 Fax no: (691) 350-5225<br />
Email: contracts@mail.fm<br />
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
<strong>ADDENDUM</strong> NO. 1<br />
November 29, 2010<br />
The following changes shall be incorporated into and shall become part of the plans,<br />
specifications, and contract documents for the project:<br />
A. Mobilization:<br />
The Mobilization Payments shall be made for costs associated with establishment of a<br />
camp, yard, and offices, shipment of equipments, personnel, supplies, and incidentals to<br />
the project site, and for all other work and operations that must be performed or cost<br />
incurred before beginning work on the project.<br />
1. The maximum amount of the mobilization item is limited to no more than twenty (20)<br />
percent of the total contract price.<br />
2. The minimum amount of the demobilization is limited to three (3) percent of the total<br />
contract amount and is within the different bid items.<br />
3. Payments for mobilization will made as follows:<br />
a) After the Contractor’s equipment which will be needed on this project, is on site,<br />
payment of forty (40) percent of the mobilization bid item will be allowed.<br />
b) After the Contractor’s materials which will be needed on this project, is on site,<br />
payment of forty (40) percent of the mobilization bid item will be allowed.<br />
c) After the Contractor’s camp, yard, and offices are established; payment of ten<br />
(10) percent of the mobilization bid item will be allowed.<br />
d) After five (5) percent of the contract work, exclusive of mobilization insurance and<br />
bonds, is complete, payment of the remaining portion is allowed.<br />
B. Utilities:<br />
The telephone lines and pedestals, sewerlines, and manholes, waterlines and their<br />
accessories are within the roadway project easement. The Contractor shall verify the<br />
location of the utilities prior to excavation on any part of the project. Damages to the<br />
utilities shall be borne by the Contractor.<br />
C. Coral Material Dredging:<br />
A dredge site for this project is located in Yyin, Fanif, <strong>Yap</strong>. The dredging activities shall<br />
comply with the agreement between the community of Yyin and DPW&T, <strong>Yap</strong> <strong>State</strong><br />
<strong>Government</strong>. Refer to copy of the Agreement.<br />
The law requires an Environmental Impact <strong>State</strong>ment report to be prepared and<br />
submitted to EPA Board for review and approval. The process for scrutiny of the report<br />
to the level of final approval is lengthy and can easily take up to 90 days.<br />
When the final approval is made, the mitigation measures shall be implemented<br />
immediately before and during the actual dredging operation. At this phase, three sets of<br />
plans shall be prepared and submitted to EPA Board for review and approval.<br />
Erosion Sediment Control Plan (ESCP) and Environmental Protection Plan (EPP) shall<br />
be prepared by the Contractor to base upon the approved final EIS. The Water Quality<br />
Page 1 of 5<br />
Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010
Monitoring Plan (WQMP) shall be prepared by the Contracting Officer. The Contractor<br />
shall comply with the recommendations derived from the WQMP.<br />
The following are the General Guidelines of said plans.<br />
1. Erosion and Sediment Control Plan (ESCP)<br />
The ESCP should include, but in not limited to, the following points:<br />
• Introduction/Purpose<br />
• Project Description<br />
• Project Site<br />
‣ Existing site description<br />
‣ Current plant/animal life and habitat<br />
‣ Current state of coral reef, fish population, other organisms<br />
‣ Water flow-tides, currents<br />
• Dredging Plan – Map, Quantity, Methodology, etc.<br />
• Dredging Schedule<br />
• Sediment/Turbidity control measures<br />
‣ Water Quality objectives<br />
‣ Sediment characterization<br />
‣ Predicted flow rates and direction<br />
‣ Control Measures<br />
o Dredging practices – equipments, methodology<br />
o Floating turbidity curtains<br />
o Silt fences – land-based activities<br />
o Dredging sequencing/timing<br />
o Berm Construction<br />
‣ Stockpiling of dredge material<br />
‣ Disposal of unsuitable material, including vegetation<br />
‣ Shoreline rock walls<br />
• Maintenance of protective measures<br />
‣ Turbidity curtains<br />
‣ Silt fences<br />
‣ Berms<br />
‣ Walls<br />
2. Environmental Protection Plan (EPP)<br />
The EPP should include, but is not limited to, the following points:<br />
• Introduction/Purpose<br />
• Project Description<br />
• Protection of natural resources<br />
‣ Water Resources<br />
‣ Historical, Cultural, and Archeological Resources<br />
‣ Biological Resources<br />
‣ Land Resources – including limits of activities<br />
• Petroleum hydrocarbon use and storage<br />
‣ Gasoline<br />
‣ Hydraulic fluid, diesel, lubricants, grease<br />
‣ Oily wastes<br />
‣ General requirements for motorized equipment<br />
• Erosion and sediment control measures & maintenance – land based only<br />
• Waste Management<br />
‣ Dredging/Construction and solid waste<br />
Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />
Page 2 of 5
‣ Sanitary waste<br />
‣ Chemical waste<br />
‣ Hazardous waste<br />
• Air Pollution<br />
‣ Particualates<br />
‣ Smokes<br />
‣ Motorized vehicles/machinery emissions<br />
• Noise Pollution<br />
• Typhoon/adverse weather contingency plan<br />
• Reference<br />
• Appendix – maps, erosion control measures, silt fence installation<br />
schematics, etc.<br />
3. Water Quality Monitoring Plan (WQMP)<br />
The WQMP should include, but is not limited to, the following points:<br />
• Introduction/purpose<br />
• Environmental setting<br />
‣ Site Description<br />
‣ Tides/currents<br />
‣ Sensitive receptors<br />
• Water Quality criteria and objectives<br />
• Baseline Sampling – pre dredging<br />
• Operational sampling – Sampling and Analysis Plan (SAP)<br />
‣ Sample Locations – weather, current, and tide related; up and down<br />
gradient<br />
‣ Sampling equipment and methodologies<br />
‣ Sample timing – regular and storm events<br />
‣ Quality Control/Quality Assurance<br />
• Reporting – format and frequency<br />
• Corrective measures implementation<br />
• Training requirements for sampling and testing staff<br />
• Appendix – Water classification map<br />
D. Project Sign:<br />
On commencement of work on this project, the Contractor shall furnish and erect a<br />
project sign identifying the project in accordance with the instructions of, and in a<br />
location selected by the Contracting Officer. The Contractor shall maintain the sign in<br />
good condition throughout the project construction period, and upon completion, remove<br />
the sign from the premises. No other signs other than those authorized in writing shall be<br />
allowed on the project.<br />
E. Unscheduled Items:<br />
This bill allows for the Contractor to list and price any unscheduled items, which are<br />
necessary for the completion of the works specified, but which have not been scheduled.<br />
Prices shall include the cost of all equipment, materials, labor, profit, and overheads for<br />
the completion of the unscheduled items.<br />
F. Existing Culverts/Bridges:<br />
The existing culverts/bridges throughout the entire length of the roadway, for those<br />
shown on the plans and the others not shown on the plan shall be cleared of vegetation<br />
and remove of accumulated soils and debris (de-clogging). A list of these culverts and<br />
bridges with condition of each shall be provided to the Contracting Officer during the first<br />
Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />
Page 3 of 5
month of field work. The cost of this work shall be fitted in the most appropriate item of<br />
work.<br />
G. Existing Pathways, Driveways, and Intersections:<br />
The existing road intersections, driveways, and pathways throughout the entire length of<br />
the roadway, for those shown on the plans and the others not shown on the plans shall<br />
remain and shall have improved access from the project roadway to every single one of<br />
them. The cost of this work shall be fitted in the most appropriate item of work.<br />
H. Quarry Site:<br />
If the Contractor needs quarry materials, it therefore shall find the source and make all<br />
preparatory works and pay any associated costs.<br />
I. Earth Moving Permit:<br />
The clearing, grubbing, earthwork, quarry work, dredging work, and hauling of soil<br />
materials shall have a valid Earth Moving Permit from EPA and shall be acquired by the<br />
Contractor prior to any earthmoving activities.<br />
J. Additional Technical Requirements:<br />
The following set of Technical Requirements shall be added to the project specifications<br />
and shall become part of the contract documents for the project. The Contractor shall<br />
carefully review and evaluate the additional provisions and requirements as stated<br />
herein and inform the Contracting Officer of any discrepancies and conflicting sections.<br />
The Contracting Officer shall review the issue(s) and shall come up with the<br />
Information/Instructions within 3 days from receipt of RFI.<br />
1. Series 100 – Preliminaries and General Description of Works.<br />
2. Series 200 – Environmental Protection<br />
3. Series 300 – Acheological Deposits and Recovery<br />
4. Series 500 – Maintaining of Traffic<br />
5. Series 900 – Subbase Coarse<br />
6. Series 1000 – Cement Treated Base Coarse<br />
7. Series 1100 – Bituminous Prime Coat<br />
8. Series 1800A – Bituminous Tack Coat<br />
9. Series 1800B – Bituminous Hot Mix Pavement<br />
K. Revisions on Final Elevation on Low-lying Areas as shown on Drawing Plans:<br />
The final road elevation on low-lying areas of the road shall be adjusted as follows:<br />
From STA 5+00 at Centerline Elevation of 10.10ft, the roadway<br />
shall be redesign to smoothly connect back to the proposed<br />
elevation at the preceding station and transition forward to the<br />
existing road elevation as per Standard Vertical Curve Design.<br />
Furthermore, the redesign of vertical curves along the Road<br />
Centerline to STA 68+00 at Elevation 15.63ft shall be treated<br />
for a uniform connection to proposed elevation at station ahead.<br />
Second low-lying area is from STA 95+00 at Elevation 8.88ft to<br />
STA 106+00 at Elevation 15.83ft with the same recommendation<br />
for redesign work as per indicated guidelines above.<br />
The third low-lying area is from STA 109+00 at Elevation 25.47ft<br />
to STA 124+00 at Elevation 23.26ft with the same recommendation,<br />
also for redesign work as indicated guidelines above.<br />
Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />
Page 4 of 5
Within the low-lying areas, the road superelevation shall remain<br />
as per original design. The existing ditches, existing sidewalks,<br />
existing sewer system, shore protection, existing water system<br />
shall be adjusted as required by the redesign requirements.<br />
The Contractor is responsible for the re-designing of, but not<br />
limited to, the Final Elevations, Vertical Curves<br />
(BVC, PIVC, EVC), Superelevations, Horizontal Curve, Elevation<br />
at Driveways, Pathways, and Road Intersections, Drainage,<br />
Concrete Ditch, Sidewalks, Volumes of Cut and Fill.<br />
The redesigning works shall be finalized prior to Earthwork Activites.<br />
L. Construction Term:<br />
The construction duration shall allow for project completion including the rainy months<br />
from April to December and the difficulties in Materials and Equipments shipment within<br />
twelve (12) months.<br />
M. Drainage Crossing at Carraigeway:<br />
Delete all proposed drainage crossings (culverts) at the following locations:<br />
1. STA 4+89.21<br />
2. STA 9+39.40<br />
3. STA 55+82.31<br />
4. STA 91+08.81<br />
5. STA 118+00.43<br />
6. STA 189+15.82<br />
N. Existing Retaining Walls:<br />
The following retaining walls shall not be removed at stations:<br />
1. STA 20.68 (driveway is located after the existing retaining wall)<br />
2. STA 106+74.83 to STA 108+44.08<br />
Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />
Page 5 of 5
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
DETERMINATION<br />
This Preliminary Environmental Impact <strong>State</strong>ment is prepared according to <strong>Yap</strong> <strong>State</strong><br />
Environmental Protection Agency (EPA) regulations Title II - Environmental Impact<br />
Assessment (EIA), Part II Preliminary Environmental Impact <strong>State</strong>ment, pursuant to the<br />
procedures set out in Environmental Quality Protection YSC, Title 18 Conservation and<br />
Resources.<br />
The purpose of the draft EIA process is intended to help the general public and government<br />
officials make decisions with the understanding of the environmental consequences of a<br />
proposed action, and take actions consistent with the goal of protecting, restoring, and<br />
enhancing the environment.<br />
In addition, this process is designed to: (a) integrate the EIA process into early planning of<br />
projects to ensure timely consideration of environmental factors and to avoid delay; and (b)<br />
identify at an early stage the significant environmental issues requiring further study and deemphasize<br />
insignificant issues, thereby defining the scope of the EPA.<br />
It is not the intent of this process to require an exhaustive EIA for all projects large and<br />
small. The degree of environmental assessment detail for a project depends upon the<br />
significance of its potential environmental impact.<br />
LYON ASSOCIATES<br />
i
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
ABREVIATIONS AND<br />
ACRONYMS<br />
BMP<br />
CBD<br />
CBO<br />
COM<br />
COP<br />
EIA<br />
EIS<br />
EPA<br />
ENSO<br />
FSM<br />
IUCN<br />
MAREPAC<br />
NBSAP<br />
NEMS<br />
NGO<br />
NTP<br />
SPREP<br />
TTPI<br />
UN<br />
WSO<br />
Best Management Practices<br />
Convention on Biological Diversity<br />
Community-based Organizations<br />
College of Micronesia<br />
Conference of the Parties<br />
Environmental Impact Assessment<br />
Environmental Impact <strong>State</strong>ment<br />
YAP <strong>State</strong> Environmental Protection Agency<br />
El Nino/Southern Oscillation Phenomena<br />
Federated <strong>State</strong>s of Micronesia<br />
International Union for the Conservation of Nature and Natural<br />
Resources<br />
Marine Resources Pacific Consortium<br />
National Biodiversity Strategy and Action Plan<br />
National Environmental Management Strategies<br />
Non-governmental Organization<br />
Notice to Proceed<br />
South Pacific Regional Environment Program<br />
Trust Territory of the Pacific Islands<br />
United Nations<br />
Weather Service Office<br />
LYON ASSOCIATES<br />
ii
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
TABLE OF CONTENTS<br />
1 BRIEF DESCRIPTION OF PROJECT ....................................................................................... 1-1<br />
1.1 Location ............................................................................................................................ 1-1<br />
1.2 Brief Description of the Existing Road ............................................................................. 1-2<br />
1.3 Proposed Road Improvements ........................................................................................ 1-2<br />
1.4 Scope of Work .................................................................................................................. 1-2<br />
1.5 Project Schedule .............................................................................................................. 1-2<br />
2 ENVIRONMENTAL SETTING OF PROJECT ............................................................................ 2-4<br />
2.1 Geology ............................................................................................................................ 2-4<br />
2.2 Physical Features ............................................................................................................. 2-6<br />
2.3 Climate ............................................................................................................................. 2-7<br />
2.4 Soils & Drainage ............................................................................................................... 2-8<br />
2.5 Wetlands ........................................................................................................................ 2-12<br />
2.6 Forests ........................................................................................................................... 2-12<br />
2.7 Noteworthy Fauna .......................................................................................................... 2-13<br />
2.8 Noteworthy Flora ............................................................................................................ 2-14<br />
2.9 Land Use ........................................................................................................................ 2-14<br />
2.10 Population ...................................................................................................................... 2-15<br />
2.11 Economic Issues ............................................................................................................ 2-17<br />
2.12 Cultural History ............................................................................................................... 2-22<br />
3 GENERAL DESCRIPTION OF PROJECT EFFECTS ............................................................... 3-1<br />
3.1 Problems with the Existing Road Segments .................................................................... 3-1<br />
3.2 Disturbances and Threats to Wetlands ............................................................................ 3-3<br />
3.3 Hydrological & Biophysical Values ................................................................................... 3-3<br />
3.4 Road Improvement Construction ..................................................................................... 3-3<br />
4 POSSIBLE ENVIRONMENTAL IMPACT CHECKLIST ............................................................. 4-4<br />
4.1 Initial Environmental Assessment Checklist .................................................................... 4-4<br />
4.2 Earth- Will the proposed project result in: ........................................................................ 4-4<br />
4.3 Air- Will the proposed project result in: ............................................................................ 4-5<br />
4.4 Water- Will the proposed project result in: ....................................................................... 4-6<br />
4.5 Plant Life- Will the proposed project result in: .................................................................. 4-7<br />
4.6 Animal Life- Will the proposed project result in: ............................................................... 4-7<br />
4.7 Noise- Will the proposed project result in: ....................................................................... 4-8<br />
4.8 Land Use- Will the proposed project result in: ................................................................. 4-8<br />
4.9 Natural Resources- Will the proposed project result in: ................................................... 4-8<br />
4.10 Risk of Upset- Will the proposed project result in: ........................................................... 4-8<br />
4.11 Population- Will the proposed project result in: ................................................................ 4-9<br />
4.12 Housing- Will the proposed project result in: ................................................................... 4-9<br />
4.13 Transpiration- Will the proposed project result in: ............................................................ 4-9<br />
4.14 Public Services ................................................................................................................. 4-9<br />
4.15 Utilities ............................................................................................................................ 4-10<br />
4.16 Human Health- Will the proposed project result in: ........................................................ 4-10<br />
4.17 Aesthetics- Will the proposed project result in: .............................................................. 4-10<br />
4.18 Recreation- Will the proposed project result in: ............................................................. 4-10<br />
4.19 Cultural Resources- Will the proposed project result in: ................................................ 4-10<br />
4.20 Others- Will the proposed project result in: .................................................................... 4-11<br />
5 ALTERNATIVES TO MITIGATE ADVERSE IMPACTS ........................................................... 5-12<br />
5.1 Design Considerations ................................................................................................... 5-12<br />
5.2 Erosion Control Plan ...................................................................................................... 5-13<br />
5.3 Monitoring Plan .............................................................................................................. 5-14<br />
5.4 Traffic Control Plan......................................................................................................... 5-14<br />
6 THE NEED FOR THE PROPOSED PROJECT ......................................................................... 6-1<br />
6.1 Summary .......................................................................................................................... 6-1<br />
7 REFERENCE ............................................................................................................................. 7-2<br />
LYON ASSOCIATES<br />
iii
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
ALL THE EXHIBITS<br />
Exhibit A Ziemer's Observations During Trip To FSM October 28 to November 8, 1990, <strong>Yap</strong><br />
Except<br />
LIST OF TABLES<br />
Table 2-1 Seasonal Precipitation Summary from 1953 to 2006 ..................................................... 2-7<br />
Table 2-2 Monthly Precipitation Summary from 1953 to 2006 ....................................................... 2-8<br />
Table 2-3 Population Distribution: 1930 to 2009 .......................................................................... 2-16<br />
Table 2-4 Total Employment by Sector: FY 2002 to FY 2006 ...................................................... 2-17<br />
Table 2-5 Registered Motor Vehicles in <strong>Yap</strong> ................................................................................ 2-20<br />
Table 2-6 Passenger Arrivals and Departures on Foreign Aircraft and Vessels: 2000 to 2007 .. 2-21<br />
LIST OF FIGURES<br />
Figure 1-1 Road Improvement Project Limits ................................................................................ 1-1<br />
Figure 2-1 Geological Map of <strong>Yap</strong> ................................................................................................. 2-4<br />
Figure 2-2 Soil Map of Project Region ........................................................................................ 2-10<br />
Figure 2-3 Soil Map Legend ........................................................................................................ 2-11<br />
Figure 2-4 Percentage of Land Ownership by <strong>State</strong>:2001 .......................................................... 2-15<br />
Figure 2-5 <strong>Yap</strong> <strong>State</strong> Population Distribution by Age .................................................................. 2-16<br />
Figure 2-6 Dollar Value of Local Markets' Purchases of Agricultural Products by <strong>State</strong> ............ 2-18<br />
Figure 2-7 Copra Production by Volume (Tons), FSM: 1997 to 2006 ......................................... 2-18<br />
Figure 2-8 Annual Inflation Rates: 4th Qtr 2004 to 4th Qtr 2006 ................................................. 2-19<br />
Figure 2-9 Registered Motor Vehicles is FSM: 1999-2006 ......................................................... 2-20<br />
Figure 2-10 <strong>Yap</strong> Communication services: 1997 to 2006 ............................................................. 2-22<br />
Figure 3-1 Existing Watershed Map Along the Project ................................................................. 3-2<br />
Figure 4-1 Slope Stabilization Matting ........................................................................................... 4-4<br />
Figure 4-2 Slope Stabilization with Mulching ................................................................................. 4-5<br />
Figure 4-3 Watering Trucks for Dust Control ................................................................................. 4-6<br />
Figure 4-4 Secondary Containment .............................................................................................. 4-9<br />
Figure 5-1 Silt Fencing for Sediment Control .............................................................................. 5-12<br />
Figure 5-2 Silt Fencing for Cross Section .................................................................................... 5-12<br />
Figure 5-3 Stormwater Outlet Protection ..................................................................................... 5-13<br />
LYON ASSOCIATES<br />
iv
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
1 BRIEF DESCRIPTION OF PROJECT<br />
1.1 Location<br />
1.1.1 The project is located in central to northern <strong>Yap</strong> <strong>State</strong> in the Federated <strong>State</strong>s of<br />
Micronesia. The beginning of the project (BOP) is at the hospital intersection with<br />
the main road to Keng. It proceeds north and end of the project (EOP) terminates<br />
at the western edge of Tagireeng Bridge. This segment of the road travels along<br />
the coastline through the villages of Dogor, Makal, Tafgif, Rumuu, and Garfey. The<br />
approximate length of this road segment is 4.06 miles (6.55 kilometers). See<br />
Figure 1-1 below.<br />
Figure 1-1<br />
Road Improvement Project Limits<br />
Source: USGS<br />
LYON ASSOCIATES 1-1
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
1.2 Brief Description of the Existing Road<br />
1.2.1 The existing road was constructed in the late 1980’s. The <strong>Yap</strong> Road Improvements<br />
- Phase V Soil Investigation Report was in draft form 18 August 1986 by<br />
Geotesting Inc. It was prepared for GMP Associates, Guam. The As-Built Drawings<br />
HT-A-01 through HT-A-15 (presumably) prepared by GMP at the same time.<br />
1.2.2 This project will begin from <strong>Yap</strong> Memorial Hospital to Tangireeng Bridge. This<br />
segment of the road is about 4.06 miles (6.53 k) with 2 inches (5 cc) asphalt<br />
pavement, two-way 9 foot (2.7 m) wide traveling lanes, intermittent concrete<br />
shoulder on both sides and 4 ft sidewalk on the right side only, reinforced concrete<br />
culverts, 4 ft (1.2 m) wide concrete line ditch and about 1.4 miles (2.3 k) of slope<br />
protection. <strong>Yap</strong> <strong>State</strong> replaced the asphalt pavement with portland concrete<br />
pavement in segments of the road particularly that had deteriorated. Most of these<br />
segments were along the shoreline. The lowest elevation of the existing road is<br />
apparently 6 feet (1.8 m) above mean sea level.<br />
1.3 Proposed Road Improvements<br />
1.3.1 The project scope of work include surface road milling, sub-grade preparation,<br />
resurfacing of the 4.06 miles (6.53 k) long, 18 feet (5.5 m) wide roadway (no<br />
widening), elevating the road level to a minimum of 8.00 feet (2.4 m) above Mean<br />
Sea Level in respect to the global warming effects and upgrade of drainage<br />
system, walkways, shoulders, curbs, driveways and effected utilities.<br />
1.4 Scope of Work<br />
1.4.1 The <strong>State</strong> of <strong>Yap</strong>, Department of Public Works and Transportation selected and<br />
signed a contract with Lyon Associates Inc., based in Honolulu, Hawaii with offices<br />
in nearby Pohnpei, FSM and Manila, Philippines.<br />
1.4.2 In part this contract encompasses establishment of ground control, complete<br />
topographic survey of existing ground conditions, existing road condition,<br />
location/elevations of all surface and drainage structures and reduction of all field<br />
data, including, plotting onto plan/profile sheets, preparation of plans,<br />
specifications, cost estimates, basis of design and design calculations.<br />
1.4.3 Furthermore, the Consultant shall prepare the preliminary environmental impact<br />
statement, a climate change report and construction documents.<br />
1.5 Project Schedule<br />
1.5.1 The <strong>State</strong> of <strong>Yap</strong>, Department of Public Works and Transportation issued the<br />
Notice to Proceed (NTP) for the design services for this project was issued on<br />
December 9, 2009. The completion date is September 8, 2010.<br />
1.5.2 Work shall begin no later than twenty-one (21) calendar days from the issuance of<br />
the “Notice to Proceed”;<br />
1.5.3 35% submittal sixty (60) calendar days after commencement of work;<br />
1.5.4 60% submittal forty-five (45) calendar days after receipt of 35% review comments;<br />
LYON ASSOCIATES 1-2
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
1.5.5 90% submittal forty-five (45) calendar days after receipt of 60% review comments;<br />
and<br />
1.5.6 Final submittal thirty (30) calendar days after receipt of 90% review comments.<br />
LYON ASSOCIATES 1-3
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2 ENVIRONMENTAL SETTING OF PROJECT<br />
2.1 Geology<br />
2.1.1 <strong>Yap</strong> Islands are located in the western zone of Federated <strong>State</strong>s of Micronesia,<br />
and comprise four main islands: <strong>Yap</strong>, Map, Tomil, and Rumong. <strong>Yap</strong> Islands are<br />
composed mainly of accretional metamorphic rocks and volcanic rocks,<br />
accompanied by coral sand and mangrove mud. <strong>Yap</strong> Islands comprise an island<br />
arc system on the eastern convergent margin of Philippine Plate, connecting to the<br />
Palau island arc southward, and to Izu-Mariana arc northward. There are many<br />
Micronesia islands in the east of <strong>Yap</strong> islands, such as Ulithi, Woleai, Satawal and<br />
Ifalik, which are located in the Pacific Ocean plate region, and are oceanic<br />
volcanics or atolls developed on the descending volcano.<br />
2.1.2 Basement Rocks in the <strong>Yap</strong> Islands The geological map in Figure 2-1 is cited from<br />
(Johnson et al. 1960). The pre-Quaternary rocks are divided into <strong>Yap</strong> formation,<br />
Map formation, and Tomil volcanics in order of formation age (Tayama, 1935). The<br />
<strong>Yap</strong> formation constitutes the basement and is exposed all over the four islands.<br />
The <strong>Yap</strong> formation is composed mainly of greenschist and amphibolite of basalt<br />
origin.<br />
2.1.3<br />
Figure 2-1<br />
Geological Map of <strong>Yap</strong><br />
Source: Johnson et al., 1960<br />
2.1.4 The metamorphic grade increases eastward from greenschist facies (western<br />
coast of <strong>Yap</strong> island) to amphibolite facies (eastern coast of Tomil island). Among<br />
three island arcs; Izu-Mariana, <strong>Yap</strong> and Palau, the metamorphic rocks occur only<br />
on the <strong>Yap</strong> arc. Both tholeiite and calc-alkaline rock series common in island arc<br />
LYON ASSOCIATES 2-4
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
region are observed in the Palau arc, but no metamorphic rocks (Nedachi et al.,<br />
1996). The <strong>Yap</strong> formation is derived from melange trapped in the <strong>Yap</strong> trench.<br />
Ultramafic rocks intrude into the amphibolite. The rock is clinopyroxinite to olivine<br />
websterite, and the main rock-forming mineral is clinopyroxene, associated with<br />
olivine, orthopyroxene, plagioclase and magnetite. The rocks are not<br />
metamorphosed and the serpentinization is so weak.<br />
2.1.5 The Map formation postdates the <strong>Yap</strong> formation and is composed mainly of<br />
tectonic breccia with the fragments of metamorphic rocks of the <strong>Yap</strong> formation and<br />
other igneous rocks. Cole et al. (1960) described foraminifera in the sandstones<br />
and siltstones of Map formation, suggesting Miocene as the formation age.<br />
Johnson et al. (1960) thought that the igneous fragments in the Map formation<br />
were of Miocene melange, but the metamorphic grade of these fragments is far<br />
lower than that of the <strong>Yap</strong> formation. Even if the formation might be accretional<br />
member, the thrusting mechanism is different from that of the <strong>Yap</strong> formation.<br />
2.1.6 Previous workers have reported that the Tomil formation was deeply weathered.<br />
The was confirmed by Nedachi et al (1996) with strong and wide alteration by<br />
hydrothermal solution, although the rocks were overprinted by weathering. At<br />
almost all area of the four islands, we observed the network veins of hydrothermal<br />
argillization. Kaolinite is dominant, and in some places alunite can be detected.<br />
The fluid inclusions of quartz in the hydrothermal vein are homogenized at the<br />
temperature less than 200℃. Rytuba and Miller (1989) reported the gold<br />
mineralization at the northeastern end of the Tomil island, which might have been<br />
produced by a series of hydrothermal activity. The hydrothermal alteration play a<br />
role in accelerating the strong weathering, which differ slightly from ordinary<br />
laterite, characterized by the depletion of Fe2O3, Al2O3 and SiO2, and by soil<br />
poor in nutrients. These soil materials generally are not suitable for vegetation and<br />
agriculture, but kaolinite is used for ceramics. Hence a highly concentrated area of<br />
kaolinite might be a mineral resource.<br />
2.1.7 Island arcs along convergent boundary of plates often repeat to rise and escend.<br />
Then raised coral reefs are well developed in tropical and sub-tropical zone.<br />
However, it is a unique characteristic that there is no big raised coral reef nor big<br />
limestone in the <strong>Yap</strong> islands. Recent raised coral reef of small scale is observed in<br />
the offing, and 2 meters top of coral reef is exposed at low tide.<br />
2.1.8 Nedachi et al (1996) collected samples from the 35 sites in the lagoon, also<br />
included measurement of temperature of sea water, pH, Eh, content of dissolved<br />
oxygen, dielectric constant and salinity. In the laboratory, heavy minerals and clay<br />
minerals were analyzed using X-ray Diffraction, and sulfur isotopic composition<br />
were measured by VG optima isotope ratio mass spectrometer. Based on field<br />
observations, the results are as follows:<br />
2.1.9 The detrital material transported from the land area is not so abundant. Mangrove<br />
forest could have played an important role in precipitating detrital material from the<br />
land area. Almost all fragments from the outer zone of the lagoon are coral<br />
materials. The intense deposition of fragments from basement rock is observed in<br />
some places. Rather deep (20-50m) sea floor of small hollow lagoon near the<br />
western coast of the <strong>Yap</strong> island is occupied by thick mud layer transported from<br />
basement rock. The reason might be that the transportation by the current of<br />
seawater is very low, and that large fragments may not have been transported<br />
from both land and reef. On the other hand, pebble, granule and sand are<br />
predominant in the channels near Colonia harbor, and man-made channel<br />
LYON ASSOCIATES 2-5
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
between <strong>Yap</strong> and Tomil islands. The amount of organic material increases in the<br />
channel closest to the coast. Even in the channel near the coast, the activity of<br />
sulfate reducing bacteria is not so strong, and there is no stench of hydrogen<br />
sulfide. Under the microscope, framboidal pyrite can be observed in the mud<br />
samples in the channel near the coast.<br />
2.1.10 Clay mineral assemblage of sediments reflects directly the geology in the land<br />
area. Chlorite and smectite are predominant in the surrounding lagoon of the <strong>Yap</strong><br />
and Map formations, and kaolinite and gibbsite are frequently recognized around<br />
the Tomil volcanics. The sediments contain sulfur up to about 6000ppm. The<br />
sulfur isotopic ratios were measured and decreases with increasing S content of<br />
the sediment. The relationship between the sulfur isotope and S content suggests<br />
that S is fixed by bioactivity; sulfate reducing bacteria, as pyrite in detrital<br />
sediments.<br />
2.1.11 On the other hand, the values of coral sand are similar to that of sea water.<br />
Although we could not confirm the S species in the coral sediments, it can be<br />
pointed that sulfate reducing bacteria do not survive in the reef zone and coral<br />
sand. Clearly sediments in the channel near the coast line show lower sulfur<br />
isotopic ratio value, due to biogenic pyrite. Notably, the chlorite-smectite-organic<br />
matter mud in the small depression on coral near Tageegiin Village. The S content<br />
is 6100ppm.<br />
2.1.12 Although the content of dissolved oxygen of sea water is not low, the bottom of the<br />
hollow might be suitable reducing environment for sulfate reducing bacteria to<br />
survive actively. Since the human population is low, the natural environments<br />
might be suitable for bioactivity. Low sulfur isotope values are also obtained from<br />
the channel near Keeng and Makai, and the southern entrance of artificial channel<br />
between <strong>Yap</strong> and Tomil islands. Many people are living near these areas, and the<br />
sediments contain abundant organic matters, which maintain the reducing<br />
environment. The sulfur isotope value and S content might be good indicator of<br />
impact caused by human activity. On the other hand, sulfate reducing bacteria<br />
does not survive in the outer zone of the lagoon.<br />
2.1.13 In summary the <strong>Yap</strong> islands are composed mainly of metamorphic rocks of<br />
greenschist to amphibolite derived from oceanic tholeiite, and a lack of raised coral<br />
reef. These geological features might be related to the slow ascending history of<br />
<strong>Yap</strong> island arc system. Strong hydrothermal alteration is observed everywhere,<br />
and might have played a role in producing poor soils for vegetation or for other<br />
agriculture. However kaolinite might become a useful resource for ceramics if high<br />
concentration areas would be discovered. Sulfur isotopic ratio might be useful to<br />
evaluate the natural environment, or to determine the anthropogenic impact on the<br />
environment.<br />
2.2 Physical Features<br />
2.2.1 <strong>Yap</strong> <strong>State</strong> consists of 134 islands and atolls of which 22 are populated, stretching<br />
across more than 100,000 square miles of total area. The main island of <strong>Yap</strong> is<br />
made up of four high volcanic islands and accounts for 38 % of <strong>Yap</strong>’s total 49.7<br />
square miles of land area. Colonia, the <strong>State</strong>'s Capital and commercial center is<br />
located here. Most of the outer islands, stretching nearly 600 miles east of <strong>Yap</strong><br />
Island, are coral atolls.<br />
LYON ASSOCIATES 2-6
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.2.2 The landscape consists of rolling hills and lowlands covered with thick jungle like<br />
vegetation. Most of the coastal areas are mangroves with occasional coral<br />
beaches.<br />
2.2.3 Mangrove forest occurs widely around the coasts of all four of the main islands,<br />
and is especially well developed on mudflats at the mouths of drainage systems.<br />
Sheltered coasts and embayments support broad continuous belts of mangrove<br />
150-450 m wide, but along exposed shorelines, the mangrove stands become<br />
much narrower and discontinuous. The largest stands are found in Munguuy Bay<br />
and Yunearawey Passage between Maap and Tamil-Gagil, near Gachpar on the<br />
southeast coast of Tamil-Gagil, around the inner margin of Qatliirow Embayment<br />
and in the northern portion of the Tagireeng Canal between Tamil-Gagil and <strong>Yap</strong><br />
Proper, along the east coast of <strong>Yap</strong> Proper from Peelaek Channel south to<br />
Dechumur village, and along the west coast of <strong>Yap</strong> Proper between the villages of<br />
Qokaaw and Raeng. A continuous belt of mangroves, on average about 450 m<br />
wide, lines almost the entire coastline of southeastern <strong>Yap</strong> Proper, and is most<br />
extensive between the villages of Yinuuf and Luweech, where it penetrates 1.5 km<br />
inland. The mean tidal variation in <strong>Yap</strong> is 0.9 m.<br />
2.3 Climate<br />
2.3.1 The climate is humid tropical with an average annual rainfall of 3,087 mm (122<br />
inches) and a mean annual temperature of 27 o C (81 o F) . Relative humidity ranges<br />
from 65 to 100 percent, with an annual average of 83 percent.<br />
2.3.2 A season of trade winds and drought extends from December to April. The wet<br />
season, between July and October, accounts for about half of the annual rainfall.<br />
Typhoons are especially prevalent in May-June and November. The average<br />
number of typhoons is three per year and severe storms can wreak massive<br />
devastation in the Outer Islands .<br />
2.3.3 A seasonal summary of precipitation data from Station number 914951<br />
for <strong>Yap</strong> Island Weather Service Office (WSO) at the airport is presented<br />
below in Table 2-1.<br />
Table 2-1 Seasonal Precipitation Summary from 1953 to 2006<br />
>= >= >= >=<br />
Mean High Year Low Year 1 Day Max.<br />
0.01<br />
in.<br />
0.10<br />
in.<br />
0.50<br />
in.<br />
1.00<br />
in.<br />
in. in. - in. - in. Date # Days<br />
Annual 121.99 164.24 1996 88.84 1983 13.17 19820621 257 171 73 35<br />
Winter 23.11 50.16 1997 8.28 1973 8.96 19580114 61 35 13 6<br />
Spring 21.19 39.41 1999 3.16 1998 9.09 19670509 56 33 12 5<br />
Summer 42.52 69.6 2002 25.27 1995 13.17 19820621 72 53 26 13<br />
Fall 35.17 50.72 2003 21.62 1994 8.91 19601130 68 49 22 10<br />
Source Western Regional Climate Center mailto:wrcc@dri.edu<br />
LYON ASSOCIATES 2-7
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.3.4 A monthly summary of precipitation data from Station number 914951<br />
for <strong>Yap</strong> Island Weather Service Office (WSO) at the airport is presented<br />
below in Table 2-2.<br />
Table 2-2 Monthly Precipitation Summary from 1953 to 2006<br />
>= >= >= >=<br />
Mean High Year Low Year 1 Day Max.<br />
0.01<br />
in.<br />
0.10<br />
in.<br />
0.50<br />
in.<br />
1.00<br />
in.<br />
in. in. - in. - in. Date # Days<br />
Jan 7.76 23.08 1955 1.25 1983 8.96 14/1958 21 12 4 2<br />
Feb 5.63 13.36 1962 0.27 1983 5.77 8/1/62 18 9 3 1<br />
Mar 5.87 14.21 1972 0.54 1998 5.09 1/1/63 18 9 3 2<br />
April 6.06 18.15 1956 0.21 1998 6 3/1/67 18 10 3 1<br />
May 9.25 22.14 2003 1.47 1993 9.09 9/1/67 21 14 6 2<br />
June 12.63 32.01 1982 4.69 1959 13.17 21/1982 24 17 8 4<br />
July 14.77 34.71 1969 6.51 1953 8.79 18/2003 24 18 9 4<br />
Aug 15.12 29.44 1953 5.13 1973 6.69 28/1987 24 18 9 5<br />
Sept 13.28 21.16 1996 6.41 1984 6.85 14/1978 23 17 8 4<br />
Oct 12.22 22.43 1992 2.59 1976 5.5 8/1/89 23 17 8 4<br />
Nov 9.68 20.66 1960 1.96 1957 8.91 30/1960 23 15 6 2<br />
Dec 9.73 26.89 1996 2.22 1990 5.67 24/1996 22 14 6 3<br />
Source Western Regional Climate Center mailto:wrcc@dri.edu<br />
2.4 Soils & Drainage<br />
2.4.1 According the soils map in Figure 2-2 upland soils underlain by volcanic materials<br />
(areas 1 & 3), upland soils underlain by shist (areas 4 & 5) and soils on bottom<br />
lands (areas 6, 8 &10).<br />
2.4.2 Tropical climate causes rapid rock weathering that results in subgrade materials<br />
that are very high in clays. Such materials alone are low in bearing strength and<br />
are inadequate for even light-use traffic. Therefore, ballast and/or surfacing is<br />
required to prevent rutting and to maintain trafficability. This is especially true on<br />
<strong>Yap</strong> where the bedrock consists of weathered sedimentary rocks. By far the most<br />
serious and pervasive erosion problems exist on the secondary roads. Such roads<br />
are developed by individuals. Lack of knowledge about proper road construction<br />
practices the desire to minimize costs, and problems with land ownership often<br />
lead to serious erosion problems. We saw numerous examples where road grades<br />
were too steep for the type of road construction used. Landholders were<br />
constructing roads straight up the slope to minimize construction costs or to avoid<br />
problems with land ownership. In general, subgrade and surfacing procedures on<br />
the arterial roads appear to be appropriate for the intended road uses in the FSM<br />
states. On <strong>Yap</strong>, a chemical treatment called Condor SS is being used to stabilize<br />
the subgrade. This is overlain with crushed rock aggregate which is covered with a<br />
rubberized asphalt surface. (Ziemer & Megahan 1991).<br />
2.4.3 Ziemer (1991) states that a major part of the problem on secondary roads is the<br />
direct result of the lack of subgrade stability. Use of normal practices to construct<br />
stable subgrades is not practical on these roads because of high costs. However,<br />
the chemical stabilization techniques presently being used on the arterial road in<br />
LYON ASSOCIATES 2-8
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
<strong>Yap</strong> may be effective on secondary roads. We suggest that controlled tests of the<br />
Condor SS material be attempted on secondary roads on <strong>Yap</strong>. Trials of this<br />
material may also be appropriate in the other FSM states. However, such trials<br />
should be done in cooperation with the manufacturer because of possible<br />
problems caused by the volcanic parent materials. Escobar (1984) provides<br />
background information on the use, costs, and application of Condor SS. Condor<br />
SS is a mixture of ion exchange resins and sulfuric and sulfonic acids that is<br />
designed to remove the water of hydration from subgrade clays. This allows the<br />
subgrade to be compacted to a dense, highly stable state. The mixture is applied<br />
by ripping and sprinkling or by injection into the subgrade, followed by compaction<br />
with a vibrating roller (Escobar, 1984). The material is extremely acidic (pH 1.25)<br />
so care should be used to avoid spills and to prevent overland flow runoff from<br />
treated areas immediately after application. The injection procedure minimizes the<br />
opportunity for offsite pollution and is recommended for that reason.<br />
2.4.4 The inherent strength of slopes in the FSM is relatively low because of the high<br />
weathering of the bedrock that has occurred. Ziemer (1991) did see a few areas<br />
where small slope failures (landslides) had occurred on large cut slopes on the<br />
arterial roads in <strong>Yap</strong> and in Kosrae. The report continues to state that better<br />
design of dump areas for excess fill materials on <strong>Yap</strong> could have avoided some<br />
excessive erosion problems. In areas of lagoon encroachment on all states,<br />
considerable direct supply of sediments to the lagoon could be avoided by the<br />
proper installation of filter curtains to contain sediments.<br />
2.4.5 Ziemer (1969) saw a number of sites where slope protection measures were<br />
needed to help reduce both surface, and sometimes, mass erosion hazards. A<br />
variety of practices are available to accomplish this (FAO chapter 5, p. 148-166).<br />
Natural revegetation occurs rapidly in the FSM and is very effective for erosion<br />
control, but short-term measures are often needed to protect disturbed soils before<br />
natural revegetation occurs. This is especially true in areas where the potential for<br />
downslope delivery of water and sediments is high. Transplanting woody<br />
vegetation and use of various types of mulches are effective for accomplishing<br />
this.<br />
2.4.6 As a general rule, Ziemer ( recommends bridges at all channel crossings on<br />
arterial roads rather than culverts in order to minimize the possibility of clogging by<br />
debris. Channel crossings should be designed to carry at least the 25-year flow<br />
event for a given design life and chance of failure (FAO, 1989 -- p. 99).<br />
2.4.7 The soil map legend is presented in Figure 2-3. The green area represent soils on<br />
bottom lands. They are characteristically deep poorly drained soils.<br />
LYON ASSOCIATES 2-9
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Figure 2-2<br />
Soil Map of Project Region<br />
Source U.S Dept of Agriculture, Compiled in 1981<br />
LYON ASSOCIATES 2-10
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Figure 2-3<br />
Soil Map Legend<br />
Source U.S Dept of Agriculture, Compiled in 1981<br />
LYON ASSOCIATES 2-11
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.5 Wetlands<br />
2.5.1 Only these four islands possess significant wetlands, although there are some<br />
unusual stands of mangrove in the interior lagoons of some of the outer atolls.<br />
Much the most extensive wetland type is mangrove forest, which covers about<br />
1,171 ha or approximately 32.2% of the total forested area of <strong>Yap</strong>.<br />
2.5.2 Other types of wetland are very limited in extent. There are a few small saline<br />
marshes, generally along the coast adjacent to mangroves. Small stands of<br />
swamp forest occur in low wet areas just inland of mangroves (above tidal<br />
influence), in low areas along streams and in areas of impeded drainage. Many<br />
areas which probably once supported swamp forest have been converted into taro<br />
patches, and the remaining forests are now heavily disturbed, with about 85% of<br />
the forest containing secondary vegetation or agro-forest inclusions. There are<br />
also a number of small freshwater marshes in water-logged areas slightly above<br />
sea level landward of the mangroves and in depressions in upland areas. Other<br />
wetlands include a number of streams, most of which are intermittent, several<br />
small ponds, a small water storage reservoir near the capital, Colonia, and<br />
numerous small taro patches. Only one of the ponds, Machbaab Pond near the old<br />
airport in southern <strong>Yap</strong>, is permanent.<br />
2.5.3 The mangrove forest dominated by Rhizophora mucronata occurs in a broken<br />
band of variable width around all four of the main islands of <strong>Yap</strong> <strong>State</strong> and forms<br />
extensive stands in sheltered embayments.<br />
2.6 Forests<br />
2.6.1 The mangrove forests of <strong>Yap</strong> are more diverse than those of Chuuk, Pohnpei and<br />
Kosrae, and include three species which are not known to occur on the other<br />
islands Schypiphora hydrophyllacea, Ceriops tagal and Dolichandrone spathacea.<br />
The most conspicuous species in the mangrove forests are Rhizophora<br />
mucronata, R. apiculata, Bruguiera gymnorrhiza and Sonneratia alba. Rhizophora<br />
mucronata is dominant along the seaward fringe, with R. apiculata occurring<br />
behind this fringe in areas where the forest is fairly wide. Sonneratia alba becomes<br />
common along channels and towards the leeward edge of the mangrove forest,<br />
while Bruguiera gymnorrhiza and Xylocarpus granatum tend to dominate along the<br />
landward edge of the mangrove. Other species which generally occur along the<br />
landward edge of the mangrove forests are Lumnitzera littorea, Ceriops tagal and<br />
Dolichandrone spathacea. Nypa fruticans is generally found in the more brackish<br />
areas, in narrow bands along the margins of channels (Falanruw et al., 1987b).<br />
2.6.2 Species characteristic of swamp forest adjacent to mangrove forest include<br />
Dolichandrone spathacea, Heritiera littoralis, Pongamia pinnata, Cynometra<br />
ramiflora, Dalbergia candenatensis, Derris trifoliata and Acrostichum aureum. A<br />
few almost pure stands of Dolichandrone spathacea can be found, and<br />
Barringtonia racemosa is common in wetter areas. In the of swamp forests along<br />
streams and in wet inland depressions, characteristic tree species include<br />
Barringtonia racemosa, Hibiscus tiliaceus, Semecarpus venenosus, Inocarpus<br />
fagifer, Ficus tinctoria, Pandanus japensis, Cerbera manghas, Ixorea casei and<br />
Derris elliptica (Falanruw et al., 1987b).<br />
2.6.3 The plant community of the saline marshes includes Acrostichum aureum, Cyperus<br />
javanicus, Eleocharis geniculata, Fimbristylis cymosa, Paspalum distichum,<br />
LYON ASSOCIATES 2-12
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Ipomoea pes-caprae, Excoecaria agallocha, Derris trifoliata and Clerodendron<br />
inerme (Stemmermann & Proby, 1978). The vegetation of the freshwater marshes<br />
may consist of tall reeds, especially Phragmites karka, sedges, and herbaceous<br />
species such as Ludwigia hyssopifolia, L. octovalvis and Hanguana malayana<br />
(Falanruw et al., 1987b). Most of the ponds are in open savannah and support<br />
considerable rooted vegetation, including emergent species, such as Eleocharis<br />
ochrostachys, Eriocaulon sexangulare and Ischaemum polystachum, and the<br />
submerged species Blyxa sp. I. polystachum dominates the stream flora in open<br />
areas and mosses are common in cascades, but rooted vegetation is very<br />
restricted (Lobban et al., 1990). Lobban et al. (1990) collected periphyton and<br />
other visible algae from the streams and ponds, and found 12 blue-green algae,<br />
two red algae, two charophytes, seven genera of filamentous green algae and five<br />
flagellates. No endemic species were found, and it was concluded that the<br />
freshwater algal flora of the <strong>Yap</strong> Islands did not show characteristics of the biota of<br />
"oceanic" islands.<br />
2.6.4 The four main islands of <strong>Yap</strong> have long been densely populated, and most natural<br />
terrestrial ecosystems have been extensively modified, with reduction in species<br />
diversity and degradation of forests to savanna grasslands or conversion to agroforests.<br />
2.7 Noteworthy Fauna<br />
2.7.1 The mangrove forests provide habitat for a wide variety of marine organisms as<br />
well as many birds and fruit bats. They provide shelter and feeding habitat for reef<br />
fish, the most conspicuous families being Chaetodontidae (butterfly fish),<br />
Lutjanidae (snappers), Apogonidae (cardinal fish), Acanthuridae (surgeon fish),<br />
Siganidae (rabbit fish), Pomacentridae (damsel fish), Gobidae (gobies) and<br />
Gerreidae (mojarras). Gastropods such as the periwinkle Littorina scabra, the<br />
cerithiid Clypeomorus pellucida and the muricid snails Naquetia capucina and<br />
Thais aculeata are common, as are land crabs (Cardisoma sp.) and mangrove<br />
crabs (Scylla serrata) (U.S. Army Corps of Engineers, Pacific Ocean Division,<br />
1989b).<br />
2.7.2 The pond and stream fauna includes at least 50 species of aquatic insects, eight<br />
species of decapod crustacean, and 14 species of gastropods (Nelson, 1989). The<br />
most abundant fishes in the stream environments are the eleotrids Eleotris fuscus<br />
and Ophieleotris aporos, and the freshwater eel Anguilla marmorata. Other stream<br />
fishes include the mudskipper Periophthalmus vulgaris, the flagtail perch Kuhlia<br />
rupestris and the spotted scat Scatophagus argus. The introduced tilapia<br />
Oreochromis mossambicus, which escaped from an aquaculture project in the<br />
1970s, is now well established and is abundant in some of the freshwater ponds,<br />
streams and estuarine habitats (Nelson & Hopper, in Nelson, 1989).<br />
2.7.3 There are only three resident species of waterbirds on <strong>Yap</strong>; the Yellow Bittern<br />
(Ixobrychus sinensis), Pacific Reef Heron (Egretta sacra) and White-browed Crake<br />
(Porzana cinerea). The Yellow Bittern is particularly common, occurring in a wide<br />
variety of wet habitats. Situated only 1,300 km east of Mindanao in the Philippines<br />
and only 1,250 km north of western Irian Jaya, <strong>Yap</strong> lies sufficiently close to the<br />
continental island systems of eastern Asia to serve as a staging area for significant<br />
numbers of migratory shorebirds using the East Asian/Australasian flyway. Twentysix<br />
species of shorebirds have been recorded, and at least 12 of these are fairly<br />
common on migration and/or in winter. These are Pacific Golden Plover (Pluvialis<br />
LYON ASSOCIATES 2-13
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
fulva), Mongolian Plover (Charadrius mongolus), Greenshank (Tringa nebularia),<br />
Wood Sandpiper (T. glareola), Wandering Tattler (Heteroscelus incanus), Greytailed<br />
Tattler (H. brevipes), Common Sandpiper (Actitis hypoleucos), Whimbrel<br />
(Numenius phaeopus), Ruddy Turnstone (Arenaria interpres), Sanderling (Calidris<br />
alba), Rufous-necked Stint (C. ruficollis) and Sharp-tailed Sandpiper (C.<br />
acuminata) (Pratt et al., 1987). At least 175 shorebirds of 17 species were<br />
recorded during a brief survey of two islands in early September 1990 (D.A. Scott,<br />
unpublished). Other migratory waterbirds from eastern Asia which have been<br />
recorded on the islands include four species of herons and egrets, two ducks and<br />
the Whiskered Tern (Chlidonias hybrida).<br />
2.7.4 The only indigenous mammal is the Marianas Fruit Bat (Pteropus mariannus),<br />
which frequently forages in the mangrove and swamp forests. Two endemic<br />
subspecies occur in <strong>Yap</strong> P. m. yapensis on the main islands and P. m. ulithiensis<br />
on Ulithi atoll.<br />
2.8 Noteworthy Flora<br />
2.8.1 Most of the mangrove forests are still in relatively pristine condition. Mangrove<br />
species include seven species shared with the other islands of FSM Rhizophora<br />
mucronata, R. apiculata, Bruguiera gymnorrhiza, Xylocarpus granatum, Lumnitzera<br />
littorea, Nypa fruticans and Sonneratia alba, and three species of more westerly<br />
distribution Schypiphora hydrophyllacea, Ceriops tagal and Dolichandrone<br />
spathacea.<br />
2.8.2 The U.S. Forest Service has carried out a vegetation survey of <strong>Yap</strong> in cooperation<br />
with the <strong>State</strong> <strong>Government</strong> (Falanruw et al., 1987b). Detailed studies of <strong>Yap</strong>'s<br />
inland aquatic habitats were carried out by a team of aquatic biologists from the<br />
University of Guam Marine Laboratory, <strong>Yap</strong> <strong>State</strong> Department of Natural<br />
Resources and the College of Micronesia in 1988. The limn logical characteristics<br />
of the streams and ponds, the vegetation and the freshwater fishes, aquatic<br />
insects, decapod crustaceans and freshwater gastropods were investigated<br />
(Nelson, 1989). Lobban et al. (1990) have described the periphyton of <strong>Yap</strong>,<br />
excluding the diatoms and desmids.<br />
2.9 Land Use<br />
2.9.1 No conventional protected areas have been established on <strong>Yap</strong>. However, in the<br />
past, the use of land and marine resources, including mangroves, was traditionally<br />
subject to many regulations and restrictions. A complex system of ownership and<br />
rights of usage established limitations and helped to prevent over-exploitation<br />
(Yinug et al., 1989). There has been some replanting of mangroves in Nimpal<br />
Embayment on the west coast of <strong>Yap</strong> Proper to protect fishing grounds from<br />
salutation caused by construction work.<br />
2.9.2 <strong>Yap</strong> <strong>State</strong> Marine Resources Management Division is working on a Marine<br />
Resources and Coastal Management Plan incorporating traditional customs and<br />
laws (IUCN, 1991). This is likely to include recommendations for the protection of<br />
specific areas.<br />
2.9.3 The overall land area in the FSM is about 271 square miles. Pohnpei had the<br />
largest land area followed by Chuuk, <strong>Yap</strong> and then Kosrae. In 2001 , about 68 %<br />
LYON ASSOCIATES 2-14
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
of the land in FSM was privately owned. As depicted in Figure 2-3 below, <strong>Yap</strong> has<br />
the least amount of privately owned land.<br />
Figure 2-4<br />
Percentage of Land Ownership by <strong>State</strong>:2001<br />
Source Statistical Yearbook FSM 2007<br />
2.10 Population<br />
2.10.1 The total population of <strong>Yap</strong> state, based on the 2000 Census data, stands at<br />
11,241 which is a 0.6% increase over the 1994 data. The <strong>Yap</strong> population<br />
comprises 10.5% of the total population of the Federated <strong>State</strong>s of Micronesia.<br />
The median age for <strong>Yap</strong> is 20.9 years and is the highest median age among the<br />
fours states and comparatively higher that the median age of the FSM, which is 19<br />
years. The age distribution of the population in <strong>Yap</strong> is presented in Figure 2-5. It<br />
graphically shows the age distribution. Approximately 48% of the population is<br />
under 20 years of age (5,438 persons); there are 2,775 women between 15-44<br />
years of age, the child-bearing years which is 48% of the total female population.<br />
2.10.2 Table 2-1 presents the population distribution among the FSM islands. Based on<br />
the 2000 Census data <strong>Yap</strong> <strong>State</strong> has less than 11% of the FSM population.<br />
Furthermore <strong>Yap</strong> Proper contains 52% (5,870 persons) of the population of <strong>Yap</strong><br />
<strong>State</strong>. Table 2-1 also shows the change in population from 1930 and its relation to<br />
other FSM states.<br />
LYON ASSOCIATES 2-15
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Table 2-3 Population Distribution: 1930 to 2009<br />
Source: FSM Office of Statistics<br />
2.10.3 Figure 2-5 graphically presents the age distribution in <strong>Yap</strong> <strong>State</strong>. It is<br />
characterized by the large percentage of youth under 20 years of age.<br />
Figure 2-5<br />
<strong>Yap</strong> <strong>State</strong> Population Distribution by Age<br />
Source Statistical Yearbook FSM 2007 Table 2.5<br />
LYON ASSOCIATES 2-16
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.11 Economic Issues<br />
2.11.1 The four main islands are densely populated, with the 10,000 inhabitants living in<br />
over 100 villages. A subsistence lifestyle dominates; fishing is important and<br />
tourism is still a relatively minor industry. The mangrove forests are widely utilized<br />
for construction materials, wood for handicrafts, firewood and fishing, and land<br />
crabs and mangrove crabs are harvested in large numbers in some areas. In most<br />
areas, the cutting of mangrove for local building projects continues on a small<br />
scale as it has done for centuries, but in one area south of Peelaek Channel, there<br />
has been some commercial logging. Many of the freshwater swamp forests and<br />
marshes have been converted to taro fields (Colocasia esculenta and Cyrtosperma<br />
chamissonis), and in recent years, shallow ponds have also been used for the<br />
cultivation of the introduced aquatic plant Ipomoea aquatica (Nelson, 1989).<br />
2.11.2 Transportation on <strong>Yap</strong> Proper is becoming easier because of the development and<br />
improvement of paved roads; however, there are clusters of villages that are still<br />
difficult to access because of unpaved dirt roads. The outer islands are also<br />
difficult to reach because of the infrequent cargo ships. The regular field trip on the<br />
ship takes place once a month to each of the outer islands bringing supplies and<br />
health personnel to deliver goods and services.<br />
2.11.3 In the <strong>State</strong> of <strong>Yap</strong>, in the 2000 census, of the 2,030 households, 1,578 reported<br />
some cash income with a median household income of approximately $6,484 and<br />
a mean household income of $10,344. By region, the median household income<br />
was $7,299 in <strong>Yap</strong> Proper and about $4,242 in the outer islands. During this<br />
reporting year, over 50% of the population aged 15 years and over reported<br />
receiving cash income. These 3,254 income recipients represented 62% of the<br />
5,174 persons in the working age population. The median individual income for<br />
<strong>Yap</strong> was $3,368 with individual income on <strong>Yap</strong> Proper higher that income in the<br />
outer islands. Out of the total 2,030 households in FSM, 77% (1,578) reported<br />
having cash income with an average income of $10,344 and a median income of<br />
$6,489. This represents half of a percent (.5%) increase from the 1994 Census.<br />
However, there is still a disparity of income level among the <strong>Yap</strong> proper population<br />
and the outer island population. The average household income in <strong>Yap</strong> proper is<br />
$11,462 with a median income of $7,299 where as in the outer islands the average<br />
household income is $4,900 with a median income of $4,242<br />
2.11.4 Table 2-1 presents employment in <strong>Yap</strong> <strong>State</strong> from 2002 to 2006. Overall<br />
employment dipped in 2006 from its high in 2003 due to the closing of garment<br />
factories. <strong>Government</strong> employment peaked in 2005 and then fell in 2006 due to<br />
federal funding for the recovery efforts for Typhoon Sudal.<br />
Table 2-4 Total Employment by Sector: FY 2002 to FY 2006<br />
Source <strong>Yap</strong> <strong>State</strong> Annual Statistical Yearbook 2007 Table 4.1<br />
LYON ASSOCIATES 2-17
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.11.5 <strong>Yap</strong> generally shows a increase of agriculture produce by local markets between<br />
1997 to 2006 as shown below in Figure 2-6. The unusually high value were the<br />
result of banana and papaya export.<br />
Figure 2-6 Dollar Value of Local Markets' Purchases of<br />
Agricultural Products by <strong>State</strong><br />
Source Statistical Yearbook FSM 2007<br />
Figure 2-7 Copra Production by Volume (Tons), FSM: 1997 to 2006<br />
Source Statistical Yearbook FSM 2007<br />
LYON ASSOCIATES 2-18
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.11.6 Figure 2-7 shows that <strong>Yap</strong> and Pohnpei were the major copra producers in the<br />
years before 2001.<br />
2.11.7 The decline in <strong>Yap</strong> production is subsequent years resulted from natural disasters.<br />
In 2006, <strong>Yap</strong> and Pohnpei continued to be the only copra producers, <strong>Yap</strong><br />
produced 50 tons. The staple foods of the island are taro, yam, breadfruit, sweet<br />
potatoes, and coconut. The main sources of protein are fish, crabs, clams, and<br />
pork.<br />
2.11.8 The FSM annual inflation rate of the fourth quarter 2006 was 4.9%, which was a<br />
one percent increase from the same quarter in 2005. Figure 2-8 shows the steady<br />
decline in the annual inflation rates by quarter in <strong>Yap</strong>. The decrease is generally<br />
attributed to the lower prices of alcohol, tobacco, sakau, betel nut, fuel and utilities<br />
(e.g. electricity and water).<br />
Figure 2-8 Annual Inflation Rates: 4th Qtr 2004 to 4th Qtr 2006<br />
Source Statistical Yearbook FSM 2007<br />
2.11.9 In ten years from 1997 to 2006 registered motor vehicles increased 31 % in <strong>Yap</strong><br />
<strong>State</strong>, from 1,323 to 1,739. As presented in Table 2-3, sedans increased by 56%<br />
and pick-ups decreased by 34 for the same ten year period. In 2006 <strong>Yap</strong> <strong>State</strong><br />
had 21 % of the total motor vehicle registered in FSM. Pohnpei recorded 60%,<br />
Chuuk, 13% and Kosrae 9%.<br />
LYON ASSOCIATES 2-19
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Table 2-5<br />
Registered Motor Vehicles in <strong>Yap</strong><br />
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006<br />
Sedan 485 605 612 644 633 605 685 701 803 759<br />
Pick-ups 453 514 526 415 394 374 369 328 327 297<br />
Jeep 54 36 38 38 38 36 108 104 64 71<br />
Station wag 72 105 112 125 126 134 138 149 158 164<br />
Vans 103 139 141 146 148 138 146 160 170 169<br />
Flatbed trk 51 66 61 58 52 49 60 61 70 78<br />
Dump truck 26 45 51 47 44 46 39 46 38 25<br />
Ambulance 2 3 3 2 1 2 3 2 3 3<br />
Fire truck 1 1 1 2 1 1 1 1 1 1<br />
Fuel tanker 3 5 5 3 3 2 3 4 2 2<br />
Bus 12 11 10 14 14 13 14 13 12 11<br />
Motorcycle 26 31 13 15 11 11 25 52 22 18<br />
Other 35 40 106 101 99 145 90 62 151 141<br />
TOTAL 1,323 1,601 1,679 1,610 1,564 1,556 1,681 1,683 1,821 1,739<br />
Source Statistical Yearbook FSM 2007<br />
2.11.10 Figure 2-9 shows that the number of registered motor vehicles in FSM peaked in at<br />
9,731 in 2003. In 2006, it dropped to 8,121.<br />
Figure 2-9 Registered Motor Vehicles is FSM: 1999-2006<br />
Source Statistical Yearbook FSM 2007<br />
LYON ASSOCIATES 2-20
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
2.11.11 According to Table 2-4, for the period of 2000 to 2008 the passenger counts from<br />
those arriving and departing <strong>Yap</strong>, the majority of the travel is due to foreigners.<br />
The majority of those traveling to <strong>Yap</strong> arrive and depart by airplane.<br />
Table 2-6 Passenger Arrivals and Departures on Foreign Aircraft<br />
and Vessels: 2000 to 2007<br />
Source <strong>Yap</strong> <strong>State</strong> Annual Statistical Yearbook 2007 Table 8.8<br />
2.11.12 FSM Telecommunications Corporation is the only telecommunication company that<br />
services all of the states in FSM. Figure 2-10 shows the recent growth and then<br />
decline of telephone, fax and internet services for the period from 1997 to 2006.<br />
LYON ASSOCIATES 2-21
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Figure 2-10 <strong>Yap</strong> Communication services: 1997 to 2006<br />
Source FSM Office of Statistics<br />
2.12 Cultural History<br />
2.12.1 There are four indigenous languages in <strong>Yap</strong>: <strong>Yap</strong>ese, Ulithian, Woleian, and<br />
Satawalese. English is the common language of the FSM and is commonly spoken<br />
and understood. Many elderly <strong>Yap</strong>ese are fluent in Japanese.<br />
2.12.2 <strong>Yap</strong>ese society is based on a highly complex caste system involving at least seven<br />
tiers of rank. Historically, the caste rank of an entire village could rise or fall in<br />
comparison to other villages depending on how it fared in inter-village conflicts.<br />
Winning villages would rise in rank while losing villages would have to accept<br />
decline in comparative rank. In many cases lower ranked villages were required to<br />
pay tribute to higher ranked villages. Dietary taboos might be imposed on lower<br />
ranking villages, i.e. they might be prohibited from harvesting and eating the more<br />
desirable fish and animals of the sea. Within each village each family had its own<br />
rank comparative to the others. Until the arrival of the German colonializers, the<br />
caste ranking system was fluid and the ranks of villages and families changed in<br />
response to inter-village intrigues and confrontations. In the late 19th century,<br />
however, the German colonial administration "pacified" <strong>Yap</strong> and enforced a<br />
prohibition against violent conflict. The caste rank of each village in modern <strong>Yap</strong><br />
thus remains the same as it was when the system was frozen in place by the<br />
Germans.<br />
2.12.3 <strong>Yap</strong> is notable for its stone money, known as Rai: large donut-shaped, carved<br />
disks of (usually) calcite, up to 12 ft (4 m) in diameter (most are much smaller). The<br />
smallest known one is only 3 inches in diameter. Many of them were brought from<br />
other islands, as far as New Guinea, but most came in ancient times from Palau.<br />
Their value is based on both the stone's size and its history. Historically the<br />
LYON ASSOCIATES 2-22
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
<strong>Yap</strong>ese valued the disks because of the difficulty and hazards involved in obtaining<br />
them. To quarry the stones, <strong>Yap</strong>ese adventurers had to sail to distant islands and<br />
deal with local inhabitants that were sometimes hostile. Once quarried, the disks<br />
had to be transported back to <strong>Yap</strong> via rafts towed behind wind-powered canoes.<br />
The scarcity of the disks, and the effort and peril required to obtain them, made<br />
them valuable to the <strong>Yap</strong>ese. However, in 1874, an enterprising Irishman named<br />
David O'Keefe hit upon the idea of employing the <strong>Yap</strong>ese to import more "money"<br />
in the form of shiploads of large stones, also from Palau. O'Keefe then traded<br />
these stones with the <strong>Yap</strong>ese for other commodities such as sea cucumbers and<br />
copra. Although some of the O'Keefe stones are larger than the canoe-transported<br />
stones, they are less valuable than the earlier stones due to the comparative ease<br />
in which they were obtained. Approximately 6,800 of them are scattered around<br />
the island. As no more disks are being produced or imported, this money supply is<br />
fixed (Washington Post, 1984). The islanders know who owns which piece, but do<br />
not necessarily move them<br />
2.12.4 <strong>Yap</strong> Proper (known as Wa'ab or Waqab) was initially settled by ancient migrants<br />
from the Malay Peninsula, the Indonesian Archipelago, New Guinea, and the<br />
Solomon Islands. The <strong>Yap</strong>ese language is related to the Malay languages of<br />
Southeast Asia, though with strong New Guinean influences. In contrast, the<br />
people of <strong>Yap</strong>'s outer islands are descendants of Polynesian settlers, and as such<br />
have significant ethnic dissimilarities from the people of <strong>Yap</strong> Proper. Their culture<br />
and languages (Ulithian and Woleaian) are closely related to those of the<br />
neighboring islands of Chuuk.<br />
2.12.5 <strong>Yap</strong> was under Spanish control from the late 17th century until sold to Germany in<br />
the late 19th century. Germany held the islands until they were seized by Japan in<br />
World War I. Despite protests by the United <strong>State</strong>s, the League of Nations<br />
mandated <strong>Yap</strong> to Japan after the war. The Japanese operated military bases here<br />
during World War II. The United <strong>State</strong>s took possession after the war, and in 1947<br />
<strong>Yap</strong> became part of the Trust Territory of the Pacific Islands under United <strong>State</strong>s<br />
administration. In 1986 <strong>Yap</strong> became part of the self-governing Federated <strong>State</strong>s of<br />
Micronesia.<br />
2.12.6 In summary the relationship between human activity and the environment is<br />
dynamic and complex. This setting of this project in this environment is no<br />
exception. The highlights of this section indicates a population, dollar value of<br />
local market purchases of agricultural products and registration of vehicles has<br />
increased in recent years. Employment, interstate and international travel, copra<br />
production by volume, the rate of annual inflation and communication services has<br />
fallen in recent years. These factors individually or combined have not driven the<br />
need for this project nor the scope of the project. The project will not significantly<br />
increase the capacity of this roadway but simply decrease the operations and<br />
maintenance cost and increase public safety and reliability in using the existing<br />
road. There is not a economic viable alternative for the people and vehicles that<br />
use this road. The characteristic and location of deep poorly drained soils, the<br />
frequency and height of storm surges and issues caused by drainage have<br />
contributed to the need for this project. The object of this project is to better<br />
understand and make improvements to the existing roadway and its environment.<br />
LYON ASSOCIATES 2-23
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
3 GENERAL DESCRIPTION OF PROJECT EFFECTS<br />
3.1 Problems with the Existing Road Segments<br />
3.1.1 Although the road from beginning of the project (BOP) at the hospital intersection<br />
with the main road to Keng to the end of the project (EOP) at the western edge of<br />
Tagireeng Bridge was constructed in the mid 1980s, the following problems have<br />
been sited:<br />
• The existing road surface is rubberized asphalt pavement . It has deteriorated<br />
in several segments of the road particularly along the shoreline. <strong>Yap</strong> <strong>State</strong> has<br />
replaced the asphalt pavement in these areas with portland concrete<br />
pavement.<br />
• The construction of this road segment changed the pre-existing drainage<br />
system resulting in changing upland forest into upland marshes and altering<br />
flow patterns to downstream both freshwater and saltwater wetland.<br />
3.1.2 The premature deterioration of the asphalt pavement can be attributed to three<br />
issues:<br />
• As the soil map of the project region depicts in Figure 2-2, the green area<br />
beneath this section of the road are characterized as deep poorly drained soils;<br />
• Segments of the road are subjected to flooding by storm surges; and<br />
• Segments of the road are subjected to flooding by stormwater runoff.<br />
3.1.3 The cause and effect mechanisms are two fold: the saturation of the road bed<br />
reduces the strength and bearing capacity; and secondly, the wheel loads provide<br />
energy to accelerate the water within the saturated road bed which forces<br />
structural changes and has the capacity to transport soil particles. This<br />
mechanism is often referred to as pumping. It creates voids which results in the<br />
reduction of support to the pavement.<br />
3.1.4 The water velocity caused by the flooding subjects it path to forces that can<br />
transport material. This process can both undermine the road by erosion or carry<br />
away the broken pieces of the asphalt pavement. As mentioned above both<br />
waves from storm surges and stormwater runoff provides velocity to the water.<br />
3.1.5 In summary the design of a road bed capacity to carry or support wheel loads is<br />
based on non-saturated strength of the material. The pavement is one of the ways<br />
to protect the road bed from being saturated. In overall drainage system is needed<br />
to assure the road be is not subjected to ponding along the road or raising the<br />
ground water level into the road bed,<br />
3.1.6 This project was commissioned by the <strong>State</strong> of <strong>Yap</strong>, Department of Public Works<br />
and Transportation in order to address these problems. The scope of work for this<br />
project encompasses this preliminary environmental impact statement, a climate<br />
change report and construction documents. A separate preliminary environmental<br />
impact statement is being prepared for the quarry (borrow) site and dredging site.<br />
3.1.7 The climate change report will focus on the reviewing the existing literature as it<br />
pertains to height and frequency of the sea level on the <strong>Yap</strong>'s shoreline. This will<br />
provide information to determine the most cost effective and environmentally<br />
sound elevation of the road along the shoreline.<br />
LYON ASSOCIATES 3-1
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
3.1.8 As part of the basis of design Lyon Associates will analyze and evaluate the<br />
drainage system that surrounds the road. This analysis and evaluation will also be<br />
presented in report form.<br />
Figure 3-1 shows the watershed map along the project.<br />
Figure 3-1<br />
Existing Watershed Map Along the Project<br />
Source: Drainage Assessment, Draft Lyon Associated 2010<br />
3.1.9 As a summary, the basis of design for the Northern <strong>Yap</strong> Improvements Project will<br />
encompass the findings of this preliminary environmental impact statement, the<br />
climate change report and the drainage assessment and the road design<br />
standards from the <strong>Yap</strong> <strong>State</strong> Department of Public Works and Transportation in<br />
order to recommend the most cost effective and environmentally sound<br />
improvements to the existing road.<br />
LYON ASSOCIATES 3-2
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
3.2 Disturbances and Threats to Wetlands<br />
3.2.1 Freshwater wetlands have been extensively modified for agricultural use, and<br />
some mangrove areas are threatened by uncontrolled harvesting of timber, filling<br />
to create land for houses and other development, and the dumping of rubbish and<br />
toxic materials. Some mangroves were destroyed by salutation during the<br />
construction of a new airport, but there has been some recovery since then. The<br />
construction of roads with too few drainage culverts has resulted in localized<br />
impoundment of mangroves, and the building of a solid causeway between Gagil-<br />
Tamil and Maap islands has resulted in the death of mangroves along part of the<br />
Yunearawey Passage. A small amount of commercial logging has been reported,<br />
but a proposal (with Taiwanese backing) to undertake commercial logging in the<br />
mangroves on a large scale has been rejected. At least two proposals to clear<br />
mangroves for aquaculture and a proposal to utilize mangrove wood as fuel to<br />
smoke fish have also been rejected, but a proposal to use mangrove areas as<br />
rubbish dumps is still under discussion. Oil spills and pesticides have had localized<br />
impact, although Mowbray (1988) has reported a leakage of endrin and sodium<br />
arsenite into a freshwater stream and coastal lagoon which caused a large-scale<br />
kill of fish, wildlife and domestic animals. The greatest threat to the sustainable use<br />
of mangrove forests and other natural resources in <strong>Yap</strong> is the removal of traditional<br />
limitations on their exploitation, generally as a result of new technologies, outside<br />
inputs and commercialized exploitation (Yinug et al., 1989).<br />
3.2.2 One of the objectives in the road improvement project is to analyze and evaluate<br />
the drainage system along the road. Where the existing road has significantly<br />
blocked or reduced stormwater runoff to areas downstream or significantly reduce<br />
salt water circulation to mangrove forest landward of the road, the design is<br />
intended to rectify this problems.<br />
3.3 Hydrological & Biophysical Values<br />
3.3.1 Mangroves serve as natural filtering and nutrient buffering systems between the<br />
islands and the adjacent fringing reefs, protecting the reefs from sedimentation and<br />
providing for a slow sustained release of nutrients. The mangrove forests afford<br />
some protection against storm damage, and may also be important in stabilizing<br />
the shoreline against erosion. They play a critical role as nursery habitat for larval<br />
and juvenile fishes and thereby help to maintain the coastal fishery.<br />
3.4 Road Improvement Construction<br />
3.4.1 The improvements to existing road although temporary has the potential to cause<br />
or effect the many possible environmental impacts. <strong>Yap</strong> <strong>State</strong> Environmental<br />
Protection Agency has promulgated regulations requiring this preliminary<br />
environmental impact statement. They have provided an initial environmental<br />
Assessment checklist in appendix A of the regulations. This check list will be<br />
addressed in the following section of this report.<br />
LYON ASSOCIATES 3-3
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
4 POSSIBLE ENVIRONMENTAL IMPACT CHECKLIST<br />
4.1 Initial Environmental Assessment Checklist<br />
4.1.1 The content of this checklist is was taken form Appendix A. The questions of the<br />
checklist are present in italic font larger than the normal font.<br />
4.2 Earth- Will the proposed project result in:<br />
4.2.1 Destruction, covering or modification of any unique geologic or<br />
physical features? No. The project is to make improvements to the existing<br />
road.<br />
4.2.2 Creation of steep slopes or other unstable earth conditions? No. Any<br />
new slopes will be designed in accordance to the geotechnical report for the<br />
project. The recommend slope design will not exceed the ratio of 1 vertical to 2<br />
horizontal. BMPs shall be incorporated into the design documents e.g. Seeding of<br />
grasses and plantings of trees, shrubs, vines and ground covers provide longterm<br />
stabilization of soil. The type of vegetation, site and seedbed preparation, planting<br />
time, fertilization and water requirements will be specified for each application.<br />
Mattings may also be designated on disturbed soils and where existing vegetation<br />
has been removed. The following organic matting materials provide temporary<br />
protection until permanent vegetation is established, or when seasonal<br />
circumstances dictate the need for temporary stabilization until weather or<br />
construction delays are resolved: Jute or straw mattings. The following synthetic<br />
mattings may be used for either temporary or post-construction stabilization, both<br />
with and without vegetation: Excelsior matting, Glass fiber matting, Staples and<br />
Mulch nettings. Note that the seeding procedure will be included in the<br />
specifications.<br />
Figure 4-1<br />
Slope Stabilization Matting<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
4.2.3 Any potential for increase wind or water erosion of soils, either on of<br />
the site? Yes. The temporary construction activities will generate dust and loosen<br />
LYON ASSOCIATES 4-4
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
soil and pavement particles. The construction plans and specifications will include<br />
best management practices (BMPs) such as filter curtains to mitigate sediment<br />
transport into the water ways and silt fencing and/or using watering trucks for dust<br />
control. The design documents will include mulching to temporarily and<br />
permanently stabilize cleared or freshly seeded areas. Note the filter curtain will be<br />
included in the project specifications.<br />
Figure 4-2<br />
Slope Stabilization with Mulching<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
4.2.4 Changes in the channel of stream, or the bed of the ocean? Maybe.<br />
The scope of work calls for analyzing the existing drainage system within the<br />
project limits. It is possible that the existing drainage structures are not adequate<br />
or additional drainage structure will be required. In these cases the drainage<br />
channel may be modified. The construction plans and specifications will include<br />
BMP cover requirements to mitigate sediment during construction within the<br />
drainage channels or embankments along the bays and channel.<br />
4.2.5 Exposure of people or property to geological hazards such as<br />
landslides, ground failure, or similar hazards? Maybe. The scope of work<br />
calls analyzing the steep cuts, embankments and slope protection on the existing<br />
road. It is possible that the existing slopes or slope protection are deemed unsafe<br />
and efforts maybe necessary to correct the existing condition. The construction<br />
plans and specifications will include BMP cover requirements to prevent landslide.<br />
4.3 Air- Will the proposed project result in:<br />
4.3.1 Substantial air emissions or deterioration of existing air quality? No. The<br />
temporary construction activities will generate dust and increase the hydrocarbon<br />
emissions in the area where construction equipment is operating. The<br />
construction plans and specifications will include best management practices<br />
(BMPs) to mitigate dust and to control dust, e.g. using water trucks to spray water<br />
on areas of unstabilized soil.<br />
LYON ASSOCIATES 4-5
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Figure 4-3<br />
Watering Trucks for Dust Control<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
4.3.2 Creation of objectionable odors? Maybe. The temporary construction<br />
activities may pike the levels of hydrocarbon emissions in the localized areas<br />
where construction equipment is operating or in asphalt paving. Typically many of<br />
the construction equipment have diesel engines. The exhaust from these may<br />
temporarily create objectionable odors.<br />
4.4 Water- Will the proposed project result in:<br />
4.4.1 Changes in currents, or the course or direction of water movements,<br />
in marine or fresh waters? Maybe. The scope of work calls for analyzing<br />
and evaluating the existing drainage system within the project limits. It is possible<br />
that the existing drainage structures are not adequate or additional drainage<br />
structure will be needed. In these cases the drainage course or direction may be<br />
modified. The construction plans and specifications will include BMPs to mitigate<br />
sediment transfer during temporary construction within the drainage course or<br />
embankments along the bays and channel.<br />
4.4.2 Changes in absorption rates, drainage patterns, or the amount of<br />
surface runoff? Maybe. Reportedly, the construction of the existing road did<br />
change the infiltration rates, drainage patterns, the amount and path of surface<br />
runoff. The scope of work calls for analyzing and evaluating the existing drainage<br />
system within the project limits. It is possible that the existing drainage structures<br />
are not adequate or additional drainage structure will be required. In these cases<br />
the changes in one or all three topics may be modified.<br />
4.4.3 Alterations to the course or flow of flood waters? Maybe. Similarly, The<br />
scope of work calls for analyzing and evaluating the existing drainage system<br />
within the project limits. It is possible that the existing drainage structures are not<br />
adequate or additional drainage structure will be required. In these cases the<br />
drainage course or direction may be modified. The construction plans and<br />
specifications will include BMPs to mitigate sediment during temporary<br />
construction within the drainage course or embankments along the bays and<br />
channel.<br />
LYON ASSOCIATES 4-6
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
4.4.4 Discharge into surface waters or any alteration of surface water<br />
quality including but not limited to temperature, dissolved oxygen,<br />
bacteria, or turbidity? Maybe. Temporary construction activities has the<br />
potential to discharge contaminates into the surface waters. These temporary<br />
construction activities will require the contractor to implement BMPs to prevent or<br />
at least mitigate the discharges from construction activities. Industrial activities are<br />
not anticipated for the site.<br />
4.4.5 Contamination of ground waters or wells, from salt water intrusion or<br />
surface activities? No.<br />
4.4.6 Changes in the quantity of ground waters, through direct additions or<br />
withdrawal, or through interception of an aquifer by cuts or<br />
excavation? Maybe. As mentioned above, The scope of work calls for<br />
analyzing and evaluating the existing drainage system within the project limits.<br />
Existing ponding of stormwater along the roadside is likely to be drained in order to<br />
reduce it contribution to temporarily increasing the groundwater level and<br />
subjecting the road bed to saturation by the groundwater. Furthermore, roadway<br />
cuts into the terrain may occur in order to stabilize the slope. Water seepage from<br />
these cuts and springs may redirected in order to reduce ponding along or above<br />
the roadway.<br />
4.4.7 Substantial reduction in the amount or quality of water otherwise<br />
available for public water supplies? No.<br />
4.4.8 Exposure of people or property to water related hazards such as<br />
flooding or tidal waves? No. One of the objectives in this project is to reduce<br />
the risk of water related hazards from flooding or tidal waves to the people using<br />
and depending on the roadway.<br />
4.5 Plant Life- Will the proposed project result in:<br />
4.5.1 Destruction of any upland or mangrove forest communities? Maybe. It<br />
is likely that the elevation of the existing roadway will be raised in order to deduce<br />
the effects and/or the frequency of storm surges and tidal action. The act of<br />
raising the roadway may require the embankment to be raise thus likely extending<br />
its footprint in order to maintain a stable slope on the embankment. It is possible<br />
that fringes of existing upland or mangrove forest communities may be affected.<br />
4.5.2 Destruction of other important plant communities, such as sea<br />
grasses or plants having potential commercial value? No.<br />
4.5.3 Reduction of the numbers of any unique, rare or endangered plant<br />
species? No.<br />
4.5.4 Introduction of new species of plants into an area, or resultant barrier<br />
to the normal replenishment of existing species? No.<br />
4.5.5 Reduction in acreage of any agricultural crop? No.<br />
4.6 Animal Life- Will the proposed project result in:<br />
LYON ASSOCIATES 4-7
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
4.6.1 Destruction of any coral reef areas? No.<br />
4.6.2 Reduction of the numbers of any unique, rare or endangered animal<br />
species? No.<br />
4.6.3 Introduction of new animal species into an area, or result in a barrier<br />
to the migration or movement of animals? No.<br />
4.6.4 Substantial deterioration of fish or wildlife habitat? No.<br />
4.7 Noise- Will the proposed project result in:<br />
4.7.1 Increase in existing noise levels or exposure of people to severe noise<br />
levels? No, industrial or other activities that will create severe noise levels are<br />
anticipated at the site after the completion of the road improvement project.<br />
4.8 Land Use- Will the proposed project result in:<br />
4.8.1 Substantial alteration of the present or planned land use of an area?<br />
No. This project will make improvements to the existing road.<br />
4.9 Natural Resources- Will the proposed project result in:<br />
4.9.1 A noticeable increase in the rate of use of any natural resources? No.<br />
4.9.2 Substantial depletion of any non-renewable natural resources? No.<br />
4.10 Risk of Upset- Will the proposed project result in:<br />
4.10.1 A risk of an explosion or the release of hazardous substances<br />
including but not limited to oil, pesticides, chemicals, or radiation, in<br />
the event of an accident or upset conditions? No. The design process to<br />
date has not selected to chemical treatment such as Condor SS unless the <strong>State</strong><br />
of <strong>Yap</strong>, Department of Public Works and Transportation recommends otherwise.<br />
Condor SS is a mixture of ion exchange resins and sulfuric and sulfonic acids that<br />
is designed to remove the water of hydration from subgrade clays. This allows the<br />
subgrade to be compacted to a dense, highly stable state. The mixture is applied<br />
by ripping and sprinkling or by injection into the subgrade, followed by compaction<br />
with a vibrating roller (Escobar, 1984). The material is extremely acidic (pH 1.25)<br />
so care must be used to avoid spills and to prevent overland flow runoff from<br />
treated areas immediately after application. In order to prevent or reduce the<br />
discharge of pollutants e.g. liquid petroleum products to storm water from material<br />
delivery and storage by minimizing the storage of hazardous materials on-site,<br />
storing materials in a designated area, installing secondary containment,<br />
conducting regular inspections, and training employees and subcontractors.<br />
LYON ASSOCIATES 4-8
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Figure 4-4 Secondary Containment<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
4.10.2 Possible interference with an emergency response plan? No.<br />
4.11 Population- Will the proposed project result in:<br />
4.11.1 Relocation or altered distribution, density, or growth rate of the human<br />
population of an area? No.<br />
4.12 Housing- Will the proposed project result in:<br />
4.12.1 Changes in existing housing or create a demand for additional<br />
housing? No.<br />
4.13 Transpiration- Will the proposed project result in:<br />
4.13.1 Generation of substantial additional vehicular movement? No.<br />
4.13.2 Substantial impact on roads and existing transportation system? Yes.<br />
Traffic patterns should remain the same. Temporary disruptions to the traffic is<br />
expected during construction activities. As a result of the road improvement, the<br />
roadway operation and maintenance costs for this segment of the road will be<br />
reduced.<br />
4.13.3 Alteration to present patterns of movement of people and/or goods?<br />
No.<br />
4.14 Public Services<br />
4.14.1 Will the proposed project result in or affect the need for new or altered<br />
services in Police or fire protection? No.<br />
4.14.2 Will the proposed project result in or affect the need for new or altered<br />
services in Schools? No.<br />
LYON ASSOCIATES 4-9
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
4.14.3 Will the proposed project result in or affect the need for new or altered<br />
services in Parks or other recreational facilities? No.<br />
4.14.4 Will the proposed project result in or affect the need for new or altered<br />
services in Hospital? No.<br />
4.14.5 Will the proposed project result in or affect the need for new or altered<br />
services in Other government services? No.<br />
4.15 Utilities<br />
4.15.1 Will the proposed project result in the need for new systems, or<br />
substantial changes in the Power? No.<br />
4.15.2 Will the proposed project result in the need for new systems, or<br />
substantial changes in Communications? No.<br />
4.15.3 Will the proposed project result in the need for new systems, or<br />
substantial changes in Water? Yes. There will be adjustments to the<br />
existing waterlines at those existing culverts to be added-on the new culverts.<br />
4.15.4 Will the proposed project result in the need for new systems, or<br />
substantial changes in Sewage disposal? No.<br />
4.15.5 Will the proposed project result in the need for new systems, or<br />
substantial changes in Solid waste disposal? No.<br />
4.16 Human Health- Will the proposed project result in:<br />
4.16.1 Creation of any health hazard or potential health hazard? No.<br />
4.16.2 Improvement of human health? No.<br />
4.17 Aesthetics- Will the proposed project result in:<br />
4.17.1 Obstruction of any scenic vista? No.<br />
4.18 Recreation- Will the proposed project result in:<br />
4.18.1 Changes in the quality or amount of existing recreational<br />
opportunities? No.<br />
4.19 Cultural Resources- Will the proposed project result in:<br />
4.19.1 Alteration or destruction of archaeological sites? No.<br />
4.19.2 Adverse physical or aesthetic impacts on a historic site? No.<br />
LYON ASSOCIATES 4-10
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
4.19.3 Potential to cause a physical change which would affect unique<br />
cultural values? No.<br />
4.19.4 Restriction of existing religious or sacred uses within the affected<br />
area? No.<br />
4.20 Others- Will the proposed project result in:<br />
4.20.1 Please specify. None<br />
LYON ASSOCIATES 4-11
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
5 ALTERNATIVES TO MITIGATE ADVERSE IMPACTS<br />
5.1 Design Considerations<br />
5.1.1 As stated above in this report, the objective of the project is to mitigate adverse<br />
impacts on and around the existing road. Project design considerations will<br />
encompass:<br />
• Design project to integrate into existing land contours.<br />
• Significant regrading of a site will require more costly erosion and<br />
sedimentation control measures and may require that on-site drainage facilities<br />
be installed e.g. silt fencing as shown in Figures 5-1 and 5-2. Note these<br />
figures will be included in the project construction plans and specifications<br />
Figure 5-1<br />
Silt Fencing for Sediment Control<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
Figure 5-2 Silt Fencing for Cross Section<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
LYON ASSOCIATES 5-12
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
• Carefully planned preservation of existing vegetation minimizes the potential of<br />
removing or injuring existing trees, vines, shrubs and/or grasses that serve as<br />
erosion controls.<br />
• Clearly mark, flag or fence vegetation or areas where vegetation should be<br />
preserved.<br />
• Prepare landscaping plans which include as much existing vegetation as<br />
possible and state proper care of this vegetation both during and after<br />
construction.<br />
• Define and protect with berms, fencing, signs, etc., a setback area from<br />
vegetation to be preserved. Setback area size should be based on the location,<br />
species, size, age and potential impact of adjacent construction activities or<br />
permanent improvements.<br />
• Proposed landscaping plans which do not include plant species that compete<br />
with the existing vegetation.<br />
• Do not locate construction traffic routes, spoil piles, etc., where significant<br />
adverse impact on existing vegetation may occur.<br />
• Rock outlet protection is a physical device composed of rock, grouted riprap, or<br />
concrete rubble which is placed at the outlet of a pipe to prevent scour of the<br />
soil caused by high pipe flow velocities, and to absorb flow energy to produce<br />
non-erosive velocities.<br />
Figure 5-3<br />
Stormwater Outlet Protection<br />
Source: Best Management Practices Manual for Const. City & County of Honolulu<br />
5.2 Erosion Control Plan<br />
5.2.1 However, during the construction of improvements best management practices<br />
(BMP) in the design documents shall be implemented by the contractor.<br />
5.2.2 The contractor shall prepare and submit to <strong>Yap</strong> <strong>State</strong> EPA for approval.<br />
Sequencing the construction project to reduce the amount and duration of soil<br />
exposed to erosion by wind, rain, runoff, and vehicle tracking. The design team is<br />
aware that construction scheduling to reduce erosion may increase other<br />
LYON ASSOCIATES 5-13
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
construction costs due to reduced economies of scale in performing site grading.<br />
Note that the erosion control will be included in the specifications. The cost<br />
effectiveness of scheduling techniques should be compared with the other, less<br />
effective erosion and sedimentation controls to achieve a cost-effective balance.<br />
Recommended approaches shall include:<br />
• Avoid rainy periods: Schedule major grading operations during dry months.<br />
• Allow enough time before rainfall begins to stabilize the soil with vegetation or<br />
physical means or to install temporary sediment trapping devices<br />
• Sequence construction so that haul roads and stockpiles are buffered with<br />
planted areas prior to discharging offsite.<br />
• Separate offsite runoff where possible, so that it flows through the construction<br />
site without going through bare ground.<br />
• Locate stockpiles away from waterways or low spots.<br />
• Maintain swales and natural drainage ways in vegetated condition.<br />
• Save trees and other existing vegetation. Vegetation along the perimeter of the<br />
site provides an effective buffer against sediment leaving the construction site.<br />
• Use naturally level area for parking during construction.<br />
• Maintenance and inspect erosion control BMPs daily and log the findings.<br />
• Provide mulching, grassing other ground cover to reduce bare areas.<br />
• Minimize soil exposed at one time: Schedule projects to disturb only small<br />
portions of the site at any one time. Complete grading as soon as possible.<br />
Immediately stabilize the disturbed portion before grading the next portion.<br />
Practice staged seeding. Revegetate cut and fill slopes as the work<br />
progresses.<br />
• Trenching: Close and stabilize open trenches as soon as possible. Sequence<br />
trenching projects so that most open portions of the trench are closed before<br />
new trenching is begun.<br />
5.3 Monitoring Plan<br />
5.3.1 The design team recommends and will include a monitoring plan in the<br />
specifications that <strong>Yap</strong> EPA require the contractor to prepare and conduct a<br />
surface water monitoring program for construction activities within water ways.<br />
5.4 Traffic Control Plan<br />
5.4.1 The design team will prepare a traffic control plan in order to mitigate traffic delays<br />
during construction and to enhance public safety and will include traffic control plan<br />
requirements in the specifications.<br />
LYON ASSOCIATES 5-14
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
6 THE NEED FOR THE PROPOSED PROJECT<br />
6.1 Summary<br />
6.1.1 Although the existing was only constructed in the mid 1980s, the following<br />
problems have been sited:<br />
• The asphalt pavement has deteriorated in several segments of the road<br />
particularly along the shoreline. <strong>Yap</strong> <strong>State</strong> has replaced the asphalt pavement<br />
in some of these areas with portland concrete pavement but the problem<br />
persists.<br />
• The original construction of this road segment in this project changed the preexisting<br />
drainage system resulting in changing upland forest into upland<br />
marshes and altering flow patterns to downstream both freshwater and<br />
saltwater wetland.<br />
6.1.2 The <strong>State</strong> of <strong>Yap</strong>, Department of Public Works and Transportation defined the<br />
scope of this project and published a request for proposal (RFP). Lyon Associates<br />
was selected and was issued the Notice to Proceed (NTP) for the design services<br />
for this project December 9, 2009. The document was prepared in accordance to<br />
the contract.<br />
LYON ASSOCIATES 6-1
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
7 REFERENCE<br />
Buden, D.W. 1996. Rediscovery of the Pohnpei Mountain Starling (Aplonis pelzelni). The<br />
Auk 113(1):229-230.<br />
Buden, D.W. 2000. A comparison of 1983 and 1994 bird surveys of Pohnpei, Federated<br />
<strong>State</strong>s of Micronesia. Wilson Bull. 112(3):403-410.<br />
City and County of Honolulu, Dept. of Environmental Services 1999. Best Management<br />
Practices Manual for Construction Sites in Honolulu, pp 144.<br />
Cole, W.S. 1960 Bull Am Pal., 41 pp 77-83<br />
Devoe, N. 1991. Interim Report: Mangrove Areas Use Classification, Pohnpei, FSM.<br />
Institute of Pacific Islands Forestry, U.S.D.A. Forest Service, Honolulu, Hawaii 96813.<br />
28 pp. Unpublished manuscript.<br />
Engbring J., F.L. Ramsey and V.J. Wildman 1990. Micronesian forest bird surveys, the<br />
federated states: Pohnpei, Kosrae, Chuuk and <strong>Yap</strong>. U.S. Fish and Wildlife Service.<br />
Department of the Interior, Washington D.C.<br />
Escobar, R. 1984. Electrochemical soil stabilization. Joint publication of the Organization<br />
Condor, Apartado 80565, Caracas '1080A Venezuela and Earth Science Products<br />
Corp. 1960 S. W. 16th Ave, Portland, Oregon, 97201, USA. 110 p.<br />
Falanruw, M., Cole, T., Ambacher, A., McDuffie, K. & Maka, J. 1987a. Vegetation Survey of<br />
Moen, Dublon, Fefan and Eten, <strong>State</strong> of Truk, Federated <strong>State</strong>s of Micronesia. Resour.<br />
Bull. PSW-20. Pacific Forest and Range Experiment Station, U.S. Department of<br />
Agriculture, Berkeley, California. 6 pp + 3 maps.<br />
Falanruw, M., Whitesell, C., Cole, T., MacLean, C. & Ambacher, A. 1987b. Vegetation<br />
Survey of <strong>Yap</strong>, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-21. Pacific Forest<br />
and Range Experiment Station, U.S. Department of Agriculture, Berkeley, California. 9<br />
pp + 4 maps.<br />
Falanruw, M.V.C., T. Cole, A.H. Ambacher, K.E. McDuffie & J.E. Maka. 1987. Vegetation<br />
Survey of Moen, Dublon, Fefen and Eten, <strong>State</strong> of Truk, Federated <strong>State</strong>s of<br />
Micronesia, USDA Forest Service, Resource Bull. PSW-20, 6pp+ 3 maps.<br />
Falanruw, M.V.C. 1988. On the status, reproductive biology and management of fruit bats<br />
of <strong>Yap</strong>. Micronesica 21 (1-2), pp. 39-51.<br />
Food and Agricultural Organization of the United Nations. 1989. Watershed management<br />
field manual - Road design and construction in sensitive watersheds. FAO<br />
Conservation Guide, 13/5. 196 p.<br />
Fosberg, F.R., M-H. Sachet and R. Oliver 1979. Geographical checklist of the Micronesian<br />
Dicotyledonae. Micronesica 18(1):23-82.<br />
Fosberg, F.R., M-H. Sachet and R. Oliver 1982. Geographical checklist of the Micronesian<br />
Pteridophyta and Gymnospermae. Micronesica 18(1):23-82.<br />
Fosberg, F.R., M-H. Sachet and R. Oliver 1987. Geographical checklist of the Micronesian<br />
Monocotyledonae. Micronesica 18(1):23-82.<br />
Fosberg, F.R. 1947. Micronesian Mangroves. New York Bot. Gard. Jour. 48: 128-138.<br />
Fosberg, F.R. 1975. Phytogeography of Micronesian Mangroves. Proc. International<br />
Symposium on Biological Management of Mangroves. 1: 23-42.<br />
FSM 1999. Proceedings of the 2 nd FSM Economic Summit. Pohnpei, FSM<br />
FSM 2000. Coastal Fisheries Consortium Report of Proceedings. FSM Department of<br />
Economic Affairs, Pohnpei.<br />
FSM <strong>Yap</strong> Branch Statistics Office, Division of Statistics, Department of Economic Affairs,<br />
2002. <strong>Yap</strong> <strong>State</strong> Census Report, 2000 FSM Census of Population and Housing.<br />
FSM <strong>Yap</strong> Branch Statistics Office, Division of Statistics, Department of Economic Affairs,<br />
2002. <strong>Yap</strong> <strong>State</strong> Annual Statistical Yearbook, 2007.<br />
LYON ASSOCIATES 7-2
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
FSM Statistical Unit, Division of Statistics, Department of Economic Affairs, 2007.<br />
Statistical Yearbook, FSM 2007.<br />
Gawel, M.J. 1993. The Federated <strong>State</strong>s of Micronesia <strong>State</strong> of the Environment Report.<br />
SPREP<br />
Geotesting Inc. 1986. The <strong>Yap</strong> Road Improvements - Phase V Soil Investigation Report.<br />
Holthus, P.F. 1987. Pohnpei Coastal Resources: Proposed Management Plan. Draft<br />
Report. South Pacific Regional Environment Programme, Noumea, New Caledonia.<br />
101 pp.<br />
Hosokawa, T. 1954. On the Campnosperma Forests of <strong>Yap</strong>, Ponape and Kusaie in<br />
Micronesia. Mem. Fac. Sci. Kyushu Univ. Ser. E. 1: 219-243.<br />
Hosokawa, T. 1957. Outline of the Mangrove and Strand Forests of Micronesian Islands.<br />
Mem. Fac. Sci. Kyushu Univ. Ser. E. 2(3): 101-118.<br />
Hosokawa, T. 1971. On the tropical rainforest conservation to be proposed in Micronesia.<br />
In: Proc. Symposium on Planned utilization of the lowland tropical forests: 150-164.<br />
Pre-Congress Conference in Indonesia.<br />
Hosokawa, T., Tagawa, H. & Chapman, V.J. 1977. Mangrove of Micronesia, Taiwan,<br />
Japan, the Philippines and Oceania. In: Chapman, V.J. (ed.) 1977, Wet Coastal<br />
Ecosystems: 271-291. Elsevier Publishing Co., Amsterdam.<br />
IUCN 1991. IUCN Directory of Protected Areas in Oceania. Prepared by the World<br />
Conservation Monitoring Centre. IUCN, Gland, Switzerland and Cambridge, U.K.<br />
Johnson, C., Alvis, R., Hetzter, R and Blumestock, D., 1960 U.S. Army Pacific APO 958, pp<br />
168<br />
Kogo, M., Miyagi, T. & Musahino, Y. 1985. Final Report on Mangrove Research in Truk<br />
Islands, April 19 - May 10 1985. Prepared for the UNDP/UNESCO Regional Project:<br />
Mangrove Ecosystems of Asia and Pacific RAS/79/002. Al Gurm Research Centre,<br />
Tokyo, Japan. 80 pp.<br />
Koyama, T. 1964. The Cyperaceae of Micronesia. Micronesica 1(1): 59-112.<br />
Laird, W.E. 1982. Soil Survey of Island of Ponape, Federated <strong>State</strong>s of Micronesia. USDA<br />
Soil Conservation Service, Washington, D.C. 81 pp + 1 map and 43 aerial photos.<br />
Laird, W.E. 1983a. Soil Survey of Islands of Truk, Federated <strong>State</strong>s of Micronesia. USDA<br />
Soil Conservation Service, Washington, D.C. 65 pp + 3 maps and 16 aerial photos.<br />
Laird, W.E. 1983b. Soil Survey of Island of Kosrae, Federated <strong>State</strong>s of Micronesia. USDA<br />
Soil Conservation Service, Washington, D.C. 67 pp + 1 map and 12 aerial photos.<br />
Lal, P.N. 1989. Utilization and Management of Coastal Wetland Resources in Kosrae.<br />
Unpublished manuscript. University of Hawaii Sea Grant, Honolulu, Hawaii. 39 pp.<br />
Lobban, C.S., Daily, F.K., Daily, W.A., Hoshaw, R.W. & Schefter, M. 1990. Periphyton,<br />
Excluding Diatoms and Desmids, from <strong>Yap</strong>, Caroline Islands. Micronesica 23(1): 27-40.<br />
Lyon Associates, 2010. Draft Drainage Assessment, pp 13.<br />
MacLean, C., Cole, T., Whitesell, C., Falanruw, M. & Ambacher, A. 1986. Vegetation<br />
Survey of Pohnpei, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-18. Pacific<br />
Forest and Range Experiment Station, U.S. Department of Agriculture, Berkeley,<br />
California. 9 pp + 11 maps.<br />
MacLean, C., Cole, T., Whitesell, C. & McDuffie K. 1988. Timber Resources of Kosrae,<br />
Pohnpei, Truk and <strong>Yap</strong>, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-24. Pacific<br />
Forest and Range Experiment Station, U.S. Department of Agriculture, Berkeley,<br />
California. 8 pp.<br />
Miyagi, T. & Kiyoshi, F. 1989. Geomorphological Situation and Stability of Mangrove Habitat<br />
of Truk Atoll and Ponape Island in the Federated <strong>State</strong>s of Micronesia. Science<br />
Reports of the Tohuku University, 7th Series (Geography) 39 (1): 25-52.<br />
Mowbray, D.L. 1988. Pesticide use in the South Pacific. UNEP Regional Seas Reports and<br />
Studies No.89; SPREP Topic Review No.26. UNEP, Nairobi.<br />
LYON ASSOCIATES 7-3
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Nedachi, M., Meada, T., Shigeyoshi, R., Inoue, A., Shimada, K., Higashi, M., Habano, A.,<br />
Azuma, T. and Hatta, A. 1999 Taktai, K.M., Nedachi, Y., Yamanouchi, H. and<br />
Matsumura, K., 2001. Geology of Environments on <strong>Yap</strong> Islands, Micronesia. Occa.<br />
Paper Kagoshima Univ. Research Center for the South Pacific, 34, 69-76 pp<br />
Nedachi, M., Taktai, K.M., Nedachi, Y., Yamanouchi, H. and Matsumura, K., 1996 Occa.<br />
Paper Kagoshima Univ. Research Center for the South Pacific, 32, 24-29 pp<br />
Nelson, S.G. (ed.) 1989. The Inland Aquatic Habitats of <strong>Yap</strong>. University of Guam Marine<br />
Laboratory Technical Report No.92. Mangilao, Guam. 78 pp.<br />
Pettys, E., Peter, S., Rugg, R. & Cole, T. 1986. Timber Volumes in the Mangrove Forests of<br />
Pohnpei, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-19. Pacific Forest and<br />
Range Experiment Station, U.S. Department of Agriculture, Berkeley, California.<br />
Pratt, H.D., Bruner, P.L. & Berrett, D.G. 1987. A Field Guide to the Birds of Hawaii and the<br />
Tropical Pacific. Princeton University Press, Princeton, U.S.A. 409 pp.<br />
Smith, C.M. 1983. Soil Survey of Islands of <strong>Yap</strong>, Federated <strong>State</strong>s of Micronesia. USDA<br />
Soil Conservation Service, Washington, D.C. 90 pp + 1 map and 18 aerial photos.<br />
SPREP 1993. The Federated <strong>State</strong>s of Micronesia Nationwide Environmental Management<br />
Strategies. Apia, Western Samoa.<br />
Stemmermann, L. 1981. A guide to Pacific wetland plants. U.S. Army Corps of Engineers,<br />
Honolulu, Hawaii. 118 pp.<br />
Stemmermann, L. & Proby, F. 1978. Inventory of Wetland Vegetation in the Caroline<br />
Islands (2 volumes). U.S. Army Corps of Engineers, Pacific Ocean Division, Fort<br />
Shafter, Hawaii. 93 pp + 61 maps (Volume 1); 382 pp (Volume 2).<br />
Trustrum, N.A. 1996. Pohnpei’s Watershed Spatial Plan and Management Guidelines.<br />
Landcare Research, New Zealand, Ltd. Palmerston North, New Zealand.<br />
Tsuda, R.T., Fosberg, F.R. & Sachet, M.H. 1977. Distribution of Seagrasses in Micronesia.<br />
Micronesica 13 (2): 191-198.<br />
UNEP/IUCN 1988. Coral Reefs of the World. Volume 3: Central and Western Pacific. UNEP<br />
Regional Seas Directories and Bibliographies. IUCN, Gland, Switzerland and<br />
Cambridge, U.K./UNEP, Nairobi, Kenya.<br />
U.S. Army Corps of Engineers, Pacific Ocean Division 1988. <strong>Yap</strong> Coastal Resource Atlas.<br />
Manoa Mapworks, Honolulu, Hawaii. 67 pp.<br />
U.S. Army Corps of Engineers, Pacific Ocean Division 1989b. <strong>Yap</strong> Islands Coastal<br />
Resource Inventory. U.S. Army Corps of Engineers, Pacific Ocean Division, Fort<br />
Shafter, Hawaii. 355 pp.<br />
U.S. Department of Agriculture, Soil Conservation Service, Forest Service, U.S. Department<br />
of Interior, Office of the High Commissioner, Trust Territory of the Pacific Islands,<br />
University of Hawaii at Manoa, College of Tropical Agriculture and Human Resources<br />
1981. General Soil Map, Islands of <strong>Yap</strong>, FSM.<br />
Western Regional Climate Center 2007. Summary Precipitation <strong>Yap</strong> WSO Station.<br />
Whitesell, C., MacLean, C., Falanruw, M., Cole, T. & Ambacher, A. 1986. Vegetation<br />
Survey of Kosrae, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-17. Pacific<br />
Forest and Range Experiment Station, U.S. Department of Agriculture, Berkeley,<br />
California. 8 pp + 1 map.<br />
Wiles, G.J., D.W. Buden and D.J. Worthington 1999. History of introduction, population<br />
status, and management of Philippine deer (Cervus mariannus) on Micronesian<br />
Islands. Mammalia, t.63,n o 2: 193-215<br />
Wilson, A. Meriwether & Hamilton, L.S. (eds) 1992. Kosrae Island Integrated Coastal<br />
Resources Assessment for Biodiversity/Cultural Conservation and Nature-Based<br />
Tourism. The East-West Center, Environment and Policy Institute, Honolulu, Hawaii.<br />
121 pp.<br />
LYON ASSOCIATES 7-4
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
<strong>Yap</strong> <strong>State</strong> Environmental Protection Agency, c. 1995. Title II Environmental Impact<br />
Assessment.<br />
Ziemer, R.R., & Megahan, W.F. 1991. Erosion and Sedimentation Control on Roads and<br />
Construction Sites in the Federated <strong>State</strong>s of Micronesia.<br />
LYON ASSOCIATES 7-5
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
This preliminary environmental impact statement was prepared by Terry Kearney, PE, Civil<br />
and Environmental Engineer. Mr. Kearney has reviewed and/or prepared environmental<br />
documents for 38 years. He has a masters degree in public health with a specialty in<br />
environmental heath and a masters degree in urban and regional planning. He has worked<br />
for Lyon Associates for eight years.<br />
LYON ASSOCIATES 7-6
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Appendix A<br />
OBSERVATIONS DURING TRIP TO FSM<br />
October 28 to November 8, 1990<br />
Robert R. Ziemer & Walter F. Megahan<br />
YAP<br />
We drove the length of the cross-island road that was being constructed by You One<br />
Construction Company from Korea. The new road runs from Colonia through Tomil to the<br />
northeastern coast of Maap. Construction began in Maap and is proceeding to Colonia.<br />
Construction is nearing completion in Maap and Tomil, but paving had not yet begun. Rightof-way<br />
clearing is just beginning near Colonia. The road seems to be well-designed. The<br />
subgrade is being stabilized using injected Condor SS. This is designed to chemically<br />
extract water from the clay lattice, allowing the lattice to collapse and the clay to be<br />
compacted. There was local concern about the environmental safety of Condor SS. There<br />
was an unverified report that about 500 gallons of the material had recently been spilled,<br />
but we did not see the location.<br />
The road surface is crowned, directing drainage to poured-in-place concrete V-shaped<br />
drainage ditches on both sides of the road. We were unable to obtain information on the<br />
design flow of the ditches, but they appear in some cases to be too small to carry intense<br />
storm runoff. In several cases, the ditches are so constructed that runoff will probably jump<br />
the turn at the downhill end and continue down the road rather than be diverted from the<br />
road as expected.<br />
The road near Colonia is intended to encroach into the mangrove and lagoon margin. We<br />
recommend that during construction, a silt; fence be installed to limit migration of sediment<br />
into the lagoon. And, upon completion of the subgrade, the road fill be protected by a sea<br />
wall or rip-rap.<br />
At the bridge site between Tomil and Maap, the channel has been filled and an extensive<br />
soil disposal site has been constructed on the Tomil side of the channel. All flow within the<br />
channel has been blocked by the fill and the mangrove appears to be stressed and the<br />
leaves seem to be yellowing. A burlap silt fence has been constructed near the disposal<br />
site, but it seems to be ineffective. The plan is to construct a bridge and to eventually<br />
remove the fill. Construction costs are probably lowered by this method, but the amount<br />
of sediment introduced to the channel is very large. The environmental consequences of<br />
this additional sediment is unknown.<br />
About 1 mile from the bridge site on Maap, there is a large fill and disposal site containing<br />
about 30,000 cubic yards of soil. This material appears to be uncompacted and poor<br />
surface drainage has caused severe gullying on the fill face. Eroded material is being<br />
transported to and down a small drainage basin to be discharged into the lagoon about 1/4<br />
mile away. Surface drainage here should be controlled and routed to a hardened and safe<br />
location. The fill should be quickly revegetated with woody plants to provide some<br />
LYON ASSOCIATES 7-7
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
strength to the weak fill. Revegetation will assist in stabilizing the fill, but since the entire fill<br />
was not compacted there is little internal strength and vegetation can not be expected to<br />
solve the problem. Unless surface water is directed away from the fill face, a serious<br />
gullying problem can be expected at this location for years. In addition, a silt fence: or<br />
barrier should be installed at the base of the fill to catch eroded material.<br />
Although the road itself seems to have been well-designed, the provision for dealing with<br />
water once it leaves the road is poorly planned. Apparently, concern for off-road<br />
environmental damage was not part of the road design. For example, it is not uncommon<br />
for roadside ditches to carry water for up to 1600 feet before discharging into a stream or<br />
scale. At such discharge points, inadequate provision has been made to protect the slope<br />
or stream channel from the volume or force of the water that will be discharged. For a 40-<br />
foot wide roadway, the ditch discharge for a 1600-foot run during a 1-inch storm would be<br />
20x1600x(1/12)=2667 cubic feet of water. In this climate, it is perhaps not unusual to have a<br />
1-inch rainfall in 10 minutes. It is important to calculate expected 5- and 10-minute<br />
intensities for different return intervals, and further to calculate anticipated peak discharges<br />
from the road surface and surrounding right-of-way that contributes to ditch flow. The NOAA<br />
Weather Service collects such intensity data, but discussions with the local NOAA offices in<br />
<strong>Yap</strong>, Chuuk, Pohnpei, Kosrae, Guam, and Honolulu did not yield the records.<br />
Where energy dissipation and channel lining is provided, it is too small an effort to be very<br />
effective during storm flows. Across the road from the Maap fill disposal site is an example<br />
of poorly designed discharge of road drainage. The road drainage ditch runs for about 1100<br />
feet to a drop inlet where a box culvert discharges into a small grass and fern vegetated<br />
swale. Although water has been directed onto this scale for only about a month, there is<br />
evidence that a deep gully will form within a short time. The shallow grass-fern root system<br />
has already been penetrated by the incipient gully and there is little soil resistance to<br />
prevent accelerated gullying. It is important to control the force of water leaving the culvert<br />
and as it travels down this steep swale. We suggested that this would be an ideal place to<br />
demonstrate erosion control techniques. It is important to get some woody vegetation<br />
established to provide a fibrous root system and strengthen the soil. Marjorie Falanruw<br />
suggested that hibiscus can be established by simply pushing cuttings into the ground. It<br />
would be useful to test several types of vegetation for effective erosion control. The<br />
vegetation should be quick to establish and produce a deep and dense network of fibrous<br />
roots. In addition, the vegetation must be capable of withstanding the force of high velocity<br />
running water. The force of water could be reduced by placing and staking logs across the<br />
slope, creating a series of check dams as the water is routed down the slope. Had the water<br />
been routed about another 50 feet down the road, it could have been discharged onto a<br />
small ridge, rather than into the swale, and the runoff would have tended to disperse rather<br />
than concentrate.<br />
The question of the effectiveness of Vetiver grass was raised. There is<br />
concern in <strong>Yap</strong> that if introduced, Vetiver may escape and become a pest. In general, it is<br />
preferable that native rather than introduced species be used for three reasons: the ready<br />
availability of native materials, the cost of exotics, and the hazard of exotics becoming a<br />
pest.<br />
Not only has off-road erosion control not had high priority in the road<br />
design, there are no funds budgeted for continued road maintenance, let alone<br />
off-site erosion control.<br />
LYON ASSOCIATES 7-8
NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />
Unfortunately, without some local responsibility and technical direction, it is doubtful that<br />
any preventative action will be taken and large scale gullies will become common at the<br />
outfalls of many road ditches. Once the gullies form, repair or control will be extremely<br />
expensive and probably beyond the financial and technical capabilities of <strong>Yap</strong> <strong>State</strong>. To the<br />
direct costs of erosion control must be added the additional environmental damage to<br />
hill slopes, streams, taro patches, and lagoon ecology.<br />
Although we spent much of our time observing the major cross-island road, there are<br />
numerous secondary and agricultural roads that are constructed with little or no planning or<br />
erosion maintenance. In total, these roads produce a large and dispersed source of<br />
continuing sedimentation to agriculture, streams, and lagoon. Some of these secondary<br />
roads are constructed by the Seabees, sometimes as a favor to the local chief or<br />
landowner. It is common for <strong>Yap</strong> EPA to be excluded from review or notification. There<br />
should be some central clearing house agency or procedure for requesting and reviewing<br />
road construction plans.<br />
We visited the NOAA Weather Station on <strong>Yap</strong>, Chuuk, Pohnpei, and Kosrae. The story<br />
was the same at each location: the local station does not retain weather data, but sends it<br />
all to the National Climate Data Center in Ashville, NC. Each station records the time of<br />
each tip of the tipping-bucket rain gage (0.01-inch). Rainfall intensities of 24-hour and 1-<br />
hour have been published for the past 30+ years, but the 1-hour intensities are on the datatapes<br />
for only the past 3 or so years. NOAA states that previous years have not been<br />
"digitized". For estimating erosion hazard from small drainages, it is important to develop<br />
intensity curves for time periods as short as 5 minutes. The time of concentration for peak<br />
discharge from the road ditches will be 5 to 10 minutes.<br />
We visited the USGS gauging stations at Burong Stream and Eyeb Stream. We found the<br />
concrete weirs, but the gage housing had been removed. When we arrived in Guam, we<br />
telephoned Greg Ikehara, USGS Guam (339-5293). He stated that in August the <strong>Yap</strong> <strong>State</strong><br />
Legislature did not vote funds to continue data collection. Ikehara has been working<br />
primarily with Charles Chieng, Director of <strong>Yap</strong> Public Works. Adrian Gimed has been the<br />
streamgager on <strong>Yap</strong> for many years. He has not been employed since funding was<br />
terminated. Funding for gaging stations is shared equally between each FSM <strong>State</strong> and the<br />
USGS. Earlier in the year, Ikehara and Bill Meyer of the USGS Honolulu office (808-541-<br />
2654) visited <strong>Yap</strong> to explain to the Governor, Legislature, and Public Works Director Chiang<br />
the importance of the hydrologic record. Ikehara thought that their arguments were wellreceived<br />
and that funding would be restored, but as of November there has been no further<br />
communication with <strong>Yap</strong>. Ikehara also mentioned that streamgages were discontinued and<br />
removed from Chuuk <strong>State</strong> "several years ago" after a couple years of continued nonpayment<br />
of the Chuuk <strong>State</strong> funding share. Ikehara stated that funding was continuing in<br />
Pohnpei and Kosrae and the stream gages were still operating there. However, when we<br />
arrived in Kosrae we were told by Bruce Howell that the Kosrae legislature had recently<br />
voted to terminate funding for the Kosrae gauging station network. Howell stated that the<br />
Kosrae share of the cost was $5000 per year.<br />
LYON ASSOCIATES 7-9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
SERIES 100<br />
PRELIMINARIES AND GENERAL DESCRIPTION OF WORKS<br />
101. INTRODUCTION<br />
101. The <strong>Government</strong> of <strong>Yap</strong> <strong>State</strong> as part of their road development program<br />
proposes to rehabilitate and improve approximately 4.06 miles of road known<br />
as Northern <strong>Yap</strong> Road Improvements Project.<br />
102. LOCATION<br />
102.1 The project is located in central to northern <strong>Yap</strong> <strong>State</strong>, Federated <strong>State</strong>s of<br />
Micronesia.<br />
103. DETAILS OF PROJECT<br />
103.1 The beginning of the project is at the Hospital Intersection with the main road to<br />
Keng. It proceeds north and terminates at the western edge of Tagireeng<br />
Bridge. This segment of the road travels along the coastline through the villages<br />
of Keng, Dugor, Makal, Tafgif, Rumuu, Gargey, and Daboch.<br />
104. WORKS INCLUDED IN THIS CONTRACT<br />
104.1 The scope of Works includes:<br />
a) Site clearing of shrubs and undergrowth, grubbing, demolition of<br />
obstructions on the site in the way of or otherwise affected by the Works as<br />
shown in the drawing plans and specifications.<br />
b) Drainage works including culverts, concrete ditches and interceptor drains.<br />
c) Repair of gabion type seawall construction for road embankment protection<br />
in low areas.<br />
d) Subbase preparation, base and wearing course for the pavement.<br />
e) Asphalt paving works.<br />
f) Maintain all roads or access affected by construction in a motorable<br />
condition at all times.<br />
g) Payment of all costs including royalty for borrow materials from borrow pit<br />
outside the construction limit.<br />
h) All works incidental to the project including adjustment or relocation of<br />
services carried out within the terms of the Contract.<br />
SERIES 100 Page 1 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
105 WORKS UNDER WATER<br />
105.1 Certain of the Works may have to be carried out under water, and the rates and<br />
prices named by the Contractor in his bid shall include for all extra costs and<br />
changes whatsoever arising out of such work including the effects of<br />
exceptionally high flood levels and including any cost involved in working<br />
outside normal working hours or on rest days.<br />
106 WORKS TO BE COMPLETED<br />
106.1 This Specification has been drawn up with all possible care and is intended to<br />
cover supply of all materials and the execution of all works necessary to<br />
complete the Works (except as otherwise provided in this Specification). In<br />
case there are any details of construction or materials which have not been<br />
referred to in this Specification and Drawings but the necessity of which may<br />
reasonably be implied or inferred from the Specification or Drawings or which<br />
are usual or essential to the completion of all works in all trades, the same shall<br />
be deemed to be included in the Bid Price tendered by the Contractor.<br />
107. BID DOCUMENT AND VISIT SITE<br />
107.1 The Contractor shall be deemed to have read the Bid Documents for the Works<br />
and have visited the site before bidding and acquainted himself with any item or<br />
contingency liable to affect his bid price. No claims for extra remuneration or<br />
extension of the Contract time on the ground of ignorance of the working<br />
conditions or of his contractual obligations will be entertained.<br />
107.2 The accuracy of any particulars given or records referred to in the Contract<br />
Documents or supplied to the Contractors for their information is not in anyway<br />
guaranteed. The Contractor shall take into consideration all available records<br />
with regard to water levels, water courses, drains and all other physical features<br />
of the site in submitting his bid.<br />
108. MATERIALS PLANTS AND WORKMANSHIP<br />
108.1 Materials and workmanship throughout the works shall be of the highest quality<br />
of their respective kinds and it shall be understood that no superior class of the<br />
specified materials or workmanship is available in <strong>Yap</strong>.<br />
108.2 Unless otherwise specified, all materials and workmanship shall comply with<br />
<strong>Yap</strong> Standard and Codes of Practice where applicable and unless these are not<br />
available, American Standards and Codes of Practice shall apply.<br />
The Bidder may propose other Standards or Codes of Practice provided that<br />
the Standards or Codes are equivalent or superior to the relevant <strong>Yap</strong> or<br />
American Standards or Codes. Two copies of each Standard or Code<br />
proposed by the Bidder shall be provided by the Bidder with this bid. The<br />
Contractor shall as far as possible deploy labor, materials and plant available in<br />
<strong>Yap</strong> <strong>State</strong> in the execution and completion of the Work under this Contract.<br />
SERIES 100 Page 2 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
108.3 Due consideration in the award of bids will be given to Contractors who will<br />
make use of local resources in respect of labor, plant and materials.<br />
108.4 Wherever in this Specification any proprietary goods or materials are specified,<br />
goods or materials of alternative manufacturer may be considered for<br />
acceptance provided they comply in all respects as regards appearance and<br />
quality and are approved by the Contracting Officer.<br />
108.5 Wherever in this Specification any goods or materials are specified such is to<br />
be considered as being the minimum standard acceptable. In the event of the<br />
Contracting Officer allowing the substitution of any of these materials during the<br />
course of the contract, such substitution shall be accompanied by a<br />
corresponding deduction in cost unless the Contracting Officer directs<br />
otherwise.<br />
109. MATERIALS OF YAP ORIGIN<br />
109.1 The materials of <strong>Yap</strong>-origin where applicable must be used by the Contractor to<br />
the exclusion of imported materials and he shall allow for this special<br />
requirement in his bid.<br />
109.2 Under no circumstances will the Contractor be permitted to use imported<br />
materials unless he proves to the satisfaction of the Contracting Officer that<br />
local materials are not available, or if available are not of an acceptable<br />
standard or obtained practically.<br />
110. SUPPLY OF MATERIALS<br />
110.1 The Contractor shall place orders for specified materials at the earliest possible<br />
date after the acceptance of his bid.<br />
110.2 If the Contractor’s failure to supply any material causes any interruption or<br />
delay in the progress of the work, the Owner may supply any portion or all of<br />
the materials and the cost will be borne by the Contractor and shall be either as<br />
calculated at the current market rates or the actual cost to the Owner at the<br />
date of supply, including overheads and any other charges, whichever is the<br />
greater.<br />
110.3 Any costs incurred under the proceeding paragraphs shall be deducted from<br />
the Contract Sum by means of a Variation Order, but in the case of sub-clause<br />
110.2 above only, such Variation Order shall not be taken into account in<br />
computing the final sum on which the Retention Fund is based and no claim for<br />
loss profit under the conditions of this Contract shall be deemed to have risen.<br />
No action taken under these clauses shall in any way affect or modify the right<br />
of Owner to claim for damages in the event of the Contractor’s failure to<br />
complete the wok by the agreed date.<br />
111. SAMPLES<br />
111.1 The Contracting Officer shall be at liberty to call for submission of samples of<br />
materials or the execution of samples of workmanship for approval, and for<br />
SERIES 100 Page 3 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
further samples as are required until the samples submitted or executed are, in<br />
his opinion, in accordance with this Specification.<br />
112. INSURANCE AND LICENSES<br />
112.1 The Contractor shall ensure and provide evidence to the Owner that all his<br />
plant operators and lorry drivers do posses valid driving licenses and all earthmoving<br />
plant and vehicles shall be covered by third party insurance policies.<br />
The Contractor shall comply with the requirements of the <strong>Yap</strong> <strong>State</strong> Road<br />
Traffic Ordinance in all respects.<br />
113. WORKMEN’S ACCOMMODATIONS<br />
113.1 The Contractor shall provide, maintain and remove on completion of the works<br />
any necessary temporary accommodation and living facilities including all<br />
necessary services for water supply, drainage and lighting for his staff.<br />
113.2 Before any work is commenced on temporary accommodation the Contractor<br />
shall submit to the Contracting Officer a location plan and details of the<br />
proposed accommodations and services for his approval. The Contractor shall<br />
also comply with any statutory obligations and obtain any necessary approval<br />
from Statutory Authorities in writing, a copy of which shall be sent to the<br />
Contracting Officer.<br />
114. MEDICAL SERVICES<br />
114.1 The Contractor shall provide adequate medical services and first aid facilities<br />
suitable to the size and composition of his staff and labor force. The Contractor<br />
shall afford the Contracting Officer’s site staff full use of the services and<br />
facilities when required.<br />
115. EVERYTHING AT CONTRACTOR’S RISK<br />
115.1 All buildings, structures, furniture, equipment, plant, and things whatsoever<br />
which the Contractor is required by this Section of the Specification or<br />
elsewhere in the Contract Documents to provide shall at all time be at the risk<br />
of the Contractor, who shall at his own cost maintain them and renew anything<br />
as necessary notwithstanding any use of or damage thereto caused by the<br />
Contracting Officer’s site staff.<br />
116. REVERSION TO CONTRACTORS<br />
116.1 On completion of the Contract Works all buildings, structures, furniture,<br />
equipment, plant, and things provided and maintained under the terms of this<br />
Section of the Specification unless otherwise stated shall revert to the<br />
Contractor, who shall dismantle and remove all such things from the site and<br />
leave the site clean and reinstated to the approval of the Contracting Officer.<br />
SERIES 100 Page 4 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
117. PROGRAM TO BE PROVIDED<br />
117.1 The Contractor shall submit with his bid a preliminary program outlining his<br />
working methods, expected times or completion for the various parts of the<br />
work, details of any temporary structures he proposes to use and a schedule of<br />
plants and equipment.<br />
117.2 As soon as possible after the acceptance of his bid, the Contractor shall, if<br />
required, submit to the Contracting Officer for his approval, a detailed program<br />
showing the method of working, full details of any temporary structures and<br />
expected dates for completion of the various parts of the work. Refer to sub-<br />
Clause 4.5, Additional General Requirements.<br />
117.3 Once a program has been approved or agreed, the Contractor shall make every<br />
effort to maintain this program.<br />
117.4 The program may be revised subject to approval by the Contracting Officer.<br />
118. CONTRACTOR’S SUPERINTENDENCE<br />
118.1 The Contractor shall provide all necessary superintendents during the execution<br />
of the Works and as long thereafter as the Contracting Officer may consider<br />
necessary for the proper fulfillment of the Contractor’s obligations under the<br />
Contract.<br />
118.2 Without prejudice to sub-clause 7.17 of the General Requirements, the<br />
Contractor shall appoint a Site Agent who must be a qualified Engineer having<br />
sufficient relevant experience and he shall be approved by the Contracting<br />
Officer in writing (which approval may at any time be withdrawn). He shall have<br />
an aptitude for organizing and controlling men, be able to think quickly and<br />
decisively, and deal courteously and tactfully with other members of the<br />
Construction Team. He shall be constantly on the Works and shall devote the<br />
whole of his time to the superintendence of the same. If such approval is<br />
withdrawn by the Contracting Officer, the Contractor, as soon as is practicable<br />
after receiving written notice of such withdrawal shall remove the Agent from<br />
the site and shall not employ him again on the site in any capacity. Another<br />
Site Agent approved by the Contracting Officer shall replace him to take over<br />
his duties.<br />
119. DIMENSIONS AND LEVELS<br />
119.1 Before the Works or any part thereof are commenced the Contractor shall verify<br />
the dimensions and levels shown on the drawings and shall notify the<br />
Contracting Officer of any discrepancy which may affect the dimensions or<br />
levels of any part of the works. Such notification by the Contracting shall be<br />
given sufficient time to allow the Contracting Officer to prepare drawings or<br />
schedules showing his amended requirements.<br />
119.2 The Contractor shall in particular verify the levels of the existing ground<br />
surfaces within areas earthworks are to be performed and the locations and<br />
SERIES 100 Page 5 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
bed levels of watercourses. These may differ from the locations and levels<br />
shown on the drawings depending on the extending of erosion of the banks and<br />
beds are which has taken place during the interval between survey and<br />
construction. Existing roadway has been maintained by grading and there may<br />
be slight variations in the existing elevations with that shown on the drawings.<br />
120. SETTING OUT<br />
120.1 The Contractor shall be responsible for the true and proper setting out of the<br />
works and for the correctness of the position levels, dimensions and alignment<br />
of all parts of the works and for the provision of all necessary instruments,<br />
appliances and labor in connection therewith. If at any time during the progress<br />
of the works any errors shall appear or arise in the position levels dimensions or<br />
alignment of any part of the works the Contractor on being required so to do by<br />
the Contracting Officer unless such error is based on incorrect data supplied in<br />
writing by the Contracting Officer in which case the expense of rectifying the<br />
same shall be borne by the Owner. The checking of any setting-out of any line or<br />
level by responsibility for the correctness thereof and the Contractor shall<br />
carefully protect and preserve all benchmarks, sight rails, pegs and other things<br />
used in setting out the Works. The Contractor shall establish all horizontal curve<br />
points of intersection (PI’s), beginning of curve (BC’s), and end of curve (EC’s),<br />
and establish ties for these.<br />
120.2 Before commencing earthmoving at any location, the Contractor shall provide<br />
and install pre-cast concrete reference beacons on both sides of the road<br />
centerline at a spacing of 1,000 feet. The beacons shall be firmly sited at right<br />
angles to the centerline offset 50 feet or such other distance as directed by the<br />
Contracting Officer. The beacons shall not be less than 4 inch square in plan<br />
and shall take all practicable steps to safeguard the beacons including fencing<br />
and concreting in where necessary in the opinion of the Contracting Officer and<br />
shall replace any damaged beacons.<br />
120.3 The Contractor shall place slope stake at 50-foot intervals, where possible, on<br />
both sides of the roadway for the entire length of the project. The slope stakes<br />
shall consist of a wooden hub driven flush to the existing ground at the catch<br />
point with a four- foot lathe with a ribbon tied to the lathe. The appropriate fill or<br />
cut data shall be clearly written on the lathe. These shall be replaced as<br />
necessary and shall remain in place until the slope has been checked and<br />
approved by the Inspector.<br />
120.4 The Contractor shall place grade stakes at 50-foot intervals, where possible.<br />
Grade stakes shall be wooden hubs driven to the elevation of the edge of<br />
pavement and offset from the edge of pavement by a standard distance. The<br />
stakes shall remain in place, and shall be replaced if destroyed, until not longer<br />
needed.<br />
120.5 The Contractor shall place finish grade stakes at 50-feet interval. The<br />
Contractor shall demonstrate to the Contracting Officer that the various<br />
structural sections comply with allowable grade tolerances.<br />
SERIES 100 Page 6 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
121. TEMPORARY ACCESS, BRIDGES, CULVERTS, ROAD, ETC.<br />
121.1 The Contractor shall provide and maintain as long as required temporary road<br />
deviations, access roads, culverts, bridges, etc. as required facilitating the<br />
transport of materials and for the smooth construction of the work.<br />
121.2 On completion of the whole work and as directed by the Contracting Officer<br />
such temporary culverts, bridges, etc. that may have been constructed shall be<br />
removed by the Contractor and he shall make good any work disturbed during<br />
the removal.<br />
122. PUBLIC SERVICES<br />
122.1 The services identified on the drawings for adjustment or relocation are not<br />
based on field survey data. The Contractor shall verify the exact locations of<br />
these services and all other services that may exist along or across or adjacent<br />
to the works before beginning excavation work. The Contractor shall obtain<br />
permission from the C.O. and the respective <strong>Yap</strong> authority before adjusting or<br />
disturbing services of any utilities. Construction schedule shall have been<br />
approved before any work may begin on service relocation.<br />
122.2 Any damage that may occur to such services due to the negligence on the part<br />
of the Contractor or his employees, or to the improper execution of the<br />
Contracting Officer’s instruction shall be the responsibility of the Contractor who<br />
shall bear all costs for making good such damage.<br />
123. LIMITATIONS OF SITE<br />
123.1 The Contractor shall ensure that all his plant, materials, temporary workshops,<br />
store and offices shall be kept within the areas allotted to him by the<br />
Contracting Officer.<br />
123.2 Should the Contractor require additional land, outside the site for his workyards,<br />
workshops, stores, offices, temporary haul roads or any other temporary<br />
structures he shall make his own arrangements to acquire or rent so much as<br />
he may need subject to the approval by the Contracting Officer.<br />
124. COVERING UP OF WORK<br />
124.1 The Contractor shall not cover up, cast over, backfill or otherwise put out of<br />
view any work without the permission of the Contracting Officer and where<br />
directed by the Contracting Officer he shall take finish levels of the work and<br />
record these on Drawings to be signed as agreed by the Contractor and the<br />
Contracting Officer. The Contractor shall give due notice to the Contracting<br />
Officer whenever such works or foundation are ready for examination and the<br />
Contracting Officer shall attend without unreasonable delay for the purpose of<br />
examining and measuring unless he considers it unnecessary and advises the<br />
Contractor accordingly.<br />
SERIES 100 Page 7 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
124.2 If the Contractor cover up any works without the Contracting Officer’s<br />
permission, the Contractor at his own expense shall uncover or make openings<br />
in any parts of the work as and when directed by the Contracting Officer for the<br />
purpose of examination and shall reinstate and make good those parts to the<br />
satisfaction of the Contracting Officer.<br />
125. PROTECTION OF MATERIALS AND WORKS<br />
125.1 The Contractor shall provide at his own cost all things necessary for the proper<br />
protection and storage of materials to be used in the works and shall comply<br />
with manufacturer’s instructions and such directions as may be given by the<br />
Contracting Officer in this respect.<br />
125.2 The Contractor shall also his own cost provide all things necessary for the<br />
proper protection of completed works and works in progress and shall comply<br />
with such directions as may be given by the Contracting Officer in this respect.<br />
126. EXISTING ROADS AND CONVEYANCE OF PLANT AND MATERIALS<br />
126.1 The Contractor shall be responsible for any damage cause by his construction or<br />
construction traffic to any existing roads or culverts from whatsoever cause<br />
arising and shall repair and reinstate same to their original conditions to the<br />
satisfaction of the Contracting Officer and in addition shall keep such roads clear<br />
of slurry, boulders and loose earth resulting from the works.<br />
126.2 Should the Contractor not maintain, repair or reinstate the effected roads the<br />
cost of such maintenance and restoration shall be deducted from any monies<br />
due to or to become due to the Contractor under this contract.<br />
126.3 The Contractor shall arrange for the conveyance of materials and plant so as to<br />
cause a minimum of damage to existing roads and culverts and a minimum of<br />
inconvenience to the public and shall not deposit any earth, rubbish or materials<br />
upon any road, street, pavement or footway to the hindrance or obstruction of<br />
vehicles or pedestrians.<br />
127. CLEARING THE SITE ON COMPLETION<br />
127.1 On completion of the works and before the Contracting Officer issues the<br />
completion certificate, the Contractor shall dismantle and remove from the site<br />
all plant, temporary staging, traffic signs etc., temporary buildings, latrines,<br />
temporary water pipes and electricity cables and anything else not included in<br />
the works that is on site and as may be directed by the Contracting Officer.<br />
127.2 All areas shall be made good and all rubbish, debris and surplus materials shall<br />
be removed from the site and whole of the site and works shall be left in a clean<br />
and tidy condition to the satisfaction of the Contracting Officer.<br />
128. RESERVED<br />
SERIES 100 Page 8 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
129. PHOTOGRAPHS<br />
129.1 The Contractor shall supply progress photographs of a size not less that 4 X 6<br />
inches of such portions of the works in progress and completed as may be<br />
directed by the Contracting Officer each month. The camera used shall be of<br />
the SLR type and to the approval of the Contracting Officer. Photographs shall<br />
be supplied to the Contracting Officer within 14 days of the photograph being<br />
taken. The original copies of these photographs shall be the property of the<br />
Owner and no prints may be supplied to any person or persons except with the<br />
authority of the Owner or the Contracting Officer. A suitable typed subject and<br />
date taken must be visible in all the printouts. The Contractor and the<br />
Contracting Officer shall sign one copy of each photograph.<br />
130. EMPLOYMENT OF LOCAL LABOR, SUB-CONTRACTORS AND<br />
SUPPLIERS<br />
130.1 All labors, sub-contractors and suppliers used in connection with the works<br />
shall be employed from within the <strong>State</strong> where the works are situated. The<br />
Contractor shall immediately after taking possession of site, arrange with the<br />
local Labor Office or chief to affect such employment. Under no circumstances<br />
will Contractor be permitted to use imported laborers, sub-contractors and<br />
suppliers unless the Division of Manpower is satisfied that these are not<br />
available within the <strong>State</strong> of District concerned.<br />
131. EARTHMOVING AND DREDGING PERMITS<br />
131.1 Earthmoving Permit: The Contractor will not be allowed to execute any<br />
earthwork until the Contractor has procured an Earthmoving Permit. The<br />
Contractor is advised to procure the said Earthmoving Permit as soon as<br />
possible. Currently the Earthmoving Permit applications are processed by the<br />
Environmental Protection Agency (EPA), <strong>Yap</strong> <strong>State</strong>, and require approximately<br />
two months for approval.<br />
131.2 Dredging Permit: Dredge site is indicated on maps of Yyin Dredging Site. The<br />
Contractor shall supply all labor and equipments necessary to remove any<br />
deleterious materials and to obtain corals from the dredge site. The site shall<br />
be dredged in such a way that a navigable canal will be formed. The canal shall<br />
be at least one hundred (100) feet width and minimum ten (10) feet depth at<br />
mean low tide (dimensions will depend on the final environmental study).<br />
Should more dredged corals be required after the excavation of this canal, the<br />
canal may be widened to the extent approved by the C.O. The Contractor is<br />
not expected to pay royalties for dredging corals at the designated dredge site.<br />
However, it is recommended to verify before any dredging activity commences.<br />
No dredging will be allowed until the Contractor has procured an Earthmoving<br />
Permit. The Contractor is advised to consult C.O. for Dredging Permit.<br />
Currently the Dredging Permit applications are processed at the Environmental<br />
Protection Agency, <strong>Yap</strong> <strong>State</strong>.<br />
****** END OF SECTION ******<br />
SERIES 100 Page 9 of 9
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
SERIES 200<br />
ENVIRONMENTAL PROTECTION<br />
201. APPLICABLE PUBLICATIONS: The following publications listed below,<br />
including amendments and extensions effective as of the date of bid opening,<br />
but referred to thereafter by basic designation only, form a part of this<br />
specification to the extent indicated by references.<br />
201.1 <strong>Yap</strong> Environmental Protection Agency:<br />
201.1.1 Environmental Protection as amended or extended effective on date of bid<br />
opening.<br />
201.1.2 Regulations concerning the Control of Earthmoving and Sedimentation.<br />
201.1.3 Standards of Water Quality for the Waters.<br />
201.1.4 Earthmoving Permit (to be obtained by Contractor)<br />
(Note: This document will be made a part of the contract documents.)<br />
201.2 United <strong>State</strong>s <strong>Government</strong>:<br />
201.2.1 Federal Water Pollution Control Act, P.L. 92-500 as amended or extended<br />
effective on date of bid opening.<br />
202. ENVIRONMENT PROTECTION PLAN<br />
202.1 The Contractor shall be responsible for the preparation and submittal of an<br />
Environmental Protection Plan. After the contract is awarded, prior to the<br />
commencement of the work, the Contractor shall meet with the Contracting<br />
Officer, or his representative, and discuss the proposed Environmental<br />
Protection Plan. The meeting shall develop mutual understanding relative to<br />
details of environmental protection, including required reports and measures to<br />
be taken should the Contractor fail to provide adequate environmental<br />
protection in an adequate and timely manner. Not more than 14 days after the<br />
meeting, the Contractor shall submit for approval his proposed Environmental<br />
Protection Plan. The Contracting Officer before start of work by the Contractor<br />
shall approve this plan.<br />
202.2 The Contractor’s Environmental Protection Plan shall reflect the logical<br />
utilization of his available equipment, his scheme of operation, and the use of<br />
environmental protection devices specified herein.<br />
202.3 The plan must contain features that will satisfy the requirements of this Section<br />
and regulations concerning the control of earthmoving and sedimentation.<br />
Provisions shall be made in the plan for protecting existing trees which are to<br />
remain and which may be injured, bruised, defaced, or otherwise damaged by<br />
construction operations. Rocks that are displaced into un-cleared areas shall<br />
be removed. Monuments, markers, and works of art shall be protected before<br />
beginning operations. A pre-construction survey including photographs shall be<br />
SERIES 200 Page 1 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
accomplished by the Contractor and a report of survey furnished when required<br />
by the Contracting Officer.<br />
203. GENERAL REQUIREMENTS<br />
203.1 All applicable environmental protection measures of the F.S.M. and <strong>Yap</strong><br />
<strong>Government</strong>s are hereby incorporated in and made a part of these<br />
Specifications. All work performed by the Contractor and his subcontractors<br />
shall comply with the intent of all applicable publications.<br />
203.2 The Contractor shall provide and maintain environmental protection during the<br />
life of the contract as defined herein. Environmental protection shall be<br />
provided to correct conditions that develop during the construction period prior<br />
to the construction of permanent environmental protection features. Except<br />
where specifically exempted in this Contract, the Contractor’s operations shall<br />
comply with all federal and local regulations pertaining to water, air, solid waste<br />
and noise pollution. In the event that temporary additional environmental<br />
protection measures, over and above those described in the Environmental<br />
Protection Plan, are required due to the Contractor’s negligence, carelessness,<br />
or failure to provide permanent protection as part of the work scheduled, the<br />
Contractor shall take remedial action to correct the deficiencies at no additional<br />
cost. Failure to comply with all environmental protection measures outlined in<br />
this Section or as ordered by the Contracting Officer will be cause for<br />
suspension of work.<br />
204. DEFINITIONS<br />
204.1 Environmental Pollutions: Environmental pollution is defined as the presence<br />
of chemical physical or biological elements or agents that adversely affect<br />
human health or welfare; unfavorably alter ecological balances of importance to<br />
human life; affect other species of importance to man; or degrade the utilization<br />
of the environment for aesthetic and recreational purposes.<br />
204.2 Sediment: Sediment is soil that has been eroded and transported by runoff<br />
water. Sediment is also all water-borne and settled particles resulting from<br />
dredging operations including drag lining, handling, placing and disposal of<br />
dredged materials.<br />
204.3 Degradable Debris: Degradable debris is debris from demolition, clearing and<br />
construction, which can undergo biodegradation, combustion or be dissolved or<br />
suspended by water; including, but not limited to wood, paper, gypsum, unset<br />
cement, lime and natural vegetation and organic matter.<br />
204.4 Non-Degradable Debris: Non-degradable debris is inorganic or organic<br />
material from the demolition, clearing and construction that will not disintegrate<br />
nor dissolve when exposed to moisture or water and does not contain nor has<br />
been contaminated by any of the materials described under chemicals.<br />
204.5 Chemicals: Chemicals include petroleum products, bituminous materials,<br />
salts, acids, alkalies, and herbicides and pesticides.<br />
SERIES 200 Page 2 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
204.6 Sanitary Wastes: Sanitary waste consists of sewage and garbage. Sewage is<br />
defined as what is normally considered as domestic sanitary sewage. Garbage<br />
s defined as refuse and scraps resulting from preparation, cooking, dispensing<br />
and consumption of food.<br />
204.7 Project Limits: The project limits are generally defined as being within 20’ of<br />
either side of the work or to be within the road right of way. Construction<br />
activity shall be confined within these limits.<br />
204.8 Water Quality Boundary: The boundary where construction occurs beyond<br />
the shoreline, and at the dredge site is located 200 feet outside the project or<br />
dredge limits.<br />
205. PROTECTION OF NATURAL RESOURCES<br />
205.1 General: It is intended that the natural resources within the project boundaries<br />
and outside the limits of permanent work performed under this contract be<br />
preserved in their existing condition or be restored to an equivalent or improved<br />
condition upon completion of the work. The Contractor shall confine his<br />
construction activities to areas defined by the work schedule, drawings and<br />
specifications. Where there are no regulations covering specific protection of<br />
environment, United <strong>State</strong>s <strong>Government</strong> regulations shall apply.<br />
205.2 Land Resources: Except in areas indicate to be cleared, the Contractor shall<br />
not remove, cut, deface, or destroy trees or shrubs without special permission<br />
from the Contracting Officer. No ropes, cables, or guys shall be fastened to or<br />
attached to any existing nearby trees for anchorages unless specifically<br />
authorized. Where such special emergency use is permitted, the Contractor<br />
shall be responsible for any damage resulting from such use.<br />
205.2.1 Repair of Restoration: All trees or other landscape features scarred or<br />
damaged by the Contractor’s equipment or operations shall be repaired and/or<br />
restored to their original condition at the Contractor’s expense, to the<br />
satisfaction of the Contracting Officer.<br />
205.2.2 Temporary Construction: The Contractor shall obliterate all signs of temporary<br />
construction facilities such as haul roads, work areas, structures, foundations of<br />
temporary structures, stockpiles of excess or waste materials and all other<br />
vestiges of construction. Temporary roads, parking areas and similar temporary<br />
use areas shall be graded in conformance with surrounding areas, tilled and<br />
seeded. Seeding shall include topsoil and/or nutriment as necessary to<br />
establish a suitable stand of grass.<br />
205.3 Water Resources: All work under this contract shall be performed in such a<br />
manner that all adverse environmental impact is reduced to a level that is<br />
acceptable to the Contracting Officer.<br />
205.3.1 Stream Crossing: Stream crossings by fording with equipment shall be limited<br />
so as to control turbidity, and in areas of frequent crossings, temporary culverts<br />
or bridge structures shall be removed upon completion of the project and the<br />
SERIES 200 Page 3 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
area repaired in conformance with its original condition or as indicated or<br />
specified.<br />
205.3.2 Oily Substances: At all times, special measures shall be taken to prevent oily<br />
or other hazardous substances from entering the ground, drainage areas, or<br />
local bodies or water in such quantities as to affect normal use, aesthetics,<br />
produce a measurable ecological impact on the area.<br />
205.4 Fish and Wildlife Resources: The Contractor shall at all times perform all<br />
work and take such steps required to prevent any interferences of disturbance<br />
to fish and wildlife. The Contractor will not be permitted to alter water flows or<br />
otherwise significantly disturb native habitat adjacent to the project area which<br />
are critical to fish and wildlife except as may be indicated or specified.<br />
206. EROSION AND SEDIMENT CONTROL MEASURES<br />
206.1 Burnoff: Burnoff of ground cover will not be permitted.<br />
206.2 Borrow Areas: Borrow areas shall be managed and controlled to prevent<br />
sediment from entering nearby streams or lakes. Restoration of the areas,<br />
including areas outside the borrow area disturbed by the borrow and haul<br />
operations shall include grading, replacement of topsoil, and establishment or<br />
permanent vegetative cover.<br />
206.3 Reduction of Exposure of Unprotected Erodible Soils: Earthwork brought<br />
to final grade shall be finished as soon as practically possible, as indicated and<br />
specified. Side slopes and back slopes shall be protected as soon as<br />
practically possible upon completion of rough grading. All earthworks shall be<br />
planned and conducted in such a manner as to minimize the duration of<br />
exposure of unprotected soils.<br />
206.4 Temporary Protection of Erodible Soils: Such methods as may be<br />
necessary shall be utilized to effectively prevent erosion and control<br />
sedimentation, including but not limited to the following:<br />
206.4.1 Mechanical Retardation and Control of Runoff: The rate of runoff from the<br />
construction site shall be mechanically retarded and controlled. This included<br />
construction of diversion ditches, benches, and berms to retard and divert<br />
runoff to protected drainage courses.<br />
206.4.2 Borrow: Borrow will not be permitted in areas where suitable environmental<br />
controls are not possible.<br />
206.4.3 Vegetation and Mulch: Temporary protection shall be provided all exposed<br />
earth surfaces as soon as rough grading or trench backfill is completed or<br />
sufficient soil is exposed to required protection to prevent erosion. Such<br />
protection shall be by accelerated growth of permanent vegetation, temporary<br />
vegetation, mulching or netting. Slopes too steep for stabilization by other<br />
means shall be stabilized by hydro-seeding, mulching anchored in place,<br />
covering by anchored netting, sodding, or such combination of these and other<br />
methods as may be necessary for effective erosion control.<br />
SERIES 200 Page 4 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
206.5 Sediment Basins: Sediment shall be trapped in temporary or permanent<br />
sediment basins. The basins shall be designed (sized) according to recognized<br />
engineering practice.<br />
206.6 Sediment Retention at Dragline Site<br />
206.6.1 General: The Contractor shall provide sedimentation retention booms,<br />
confining embankments, and/or other devices in order to confine siltation<br />
generated by dragline activities within Water Quality Boundaries. Dragline<br />
operations shall be limited to authorized areas and shall not degrade<br />
waters outside of the Water Quality Boundary below the Standards of<br />
Water Quality for the waters. The Contractor shall limit all effluent from<br />
dragline operations to areas within confining embankments. The<br />
Contractor shall obtain an earthmoving permit for fill placed in tidal waters<br />
at the dredging site prior to start of fill operations.<br />
206.6.2 Sedimentation Retention Booms: Sedimentation retention booms made<br />
of synthetic rubber of pliable plastic shall be deployed around all dragline<br />
areas and all areas of work within waters near shore to limit the effects of<br />
siltation to these immediate areas. The sedimentation retention booms<br />
shall have a continuous float not less than 24 inches in diameter along top<br />
edge. The boom shall be sufficiently weighted along the bottom edge and<br />
shall be anchored to the bottom to prevent floating or kiting. When properly<br />
deployed the sedimentation retention boom shall hang vertically in the<br />
water. The sedimentation retention boom shall have “skirt” lengths<br />
sufficient to meet Environmental Protection regulations and shall be<br />
sufficiently long to confine siltation within the water quality boundary. The<br />
Contractor shall deploy the sedimentation retention booms in a manner that<br />
essentially creates a totally confined area around dredge and/or dredge<br />
disposal areas or other work areas. Prior to construction, the Contractor<br />
shall submit to the Contracting Officer for approval, samples, catalogues, or<br />
shop drawings of the Sedimentation Retention Booms he proposes to use.<br />
Work within near shore areas shall not commence prior to receiving<br />
approval of the proposed booms and methods of use.<br />
206.6.3 Spillages: Care shall be taken to ensure that petroleum products,<br />
bituminous materials “without the approval from the Environmental<br />
Protection Agency” or other deleterious substances including debris are not<br />
allowed to fall, flow, leach or otherwise enter the water.<br />
207. CONTROL AND DISPOSAL OF SOLID WASTE AND CHEMICAL AND<br />
SANITARY WASTES<br />
207.1 General: Waste shall be picked up and placed in containers, which are<br />
emptied on a regular schedule. All handling and disposal shall be so conducted<br />
as to prevent contamination of the site and any other areas. On completion, the<br />
areas shall be left clean and natural looking. All signs of temporary construction<br />
and activities incidental to construction of the required permanent work in place<br />
shall be obliterated.<br />
SERIES 200 Page 5 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
207.2 Disposal of Rubbish and Debris: The Contractor transport all waste off the<br />
project site and dispose of it at the Dalipebinaw sanitary landfill site or other<br />
approved site in manner that complies with <strong>Government</strong> and local<br />
requirements, or as directed by the Contracting Officer. The Contractor shall<br />
provide the Contracting Officer a copy of the <strong>Government</strong> and/or local permit or<br />
license, which reflects such agency’s approval and compliance with their solid<br />
waste disposal regulations. The permit or license and the location of the<br />
disposal area shall be provided prior to transporting any material off the project<br />
site.<br />
207.3 Sewage, Odor and Pest Control: Sewage shall be disposed of through<br />
connection of municipal or district sanitary sewage systems. Where such<br />
systems are not available, chemical toilets or comparably effective units shall<br />
be used with wastes periodically emptied into municipal or district sanitary<br />
sewage system. Provisions shall be included for pest control and for masking<br />
or elimination of odors.<br />
207.4 Chemical Waste: Chemical waste shall be stored in corrosion resistant<br />
containers, removed from the project site and disposed of, a minimum of once a<br />
month unless directed otherwise. Disposal of chemical waste shall be in<br />
accordance with standard established practices. Fueling and lubricating of<br />
equipment and motor vehicles shall be conducted in a manner that affords the<br />
maximum protection against spills and evaporation. Lubricants to be discarded<br />
and burned soil shall be disposed of in accordance with procedures meeting<br />
<strong>Government</strong> and local regulations. For oil and hazardous material spills, which<br />
may be large enough to violate <strong>Government</strong> and local regulations, the<br />
Contracting Officer shall be notified immediately.<br />
207.5 Garbage Disposal: The Contractor shall transport garbage to the dumpsite<br />
subject to approval of the Contracting Officer.<br />
207.6 Sanitary waste shall be disposed of through chemical toilets or comparably<br />
effective units with wastes periodically emptied into the Colonia wastewater<br />
treatment plant. In no case will sanitary waste discharge to the ground be<br />
allowed. Provisions shall be included for masking or elimination of odors.<br />
208. DUST CONTROL:<br />
Dust shall be kept down at all times, including non-working hours, weekends<br />
and holidays. Soil at the site, haul roads and other areas disturbed by the<br />
Contractor’s operations shall be sprinkled or treated with dust suppressors as<br />
necessary to control dust. No dry power brooming will be permitted.<br />
Vacuuming wet mopping; wet sweeping or wet power brooming shall be used<br />
instead. Air blowing will be permitted only cleaning off non-particulate debris,<br />
such as reinforcing bars. No sandblasting will be permitted unless the dust<br />
thereform is confined. Only wet cutting of concrete blocks, concrete and<br />
asphalt will be permitted. No unnecessary shaking of bags will be permitted<br />
where concrete mortar and plaster mixing is done.<br />
209. NOISE:<br />
The maximum use of “low-noise-emission products” as certified by the<br />
Environmental Protection Agency shall be made when available. No blasting or<br />
SERIES 200 Page 6 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
use of explosives will be permitted without written permission of the Contracting<br />
Officer and then only during the designated times. Unless directed otherwise,<br />
the time for such operations shall be confined to the period between 8:00 a.m.<br />
and 6:00 p.m. Monday thru Friday unless otherwise specified in the<br />
Earthmoving Permit.<br />
210. RECORDING AND PRESERVING HISTORICAL AND ARCHEOLOGICAL<br />
FINDS:<br />
All items having any apparent historical or archaeological interest, which are<br />
discovered in the course of any construction activities, shall be carefully<br />
preserved. The Contractor shall leave the archeological find undisturbed and<br />
shall immediately report the find to the Contracting Officer who will notify the<br />
proper authorities. Such items shall not become the property of the Contractor<br />
unless specifically approved by the Contracting Officer.<br />
211. CLEAN AIR AND WATER POLLUTION CONTROL REQUIREMENTS FOR<br />
ALL CONSTRUCTION CONTRACTS AND SUBCONTRACTS EXCEEDING<br />
$100,000:<br />
211.1 Contractors and Subcontractors agree:<br />
211.1.1 That any facility to be used in the performance of the contract or to benefit<br />
from the contract is not listed on the Environmental Protection Agency<br />
(EPA) List of Violating Facilities.<br />
211.1.2 To comply with all the requirements of Section 114 of Clean Air Act and<br />
Section 608 of the Federal Water Pollution Control Act and all regulations<br />
issued thereunder.<br />
211.1.3 That, as a condition for award of a contract they will notify the awarding<br />
official of the receipt of any communication from the EPA indicating that a<br />
facility to be utilized for performance of or benefit from the contract is under<br />
consideration to be listed on the EPA List of Violating Facilities.<br />
211.1.4 To include or cause to be included in any contract or subcontract, which<br />
exceeds $100,000 the aforementioned criteria and requirements.<br />
****** END OF SECTION ******<br />
SERIES 200 Page 7 of 7
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
SERIES 300<br />
ARCHAEOLOGICAL DEPOSITS AND RECOVERY<br />
301. INTENT<br />
301.1 The intent of this Section is to alert the Contractor about the archaeological<br />
deposits that exist, in fact and in theory, on or about the site. In general,<br />
archaeological deposits include:<br />
301.1.1 <strong>Yap</strong>ese stone money.<br />
301.1.2 <strong>Yap</strong>ese stone money platforms.<br />
301.1.3 Japanese graves (circa 1941-1946.)<br />
301.1.4 World War II relics.<br />
301.1.5 <strong>Yap</strong>ese graves and items of cultural interest (these may have been<br />
hidden or buried by the <strong>Yap</strong>ese during the Japanese occupation of the<br />
islands).<br />
301.1.6 American items of cultural interest (these may been appropriated by<br />
Japanese troops during World War II).<br />
301.2 All artifacts, graves or otherwise, potentially have historical interest and value<br />
and shall be preserved in accordance with the requirements of this Section and<br />
as shown on the drawings.<br />
302. GENERAL LOCATION<br />
302.1 Graves may be located within and near the construction areas. In addition,<br />
artifacts of potential historical significance, whether foreign or indigenous to<br />
Micronesia, and <strong>Yap</strong> particularly, may be found in the project area. It is possible<br />
(unlikely) that the Contractor may discover graves during the progress of<br />
construction.<br />
303. PROCEDURES<br />
303.1 All graves and artifacts discovered within the limits of work during the course of<br />
construction shall be marked by stakes establishing the locations in the<br />
discovery areas and shall not be disturbed in any manner.<br />
303.2 The Contracting Officer shall be notified as to the discovery and location as<br />
soon as possible.<br />
303.3 All graves, artifacts, and other items of historical significance and so recognized<br />
by the Contracting Officer and discovered outside or beyond the limits of work,<br />
shall remain undisturbed and protected.<br />
SERIES 300 Page 1 of 2
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
303.4 All graves, stone money, artifacts, and other items of historical significance and<br />
so recognized by the Contracting Officer, and which are immediately adjacent<br />
to the construction area shall remain undisturbed and marked and protected as<br />
specified earlier in Clause 303.1.<br />
303.5 Hazard of Unexploded Ordinance:<br />
Unexploded ordinance may be encountered during the construction of the<br />
project. The Contractor shall employ extreme diligence when performing any<br />
clearing, grubbing, grading, excavation, trenching or dredging. Any explosive<br />
device found should be reported to the Contracting Officer who will effect<br />
removal.<br />
304. RELOCATION OF STONE MONEY<br />
304.1 For stone money to be relocated, the <strong>Yap</strong>ese Owners of the stone money shall<br />
move and place all stone money to its final location. The Contractor shall<br />
provide assistance of equipment use including operator as requested by the<br />
Contracting Officer. Such assistance shall be at no additional cost to the<br />
Owner. The Contractor will not be liable for any damage to artifacts that are<br />
being salvaged by Owners with the Contractor assistance under property<br />
Owner’s direction.<br />
304.2 Prior to movement of any stone money, the Contractor shall notify the<br />
Contracting Officer at least 14 days in advance in writing.<br />
304.3 All other stone money to remain shall be protected in accordance with this<br />
section.<br />
305. RECORD REPORTS<br />
305.1 It is assumed that there may be archaeological deposits buried within the<br />
project area; thus, all precautions shall be taken to minimize subsurface and<br />
surface disturbance. The procedure governing archaeological deposits shall be<br />
in accordance with the requirements of Clause 303.<br />
305.2 All excavation equipment operation shall be given instruction on reporting any<br />
archaeological datum to their supervisors, who in turn shall report to the<br />
Contracting Officer.<br />
305.3 The Contractor in quadruplicate shall prepare a record of all findings, three<br />
copies of it shall be turned over the Contracting Officer, and the Contractor for<br />
his record shall retain the other copy.<br />
****** END OF SECTION ******<br />
SERIES 300 Page 2 of 2
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
SERIES 500<br />
MAINTAINING OF TRAFFIC<br />
501. GENERAL REQUIREMENTS<br />
501.1 Traffic control and safety devices shall be in accordance with Part VI of the<br />
Manual of Uniform Control Devices for Streets and Highways: U.S. Federal<br />
Highway Administration, hereafter referred to as the Traffic Devices Manual.<br />
501.2 Prior to beginning work, the Contractor shall submit to the Contracting Officer<br />
for approval the methods and schedule for traffic control indicating the number<br />
of lanes and detours within and along the public used thoroughfares. The<br />
Contractor shall also include a schedule listing the types and numbers of traffic<br />
control and safety devices proposed for use.<br />
501.3 Each road subject to construction activity shall be open to a minimum of onelane<br />
traffic during working hours except as approved or authorized by the<br />
Contracting Officer. Two-way, two-lane traffic shall be maintained during all<br />
non-working hours except at select construction points where self-regulating<br />
on-lane traffic shall be permitted as approved or directed by the Contracting<br />
Officer.<br />
501.4 Unless otherwise approved or directed by the Contracting Officer, the minimum<br />
widths for one-lane and two-lane traffic shall be 10 feet and 14 feet,<br />
respectively.<br />
502. TRAFFIC CONTROL DEVICES<br />
502.1 Traffic control devices shall conform to the applicable specifications, standards<br />
and principles of the Traffic Devices Manual except as amended herein. The<br />
traffic control devices shall be used at the site for construction, engineering<br />
surveys, and related work that might endanger passing motorists, pedestrians<br />
and workers.<br />
502.2 Traffic control devices shall be in the place prior to the start of any construction,<br />
maintenance, engineering survey, and related work and shall not be removed<br />
until the obstruction or danger of obstruction no longer exists. Where work is<br />
performed in stages, there shall be in place those devices that apply to the<br />
conditions and activities present during the stage in progress.<br />
502.3 Prior to the installation of any traffic control device, the Contractor shall notify the<br />
Contracting Officer who shall in turn notify the Fire Departments, the Police<br />
Department, the Ambulance Service, and Department of Public Works and<br />
Transportation and apprise those agencies of the locations of the traffic devices.<br />
502.4 All signs, markers, barricades, cones, lights, and other devices indicating the<br />
existence of special conditions and activities shall remain in place until their<br />
need is no longer required, unless otherwise directed by the Contracting Officer.<br />
Signs that do not apply to existing conditions and activities shall be removed or<br />
covered. All devices employed shall be neatly constructed and shall be<br />
SERIES 500 Page 1 of 2
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
repaired, cleaned, repainted, and properly maintained in good condition. Special<br />
care shall be taken to see that shrubbery, construction materials, equipment,<br />
spoil and other obstructions do not obscure any sign, light or barricade,<br />
particularly at intersections or curves.<br />
502.5 When it becomes necessary to excavate along or across a highway or any lane<br />
thereof, the work shall be performed to avoid existing local peak traffic hours.<br />
Trenches shall be excavated to maintain at least one lane at all times. A selfregulated<br />
one-lane road will be permitted if approved by the Contracting Officer.<br />
See paragraph “BARRIERS AND CHANNELIZING DEVICES” below.<br />
503. SIGNS<br />
503.1 Regulatory signs, warning signs, and guide signs use at construction, surveying<br />
or other work sites shall be reflectorized and shall conform to the basic<br />
standards prescribed in the Traffic Devices Manual and as specified in the<br />
applicable Sections of the Specifications. Generally, signs shall be placed in the<br />
most effective locations so as to assure the fastest and most adequate driver<br />
response time. All advance-warning signs shall indicate the general character of<br />
the work being done and the distance from the sign to the actual work area.<br />
Where the speed limit is 25 miles per hour or less, an advance warning sign<br />
shall be placed on each approach affected by the work, approximately 150 to<br />
200 feet in advance of the actual work area.<br />
503.2 The Contracting Officer may waive any requirements specified herein if advance<br />
application is made by the Contractor when, in his judgment, the placement of<br />
signs may not be feasible for such placement may interfere with the progress of<br />
the work.<br />
504. BARRIERS AND CHANNEL DEVICES<br />
504.1 Barriers and channelizing devices used at work sites shall follow the basic<br />
standards prescribed in the Traffic Devices Manual and following provisions.<br />
504.2 When it is necessary to confine the traffic to singular lanes, additional transverse<br />
barricades and drums shall be placed at close intervals (approximately 120-foot<br />
spacing on tangents and curves of more than 500-foor radius and approximately<br />
60-foot spacing on curves of 500-foot radius and less) in the closed lane.<br />
****** END OF SECTION ******<br />
SERIES 500 Page 2 of 2
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
SERIES 900<br />
SUBBASE COURSE<br />
Additional Requirements for Subbase Course Section 32 11 35.<br />
901. APPLICABLE PUBLICATIONS<br />
The following publications of the issues listed, but referred to thereafter by basic<br />
designation only, form a part of this specification to the extent indicated by the reference<br />
thereto:<br />
901.1 American Society for Testing and Materials (ASTM) Publications:<br />
D423-66 Liquid Limit of Soils (1972)<br />
D424-59 Plastic Limit and Plasticity<br />
(1971) Index of Soils<br />
D1556-82 Density of Soil In-Place by the Sand-Cone (1974) Method<br />
D1557-78 Moisture-Density Relations of Soils Using 10-lb. (4.5 Kg.)<br />
Hammer and 18-inch (457mm) Drop<br />
D1883-73 Bearing Ratio of Laboratory-Compacted Soils<br />
D2922-81 Density of Soil and Soil-Aggregate in Place by Nuclear<br />
Methods (Shallow Depth)<br />
902. QUALITY CONTROL: Approvals, except those required for field installations,<br />
field applications, and field tests, shall be obtained before delivery of material or<br />
equipment to the project site.<br />
903. SUBMITTALS: Certified Laboratory Test Reports: Before delivery of materials,<br />
certified copies of the reports of all tests required in referenced publications<br />
shall be submitted to the Contracting Officer. The testing shall have been<br />
performed in an independent laboratory approved by the Contracting Officer.<br />
Certified test reports are required for the coral material.<br />
904. DELIVERY AND STORAGE: Materials delivered to the site shall be unloaded<br />
and stored with a minimum of handling. Aggregates shall be stored in such a<br />
manner as to prevent segregation.<br />
905. MATERIALS: In addition to the Technical Specifications Section 32 11 35,<br />
The subbase material can be dredged ledge coral and containing sand, soil or<br />
other similar binding or filler material. The Contractor shall not use materials<br />
from existing roadbed excavations as subbase material.<br />
The dredged coral shall have the following properties: -<br />
Gradation: Sieve Size % Passing by Weight<br />
4 inch 100<br />
2-1/2 inch 90 -100<br />
SERIES 900 Page 1 of 4
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
No 4 40 -90<br />
No 200 3 – 25<br />
CBR – 40% min. Liquid Limit – 40% max. Plasticity Index – 15 max<br />
906. CONSTRUCTION EQUIPMENT: The Contractor shall submit a list of<br />
construction equipment to the Contracting Officer for approval.<br />
907. GENERAL REQUIREMENTS: The subbase shall be composed of granular<br />
materials constructed on a prepared subgrade. The subbase course shall be<br />
provided where indicated and shall be shaped and compacted thoroughly within<br />
the tolerances specified. Subbase courses shall not be constructed when<br />
weather conditions detrimentally affect the quality of the finished course. Areas<br />
of the subbase course that are damaged by the affects of weather conditions<br />
during any phase of the construction, shall be aerated, if required, reshaped,<br />
and re-compacted at no additional cost to the Owner. Line and grade stakes<br />
shall be provided as necessary for control. Grade stakes shall be placed in<br />
lanes parallel to the centerline of the areas to be paved, and suitably spaced for<br />
string lining.<br />
908. CONSTRUCTION<br />
908.1 Placing: The subgrade shall be cleaned of all foreign substances for proper<br />
compaction and smoothness before placement of subbase course. Material<br />
shall be placed and compacted in maximum 6” compacted lifts.<br />
908.1.1 Spreading of fine material over the surface of the compacted material is<br />
prohibited. Additional material if required shall be incorporated uniformly<br />
without segregation, throughout the thickness of the compacted material by<br />
scarifying and blading. The combined material shall meet all quality<br />
requirements specified herein.<br />
908.2 Compacting and Finishing: Layers of subbase course materials shall be<br />
compacted by rolling with tamping rollers three-wheel general purpose rollers,<br />
pneumatic-tired rollers, vibratory rollers, grid rollers or tractors, or by<br />
combinations thereof or by other approved equipment. Compaction shall be<br />
continued until the layer or layers are compacted through the full depth to at<br />
least 100 percent of the maximum density as determined by ASTM D1557.<br />
During rolling operations the material shall be maintained within 2 percent of the<br />
specified optimum moisture content to aid compaction to the density required.<br />
The surface of the layer shall be finished by blading or rolling with three-wheel<br />
general purpose rollers or light pneumatic-tired roller, or combinations thereof.<br />
In all places not accessible to the rolling equipment, the subbase material shall<br />
be compacted by mechanical tamping. Blading, rolling, and tamping shall<br />
continue until the surface is smooth and free from waves and irregularities. If at<br />
any time the subbase material is excessively moistened by rain during<br />
construction, it shall be aerated by means of blades, graders harrows, or other<br />
suitable equipment, until the moisture is controlled, and the required density is<br />
obtained. The subbase shall be maintained until the construction of the next<br />
course.<br />
SERIES 900 Page 2 of 4
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
909. MAINTENANCE: After construction is completed, the subbase shall be<br />
maintained throughout except where portions of the succeeding course are<br />
under construction thereon. Maintenance shall include drainage, rolling,<br />
shaping, and watering as necessary to maintain the course in proper condition.<br />
Deficiencies in thickness, composition, construction, smoothness, or density,<br />
which develop during the maintenance, shall be corrected by the Contractor to<br />
conform to the requirements specified hereinbefore. Sufficient moisture shall<br />
be maintained at the surface to prevent a dusty condition, by sprinkling with<br />
water.<br />
910. TESTING<br />
910.1 The Contractor at no additional cost to the Owner shall perform testing.<br />
910.1.1 Aggregate Testing: all aggregate tests shall be made on the initial source<br />
samples, and shall be repeated when there is a change of source. The<br />
tests shall include an analysis of the combined material representing the<br />
aggregate part of the mix. The Contracting Officer may request or make<br />
additional tests at random at expense of the Contractor. Four samples<br />
each shall be taken for gradation, liquid limit, plasticity index and CBR tests<br />
from each source approved.<br />
910.1.2 GRADATION: Gradation Test shall be performed at least once a day.<br />
910.1.3 CBR Tests: CBR tests shall be performed for each source in conformance<br />
with ASTM D1883.<br />
910.1.4 Liquid Limit and Plasticity Index: Liquid Limit and Plastic Limit shall be<br />
performed for each source in conformance with ASTM D423, and D424,<br />
respectively.<br />
910.1.5 Soundness Test: The material shall be hard, durable particles or<br />
fragments of coral or schist and shall be free of vegetable matter, lumps or<br />
balls of clay.<br />
910.1.6 Smoothness Test: Surface deviations in excess of 3/8 inch, when tested<br />
with a 10-foot straightedge applied parallel with and at right angles to the<br />
center line of the area to be paved, shall be corrected by loosening, adding<br />
and/or removing material, reshaping and re-compacting.<br />
910.1.7 Field Determination of Density: Field determination of density shall be in<br />
accordance with ASTM D1556 or ASTM D2922. One test shall be<br />
conducted for each 250 linear feet or at least once a day.<br />
910.1.8 Laboratory Density Tests: Laboratory density tests shall be performed in<br />
accordance with Method D, ASTM D1557, with the following modification:<br />
(1) all materials passing 2-inch sieve and retained on a ¾ inch sieve shall<br />
be removed and replaced with an equal portion of material between the No.<br />
4 and ¾ inch sieves, and (2) a separate batch of material shall be used for<br />
each compaction test specimen. No material shall be reused for<br />
SERIES 900 Page 3 of 4
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
compaction tests. One test shall be conducted for each 2,500 cubic yards<br />
of material.<br />
910.1.9 Thickness: The thickness of the completed subbase course shall be<br />
measured at intervals in such a manner that there will be a depth<br />
measurement for at least each 500 square yards of completed subbase<br />
course. The depth measurements shall be made by test holes, at least 3<br />
inches in diameter, through the subbase course. Deficiencies in thickness<br />
greater than ½ inch in diameter shall be corrected by scarifying such areas,<br />
adding mixture of proper gradation, re-blading, and re-compacting.<br />
****** END OF SECTION ******<br />
SERIES 900 Page 4 of 4
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
SERIES 1000<br />
PORTLAND CEMENT STABILIZED BASE COURSE<br />
Additional Requirements for Cement Treated Base Course Section 32 11 34.<br />
1001 APPLICABLE PUBLICATIONS: The following publications of the issues listed<br />
below, but referred to thereafter by basic designation only, form a part of this<br />
specification to the extent indicated by the references thereto.<br />
1001.1 Federal Specification:<br />
1001.2 SS-C-1960-3A Cement, Portland<br />
1001.3 American Society for Testing and Materials (ASTM) Publications:<br />
C117-87 Materials Finer then No. 200 (75-m) Sieve in Mineral<br />
Aggregates by Washing<br />
C-136-82<br />
Sieve or screen Analysis of Fine and Coarse<br />
Aggregates<br />
D75-82 Sampling Aggregates<br />
D420-69 Investigating and Sampling Soils and Rocks for<br />
(1969) Engineering Purposes<br />
D423-66 Liquid Limit of Soils<br />
(1972)<br />
D424-59 Plastic Limit and Plasticity Index Soils<br />
(1971)<br />
D558-82 Moisture-Density Relations of Soil-Cement<br />
(1970) Mixtures<br />
D1556-82 Density of Soil in Place by the Sand-Cone Method<br />
(1974)<br />
1002 GENERAL REQUIREMENTS:<br />
The base course shall be composed of graded coral aggregate or graded<br />
aggregate manufactured from quarry-run rock of an approved source, and<br />
cement uniformly blended together, mixed with water, spread, shaped and<br />
compacted in accordance with these specifications and in conformity to the<br />
lines, grades, dimensions, and typical sections shown. Base shall not be<br />
constructed when whether conditions detrimentally affect the quality of the<br />
finished course. Areas of the base that are damaged by the effects of weather<br />
conditions during any phase of the construction shall be aerated, if required,<br />
reshaped, and re-compacted at no additional cost to the Owner. Adequate<br />
drainage shall be provided during the entire construction period to prevent<br />
water from collecting or standing on the area to be stabilized or on the<br />
pulverized, mixed, or partially mixed material. Line and grade stakes shall be<br />
SERIES 1000 Page 1 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
provided as necessary for control. Grade stakes shall be placed in lanes<br />
parallel to the centerline of the areas under construction, and suitably spaced<br />
for string lining.<br />
1002.1 Definition of ‘Soil Cement’ in this series shall mean a mixture of graded<br />
corals, cement and water.<br />
1003 MATERIALS<br />
1003.1 Cement: ASTM C150, Type II.<br />
1003.2 Dredged Coral: Dredged ledge coral shall be obtained from designated<br />
dredge sites and may contain sand or other similar binding material. But<br />
should not contain any material deleterious to construction or finishing of<br />
the Base Course. The dredged coral shall have the following properties: -<br />
GRADATION: Sieve Size Percent Passing by Weight<br />
1-inch 100<br />
No. 4 35-75<br />
No. 40 15-35<br />
No. 200 2-15<br />
A minimum CBR of 100% at 7-days after cement stabilization. The portion<br />
of the dredged coral, including any blended materials, passing the No. 40<br />
mesh sieve shall have a liquid limit of not more than 25 and a plasticity<br />
index of not more than 6 when tested in accordance with ASTM D423 and<br />
D424.<br />
1003.3 Water: Water shall be clean, fresh, and free from injurious amounts of oil,<br />
acid, salt, alkali, organic matter, and other substances deleterious to the<br />
hardening of soil-cement, and shall be subject to approval<br />
1004. CONSTRUCTION EQUIPMENT<br />
1004.1 The Contractor shall submit a list of all construction equipment to the<br />
Contracting Officer for review 30 days prior to shipping the equipment to <strong>Yap</strong>.<br />
All equipment shall be dependable and adequate for the purpose intended and<br />
shall be properly maintained in satisfactory and safe operating condition at all<br />
times. Calibrated equipment such as scales, batching equipment, spreaders<br />
and similar equipment, shall have been recalibrated by a calibration laboratory<br />
recommended by the Contractor and approved by the Contracting Officer<br />
before shipping to <strong>Yap</strong>. Additional recalibration shall be done by the<br />
Contractor. The list of equipment shall include the make, model, serial number<br />
and the date on which the calibrated equipment was last recalibrated.<br />
1004.2 Rollers:<br />
1004.2.1 Steel-wheel roller shall be the self-propelled, three-wheel or tandem<br />
type, weighing not less than 10-tons, and shall be suitable for rolling<br />
soil-cement mixtures. The wheels shall be equipped with adjustable<br />
scrapers.<br />
SERIES 1000 Page 2 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
1004.2.2 Rubber-tired rollers shall be self-propelled and equipped with not less<br />
than nine rubber-tired wheels mounted on two axles in such manner<br />
than the rear group of tires will not follow in the tracks of the forward<br />
group. The rubber-tired roller shall also be equipped with suitable<br />
boxes or platforms for ballast loading and shall be loaded as directed.<br />
The tires shall be uniformly inflated.<br />
1004.2.3 Pneumatic-Tired Rollers: Pneumatic-tired rollers shall be single or<br />
double axle, vibrating or non-vibrating type equipment with tires of<br />
equal size and diameter, uniformly inflated so that the air pressure of<br />
the several tires shall not vary more than 5-pounds per square inch<br />
(psi). Rollers may be self-propelled or towed by a suitable power unit.<br />
The self propelled roller or the power unit and towed roller shall be<br />
considered a pneumatic-tired roller unit.<br />
1004.2.4 Light-Pneumatic-tired rollers shall have low axles on which are<br />
mounted not less than nine pneumatic-tired wheels in such a manner<br />
that the rear group of tires will not follow in the tracks of the forward<br />
group. The axles shall be mounted in a rigid frame provided with a<br />
loading platform or body suitable for ballast loading. The roller shall<br />
develop a load of not less than 22 pounds per inch width or tire tread<br />
and shall be capable of being loaded to provide loads up to 30 pounds<br />
per inch or normal tire width.<br />
1004.2.5 Heavy Pneumatic-Tired Rollers: Heavy pneumatic-tired rollers shall be<br />
of the vibratory or non-vibratory type with a minimum loading of 25,000<br />
pounds per tire. The loading shall be distributed equally to all wheels.<br />
1004.2.6 Vibrating Rollers: Vibrating rollers shall be the self-propelled type of a<br />
minimum static weight of 10-tons.<br />
1004.3 Blade Graders: Blade graders shall have a wheelbase of not less than 15-<br />
feet, a blade of not less than 12-feet, and shall be self-propelled.<br />
1004.4 Scarifier: Scarifiers shall have two rows of teeth with the teeth in each row not<br />
more than 8-inches apart. The rows shall be staggered so that the paths of the<br />
teeth will not be more than 4-inches apart.<br />
1004.5 Hauling Equipment: Hauling equipment shall consist of pneumatic tired<br />
vehicles having dump bodies suitable for dumping materials in windrows (for<br />
traveling plant method) or into spreading machines. Dump trucks shall be<br />
equipped with tailgates, which can be chained to proper opening to prevent<br />
segregation during dumping.<br />
1004.6 Power Brooms and Power Blowers: Power brooms and power blowers shall<br />
be suitable types for effectively cleaning prepared sub-grades, sub-bases, and<br />
base courses.<br />
1004.7 Sprinkling Equipment: Sprinkling equipment shall consist of tank trucks,<br />
pressure distributors, or other equipment designated to apply water uniformly<br />
and at controlled quantities to variable widths of surface.<br />
SERIES 1000 Page 3 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
1004.8 Mixing Plants: Mixing plants shall be so designed and constructed as to<br />
thoroughly mix the aggregates, cement, and water. The plants shall be<br />
equipped to accurately measure the required amounts of cement and water<br />
while the plants are in operation.<br />
1004.9 Mechanical Spreader: Mechanical Spreader shall be self-propelled or<br />
attached to a propelling unit capable of moving the spreader and material truck.<br />
The device shall be steer-able and shall have variable speed forward and<br />
reverse. The spreader and propelling unit shall be carried on tracks, rubber<br />
tires, or drum-type wheel rollers that will not disturb the sub-grade, sub-base, or<br />
underlying base-course layer. The spreader shall contain a hopper, an<br />
adjustable screed, and outboard bumper rolls and shall be so designed that<br />
there will be a uniform, steady flow of material from the hopper. The spreader<br />
shall be capable of laying material across the full width of the lane to a uniform<br />
thickness and to uniform loose density so that when compacted the layer or<br />
layers will conform to the thickness and grade requirements indicated.<br />
1004.10 Tampers: Tampers shall be an approved mechanical type, operated either by<br />
pneumatic pressure or by internal combustion. Tampers shall have sufficient<br />
weight and striking power to produce the compaction required.<br />
1004.11 Miscellaneous Equipment: Miscellaneous equipment such as tractors,<br />
windrow equalizers, plows, adjustable spike-tooth harrows, and discs shall be<br />
suitable for construction of soil cement stabilized courses.<br />
1005. CONSTRUCTION<br />
1005.1 General: When application of water and mixing are completed, the moisture<br />
content in the mixture, on the basis of dry weight, shall be within 10% of the<br />
specified optimum moisture content of the mixture. When the stabilized course<br />
is constructed in more than one layer, the previously constructed layers shall be<br />
cleaned of loose and foreign matter by sweeping with power sweepers or power<br />
brooms, except that hand brooms may be used where permitted by the<br />
Contracting Officer.<br />
1005.2 Stockpiling of Material: Material shall be stockpiled in the manner and at the<br />
locations approved by the Contracting Officer. Prior to stockpiling of material,<br />
the storage sites shall be cleared, drained, and leveled.<br />
1005.3 Preparation of Sub-base: Soft-yielding spots and ruts or other irregularities in<br />
the surface shall be corrected. The material in the affected areas shall be<br />
loosened and unsatisfactory material removed. Approved select material shall<br />
be added where required. The area shall then be shaped to line, grade, and<br />
cross section, and shall be compacted to the specified density requirements as<br />
directed.<br />
1005.4 Fixed Grades: The finished and completed stabilized area shall conform to the<br />
lines, grades, cross section, and dimensions indicated. The lines and grades<br />
indicated shall be maintained by means of line and grade stakes placed at the<br />
site of the work.<br />
SERIES 1000 Page 4 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
1005.5 Mixing and Placing Materials:<br />
1005.5.1 Central-Plant Method: A pugmill may be used to mix aggregate,<br />
cement, and water on jobs where select material is required for the<br />
cement treated course. Aggregate and cement shall be dry-mixed<br />
sufficiently to prevent cement balls from forming when water is added.<br />
The plant shall be capable of producing a uniform cement-treated<br />
mixture at the specified cement and moisture contents. The mixture<br />
shall be hauled to the job in trucks equipped with protective covers.<br />
The sub-base shall be thoroughly moistened and the mixture then<br />
placed on the sub-base in a uniform lay with mechanical spreaders.<br />
Not more than 60-minutes shall elapse between the start of the moist<br />
mixing and the start of compaction of the treated layer. The layer shall<br />
be uniform in thickness and surface contour and in such quantity that<br />
the completed layer, after compaction, shall conform to the required<br />
grade and cross section. Dumping the mixture in piles or windrows<br />
shall not be permitted. The mixture shall contain not less than five (5)<br />
percent cement calculated by dry weight of aggregate.<br />
1005.5.2 Traveling-Plant Method: Traveling plant, when used for mixing the<br />
materials, shall move at a uniform rate of speed and accomplish<br />
thorough mixing of the materials. Water and cement shall be delivered<br />
from supply trucks or bins at a predetermined rate. Windrows of<br />
prepared soil-cement mixture shall be of sufficient size to cover a<br />
predetermined width or roadway to the indicated compacted thickness.<br />
When this method is used, cement content shall be not less than 5-1/2<br />
percent. The mixing and placing of materials shall be as mentioned in<br />
the above Central-Plant method.<br />
1005.6 Construction Control:<br />
1005.6.1 Lay Thickness: The compacted thickness of the stabilized course<br />
shall be as called for in the drawings.<br />
1005.6.2 Compaction: Before the compaction operations begin and as a<br />
continuation of the mixing operation, the mixture shall be thoroughly<br />
loosened to the full depth. The compaction shall be started<br />
immediately after mixing is completed. The loose mixture shall be<br />
uniformly and continuously compacted until the entire depth and width<br />
of the area is compacted to at least 100 percent for maximum density.<br />
The moisture content at the surface shall be maintained near optimum<br />
at all times through the rolling but shall be less than that which shall<br />
cause the mixture to become unstable during compaction. Rolling shall<br />
begin at the outside edge of the surface and proceed to the center,<br />
overlapping on successive trips at least one-half the width of the roller.<br />
Alternate trips of the roller shall be slightly different lengths. The speed<br />
of the roller at all times shall be such that displacement of the mixture<br />
does not occur. Areas that are inaccessible to rollers shall be<br />
compacted with mechanical tampers.<br />
SERIES 1000 Page 5 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
1005.6.3 Finishing: After compaction, the surface shall be moistened, if<br />
necessary, and shaped to the required lines, grades, and cross section.<br />
If necessary, the surface shall be lightly scarified to eliminate any<br />
imprints made by the compacting or shaping equipment. The surface<br />
shall then be thoroughly compacted to specified density with rubbertired<br />
rollers and smooth wheel tandem rollers to the extent necessary to<br />
provide a smooth, dense, uniform surface that is free of surface<br />
checking, ridges or loose material, and that conforms to the crown,<br />
grade and line indicated. The surface shall then be broomed to remove<br />
any surface fines without dislodging any embedded coarser aggregates<br />
prior to application of the prime coat, which is to be applied immediately<br />
after completion of the cement treated base course. The Contractor is<br />
required to perform field trials on this operation to ascertain no<br />
dislodging of the embedded aggregates and loosening of the cement<br />
treated base course. These finishing operations shall be completed<br />
within 2-hours after completion of missing operations. In places not<br />
accessible to finishing and shaping equipment, the mixture shall be<br />
compacted with mechanical tampers to the density specified and shall<br />
be shaped and finished by hand methods. Any portion of the<br />
compacted mix that has density less than that specified shall be rerolled<br />
until the required density is obtained or shall be removed to the<br />
full depth and replaced with new base course material and again<br />
compacted. Areas removed shall have a true vertical face free of loose<br />
or shattered material.<br />
1005.6.4 Construction Joints: At the end of each day’s construction and when<br />
cement treated base operations are delayed or stopped for more than<br />
2-hours, a straight transverse construction joint shall be formed by<br />
cutting back into the completed work to form a true vertical face free of<br />
loose or shattered material. Material along construction joints not<br />
properly compacted shall be removed and replaced with soil-cement<br />
that is mixed, moistened, and compacted in accordance with this<br />
specification. Where cement treated base has been finally compacted<br />
more than one hour, longitudinal joints shall be by cutting vertically into<br />
the existing edge or approximately 3-inches and disposed properly.<br />
The face of the cut joints shall be moistened in advance of placing the<br />
adjacent base.<br />
1005.6.5 Edge of Stabilized Course: Approved material shall be placed along<br />
the edges of the stabilized course in such quantity for compaction to<br />
the thickness of the course being constructed, allowing at least a onefoot<br />
width of the shoulder to be rolled and compacted simultaneously<br />
with the rolling and compacting of the stabilized course as directed.<br />
1006.6.6 Thickness Control: The completed thickness of the stabilized course<br />
shall be within ¼ inch of the thickness indicated. The thickness of the<br />
stabilized course shall be measured at intervals in such manner that<br />
there shall be one depth measurement at least for each 500 square<br />
yards of stabilized course. The depth measurement shall be made by<br />
test holes at least stabilized course. The depth measurement shall be<br />
made by test holes at least 3-inches in diameter through the stabilized<br />
SERIES 1000 Page 6 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
course. Where the measured thickness of the stabilized course is<br />
more than ¼ inch deficient in thickness, the Contractor shall correct<br />
such areas by removal and replacement with cement-treated base<br />
course for full depth. Where the measured thickness of the stabilized<br />
course is more than ¼ inch thicker than that indicated of the stabilized<br />
course is more than ¼ inch thicker than that indicted and satisfies the<br />
required lines, grades and cross section, it shall be considered as<br />
conforming with the specified thickness requirements plus ¼ inch. The<br />
average job thickness shall be the average of the job measurements<br />
determined as specified above but shall be within ¼ inch of the<br />
thickness indicated. Material removed by making test holes will be<br />
replaced with new soil-cement mixture at no additional cost to the<br />
Owner.<br />
1005.7 Curing: Immediately after the finishing operations are completed bituminous<br />
prime coat shall be applied at a rate of 0.22 gallons per sq. yd. Or as directed<br />
by the C.O., in accordance with SERIES 1100: BITUMINOUS PRIME COAT.<br />
In the event there is a delay in applying the prime coat, the surface shall be<br />
kept wet with water. This curing membrane may serve the function of a primer<br />
if remain satisfactory prior to paving. Immediately prior to paving, if any surface<br />
appear unsatisfactory, the surface may have to be re-primed in accordance with<br />
SERIES 1100: BITUMINOUS PRIME COAT as determined by the Contracting<br />
Officer.<br />
1005.8 Traffic: Completed portions of the cement-treated soil area may be opened to<br />
light, local traffic after 4-days curing provided the curing is not impaired and to<br />
all other traffic after the curing period of 7-days, provided that the cementstabilized<br />
course has hardened sufficiently to prevent marring or distorting of<br />
the surface by equipment or traffic. If in the opinion of the C.O. a longer curing<br />
period is required for the cement treated base, he may direct the Contractor to<br />
do so at no extra cost to the Owner. Heavy equipment shall not be permitted<br />
on the area during the protection and curing period. However, the necessary<br />
cement and water may be hauled over the area with pneumatic-tired equipment<br />
with the approval of the Contracting Officer. Finished portions of cementstabilized<br />
soil that are traveled on by equipment used in constructing an<br />
adjoining section shall be protected in a manner so as to prevent equipment<br />
from marring or damaging the completed work.<br />
1005.9 Maintenance: The stabilized area shall be maintained in a satisfactory<br />
condition until the completed work is accepted. Maintenance shall include<br />
immediate repairs of any defects that may occur either before or after the<br />
cement is applied and shall be repeated as often as may as necessary to keep<br />
the area continuously intact. Defects in freshly mixed base course shall be<br />
remedied by re-rolling until required densities are obtained and imperfections<br />
corrected and leveled. Base course defects where materials have replaced<br />
with new base course material and again compacted.<br />
1006. SAMPLING, TESTING AND APPROVALS<br />
1006.1 Samples: Samples shall be of the size required for testing as specified and<br />
shall be furnished at no additional cost to the Owner. Samples of the<br />
SERIES 1000 Page 7 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />
material shall be submitted for approval prior to starting the work and<br />
thereafter at regular intervals during construction. Material samples shall<br />
be obtained at the source, from stockpiles, or from other locations<br />
designated by the Contracting Officer in conformance with ASTM D420.<br />
The source of the material shall be selected in advance of the time the<br />
materials shall be required in the work. Samples for gradation tests shall<br />
be taken in conformance with ASTM D75. Samples for density test shall<br />
be taken during construction. Samples for determining the optimum<br />
moisture content and the specified degree of compaction shall be<br />
representative of soil-cement mixtures obtained from the area being<br />
processed. Samples for determining the density of the compacted soilcement<br />
mixture shall be taken in conformance with ASTM D1556.<br />
Samples of bituminous material shall be taken in conformance with ASTM<br />
D140. Sampling shall be supervised by the Contracting Officer at his<br />
option.<br />
1006.2 Approval of Materials: Approval of materials shall be based on tests of<br />
samples for specific job but test certificates should accompany samples<br />
submitted by the Contractor.<br />
1006.3 Cement and bituminous materials shall be tested as prescribed in the<br />
referenced specification under which furnished. Cement may be accepted<br />
on the basis of mill tests and the manufacturer’s certification of compliance<br />
with the specification, provided the cement is the product of a mill with a<br />
record for the production of high-quality cement for the past 3-years.<br />
1006.4 CBR: Sampling and testing for CBR shall be taken for each 2,000 cubic<br />
yards of material.<br />
1006.5 Smoothness Test: The surface course shall not show any deviations in<br />
excess of 3/8 inch when tested with a 10-foot straightedge applied parallel<br />
with the centerline of the stabilized area. Any deviation in excess of this<br />
amount shall be corrected as hereinbefore specified in subparagraph<br />
1005.6.5.<br />
1006.6 Test shall be performed by the Contractor at no additional cost to the<br />
Owner. One test of each type listed below shall be conducted for each 250<br />
linear feet along the road or one day’s production whichever is less.<br />
1006.6.1 Sieve analysis shall be made in accordance with ASTM C136.<br />
1006.6.2 Density Tests: The density of the compacted soil-cement mixture<br />
shall be at least 100 percent of the maximum density determined in<br />
the laboratory. The density shall be determined in the field in<br />
accordance with ASTM D1556. The maximum density at optimum<br />
moisture content will be determined in the laboratory in accordance<br />
with ASTM D558.<br />
****** END OF SECTION ******<br />
SERIES 1000 Page 8 of 8
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
SERIES 1100<br />
BITUMINOUS PRIME COAT<br />
Additional Requirement for Bituminous Prime Coat Section 32 12 10.<br />
1101. APPLICABLE PUBLICATIONS: The following publications of the issues listed<br />
below, but referred to thereafter by basic designation only, form a part o this<br />
specification to the extent indicated by references thereto.<br />
1101.1 American Association of <strong>State</strong> Highway Transportation Officials (AASHTO)<br />
Publication:<br />
1101.2 American Society for Testing and Materials (ASTM), Publications:<br />
1102. QUALITY CONTROL: Approvals, except those required for field installations,<br />
field applications and field tests, shall be obtained before delivery of materials or<br />
equipment to the project site.<br />
1103. CERTIFIED TEST REPORTS: Before delivery of materials and equipment, four<br />
certified copies of the reports of all tests required in referenced publications or<br />
specified herein shall be submitted and approved. The testing shall have been<br />
performed by approved independent laboratory. Test reports shall be<br />
accompanied by notarized certificates from the manufacturer certifying that the<br />
tested material and equipment is of the same type, quality, manufacture, and<br />
make as that proposed to be supplied. Certified test reports are required for the<br />
following:<br />
1103.1 Spot test of Asphaltic Materials.<br />
1103.1.1 Emulsion Asphalt.<br />
1104. DELIVERY AND STORAGE: Materials delivered to the site shall be inspected<br />
for damage, unloaded, and stored with a minimum of handling.<br />
1105. GENERAL: The bituminous prime coat shall be applied on a previously<br />
prepared base course immediately after the completion of the cement treating<br />
base course. The bituminous prime coat may be applied to function as a curing<br />
membrane as well as a primer.<br />
1106. MATERIALS: Bituminous material for the prime coat shall be emulsified asphalt<br />
Type SS-1 where applied to cement treated base.<br />
1106.1 Emulsified Asphalt: Emulsified asphalt shall conform to ASTM D977 Type<br />
SS-1. The base asphalt used to manufacture the emulsion shall show a<br />
negative spot when tested in accordance with AASHTO T102 using<br />
standard naptha.<br />
SERIES 1100 Page 1 of 3
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
1107. APPLICATION: Application rate shall be 0.22 US gallons per square yard OR<br />
AS DIRECTED BY THE Contracting Officer. Apply prime coat to all prepared<br />
surfaces of base course prior to placement of pavement.<br />
1108. CONSTRUCTION EQUIPMENT: All equipment shall be dependable and<br />
adequate for the purpose intended and shall be properly maintained in<br />
satisfactory and safe operating condition at all times.<br />
1108.1 Bituminous Distributor: Bituminous Distributor shall have pneumatic tires<br />
of such width and number that the load produced on the base surface shall<br />
not exceed 650 pounds per inch of tire width. The distributor shall be<br />
designed and equipped to distribute the bituminous material uniformly at<br />
even heat on variable widths of surface at readily determined and controlled<br />
rates from 0.05 to 2.0 gallons per square yard, with a pressure range of 25<br />
to 75 pounds per square inch and with an allowable variation not to exceed<br />
5 percent from any specified rate. Distributor equipment shall include<br />
separate power unit for the bitumen pump, full-circulation spray bars,<br />
tachometer, pressure gauges, volume-measuring devices, adequate<br />
heaters for heating the materials to the proper application temperature, a<br />
thermometer to show the temperature of tank contents, and a hose<br />
attachment suitable for applying bituminous materials to spots unavoidable<br />
missed by the distributor. The distributor shall be equipped to circulate and<br />
agitate the bituminous material during the heating process.<br />
1108.2 Brooms and Blowers: Brooms and blowers shall be of the power type and<br />
shall be suitable for cleaning prepared sub-grades or bases.<br />
1109. WEATHER LIMITATIONS: Do not apply the prime coat during drain or when<br />
rain is imminent.<br />
1110. PREPARATION OF SURFACE: Immediately before applying the prime coat to<br />
the surface that is to be primed, all loose materials, dirt, clay, or other<br />
objectionable substances shall be removed from the surface by means of a<br />
power broom or blower supplemented with hand brooms. After the cleaning<br />
operation and prior to the application of the prime coat, an inspection of the area<br />
to be primed will be made by the Contracting Officer to determine the fitness of<br />
the area to receive the bituminous priming material. To assure a uniform spread<br />
of the bituminous material, the portion of the base course prepared for<br />
treatment, if excessively dry, shall be lightly sprinkled with water immediately<br />
before the application.<br />
1111. APPLICATION OF BITUMINOUS MATERIAL<br />
1111.1 Immediately following the preparation of the base course, the bituminous<br />
material shall be applied by means of a bituminous distributor. The<br />
bituminous material shall be applied at a pressure within the range of 25 to<br />
75 pounds per square inch and in the amounts directed. The priming<br />
material shall be applied with uniform distribution at all points of the surface<br />
to be treated. Unless the distributor is equipped to obtain satisfactory<br />
results at the junction of previous and subsequent applications, building<br />
paper shall be spread on the surface of the applied material for a sufficient<br />
SERIES 1100 Page 2 of 3
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
distance back from the ends of each application so that flow from the sprays<br />
may be started and stopped on the paper, and so that all sprayers will<br />
operate at full force on the surface to be treated. Immediately after the<br />
application, the building paper shall be removed and destroyed. All spots<br />
unavoidably missed by the distributor shall be properly treated with<br />
bituminous material.<br />
1111.2 Following the application of prime material, the surface shall be allowed to<br />
dry without being disturbed for as long a period as may be necessary to<br />
attain penetration into the foundation course and evaporation of the volatiles<br />
from prime material, which period shall be a minimum of four (4) days or as<br />
determined by the Contracting Officer. The Contractor shall maintain the<br />
primed surface until pavement is placed by protecting the surface against<br />
damage and by repairing and re-priming deficient areas at no additional cost<br />
to the Owner. No smoking, fires, or flames other than the heaters that are<br />
part of the equipment shall be permitted in the vicinity of heating,<br />
distribution, or transferring operations for bituminous materials. The surface<br />
may have to be re-primed prior for paving if it appears unsatisfactory to the<br />
C.O.<br />
1111.3 Application Temperature of Emulsified Asphalt: Application temperature of<br />
emulsified asphalt shall be as directed by the C.O. and shall provide an<br />
application viscosity between 20 and 100 seconds, Saybolt-Furol.<br />
Application temperature shall be within the range of 85 to 190 degree<br />
Fahrenheit.<br />
1112. FIELD SAMPLING AND TESTING<br />
1112.1 Samples of Bituminous Materials: Samples of bituminous materials shall<br />
be furnished by and at the expense of the Contractor. Sampling shall be in<br />
accordance with ASTM D140.<br />
1112.2 Tests: An independent testing laboratory at the expense of the Contractor<br />
shall conduct all tests of bituminous materials.<br />
1112.2.1 Spot test for bitumen shall be conducted in accordance with<br />
AASHO T102, and shall be performed on each shipment.<br />
1112.2.2 Calibration Tests: The Contractor shall furnish such equipment<br />
and materials and perform the work to calibrate the tank and<br />
measuring devices of the distributor. This shall be done on the site<br />
at the beginning of the work.<br />
****** END OF SECTION ******<br />
SERIES 1100 Page 3 of 3
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
SERIES 1800A<br />
BITUMINOUS TACK COAT<br />
Additional Requirements for Bituminous Tack Coat Section 32 12 11.<br />
PART 1 – GENERAL<br />
1.1 APPLICABLE PUBLICATIONS: The publications listed below form a part of<br />
this specification to the extent referenced. The publications are referred to in<br />
the text the basic designation only.<br />
1.1.1 American Association of <strong>State</strong> Highways and Transportation Officials<br />
(AASHTO) Publications:<br />
1.1.2 American Society for Testing and Materials (ASTM) Specifications:<br />
1.2 CERTIFIED TEST REPORTS: Before delivery of materials and equipment, six<br />
certified copies of the reports of all tests required in referenced publications or<br />
specified herein shall be approved by the Contracting Officer. The testing shall<br />
have been performed in an independent laboratory approved by the Contracting<br />
Officer. Test reports shall be accompanied by notarized certificates from the<br />
manufacturer certifying that the tested material and equipment is of the same<br />
type, quality, manufacture, and make as that proposed to be supplied. Certified<br />
test reports are required for the following:<br />
a. Spot Test of Asphaltic Materials<br />
b. Emulsified Asphalt<br />
1.3 DELIVERY AND STORAGE: Materials delivered to the site shall be inspected<br />
for damage, unloaded, and stored with a minimum of handling.<br />
1.4 WEATHER LIMITATIONS: Apply the tack coat only when the surface is dry or<br />
contains moisture not in excess of the amount that will permit uniform<br />
distribution and the desired adhesion. Apply the tack coat only when the<br />
ambient 50 degrees F or above and when the temperature has not been below<br />
50 degrees F for 12 hours immediately prior to applications, unless otherwise<br />
directed.<br />
1.5 TRAFFIC CONTROLS: Keep all traffic off surfaces freshly treated with<br />
bituminous materials. Provide sufficient warning signs and barricades so that<br />
traffic will not travel freshly treated surfaces.<br />
1.6 Tack Coat is to be applied on primed base course prior to laying of bituminous<br />
Hot Mix Pavement.<br />
PART 2 PRODUCTS<br />
2.1 MATERIALS: Bituminous Material for the tack coat shall be asphalt emulsion.<br />
SERIES 1800A Page 1 of 3
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
2.1.1 Emulsified Asphalt: Emulsified asphalt shall conform to ASTM D 977<br />
Type SS-1. The base asphalt used to manufacture the emulsion shall<br />
show a negative spot when tested in accordance with AASHTO T 102<br />
using standard naphtha.<br />
2.2 QUANTITIES TO BE APPLIED: The rate of application of actual bitumen shall<br />
be sufficient to adequately bond the succeeding course of pavement but in no<br />
case shall the rate be less than 0.05 gallon nor more than 0.15 gallon per<br />
square yard. The exact amount of tack coat to be applied shall be as indicated<br />
by the Contracting Officer after test application by the Contractor. The<br />
application rate used as a basic for bidding quantity shall be 0.10 gallons per<br />
square yard.<br />
2.3 CONSTRUCTION EQUIPMENT: All equipment shall be dependable and<br />
adequate for the purpose intended and shall be properly maintained in<br />
satisfactory and safe operating condition at all times. Calibrated equipment<br />
such as asphalt distributors, scales, batching equipment, spreaders and similar<br />
equipment shall have been recalibrated within 12 months of commencing work.<br />
The Contractor in the presence of the Contracting Officer when required by the<br />
Contracting Officer shall do additional recalibration.<br />
2.3.1 BITUMINOUS DISTRIBUTOR: The equipment used by the Contractor<br />
shall include a self-powered pressure bituminous material distributor<br />
and equipment for heating bituminous material. Bituminous distributor<br />
shall have pneumatic tires of such width and number that the load<br />
produced on the base surface shall not exceed 650 psi of tire width.<br />
The distributor shall be designed and equipped to distribute the<br />
bituminous materials uniroformly at even heat on variable widths of<br />
surface at readily determined and controlled rates from 0.05 to 2.0<br />
gallons per square yard, with a pressure range of 25 to 75 psi and an<br />
allowable variation not to exceed 5 percent from any specified rate.<br />
Distributor equipment shall include a separate power unit for the<br />
bitumen pump, full-circulation spray bars, tachometer, pressure gages,<br />
volume-measuring devices, adequate heaters for heating the materials<br />
to the proper application temperature, a thermometer to show the<br />
temperature of tank contents, and a hose attachment suitable for<br />
applying bituminous material to spots unavoidably missed by the<br />
distributor. The distributor shall be equipped to circulate and agitate<br />
the bituminous material during the heating process.<br />
2.3.2 Brooms and Blowers: Brooms and blowers shall be of the power<br />
type and shall be suitable for cleaning the prepared surfaces for<br />
application of the tack coat. They shall not create environmental<br />
pollution and shall meet the requirements of SERIES 200:<br />
ENVIRONMENTAL PROTECTION.<br />
PART 3 – EXECUTION<br />
3.1 GENERAL: The bituminous tack coat shall be applied on a previously<br />
prepared primed Portland cement stabilized base course (CTB) and concrete<br />
structures where asphaltic paving abuts new or existing items.<br />
SERIES 1800A Page 2 of 3
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
3.2 PREPARATION OF SURFACE: Immediately before applying the tack coat to<br />
the surface that is to be paved, all loose material, dirt, clay, or other objectional<br />
substance shall be removed from the surface by means of a power broom or<br />
blower supplemented with hand brooms. After the cleaning operation and prior<br />
to the application of the tack coat, an inspection of the area to be paved will be<br />
made by the Contracting Officer to determine the fitness of the area to receive<br />
the bituminous material. To assure a uniform spread of the bituminous material,<br />
the portion of the surface prepared for treatment, if excessively dry, shall be<br />
lightly sprinkled with water immediately before the application.<br />
3.3 APPLICATION OF BITUMINOUS MATERIAL: Emulsified asphalt shall be<br />
diluted with one part water to one part asphalt after the asphalt is placed in the<br />
distributor tank. The tack coat shall be applied when the surface to be treated<br />
is dry or contains moisture not in excess of that which will permit uniform<br />
distribution and the desired adhesion. Immediately following the preparation of<br />
the surface for treatment, the bituminous material shall be applied by means of<br />
the distributor, within the limits of temperature and at the rate not less 0.05<br />
gallons nor more than 0.15 gallons of bituminous material per square yard as<br />
directed by the Contracting Officer. Bituminous material shall be applied so that<br />
uniform distribution is obtained over the entire surface to be treated. All areas<br />
missed by the distributor shall be treated properly with the bituminous material.<br />
Following the application of bituminous material, the surface shall be allowed to<br />
cure without being disturbed for such period of time as may be necessary to<br />
permit setting of the tack coat. The bituminous tack coat shall be applied only<br />
as far in advance of the placing of overlaying layer as required for that day’s<br />
operation. The treated surface shall be maintained and protected from damage<br />
until the succeeding course of pavement is placed.<br />
3.3.1 Application Temperature of Emulsified Asphalt: Application<br />
temperature of emulsified asphalt shall be within the range of 85 to 190<br />
degrees F.<br />
3.4 FIELD SAMPLING AND TESTING:<br />
3.4.1 Calibration Tests: The Contractor shall furnish such equipment and<br />
materials and perform the work to calibrate the tank and measuring<br />
devices of the distributor. This shall be done on the job at the<br />
beginning of the work.<br />
3.4.2 Samples of Bituminous materials: Samples of bituminous materials<br />
shall be furnished by and at the expense of the Contractor. Sampling<br />
shall be in accordance with ASTM D140.<br />
3.4.3 Tests: An independent testing laboratory at the expense of the<br />
Contractor shall conduct all tests on bituminous materials.<br />
3.4.4 Spot Test: Spot test for bitumen shall be conducted in accordance<br />
with AASHTO T102, and shall be performed on each shipment.<br />
****** END OF SECTION ******<br />
SERIES 1800A Page 3 of 3
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
SERIES 1800B<br />
HOT MIX BITUMINOUS PAVEMENT<br />
Additional Requirements for Hot Mix Bituminous Pavement Section 32 12 17.<br />
PART 1 – GENERAL<br />
1.1 APPLICABLE PUBLICATIONS: The publications listed below form a part of<br />
this specification to the extent referenced. The publications are referred to in<br />
the text by the basic designation only.<br />
1.1.1 Military Standard:<br />
MIL-STD-620A Test Methods for Bituminous Paving Materials.<br />
1.1.2 American Association of <strong>State</strong> Highway and Transportation Officials<br />
(AASHTO) Publications:<br />
1.1.3 American Society of Testing and Materials (ASTM) Publications:<br />
1.1.4 Asphalt Institute Publications:<br />
1.2 SUBMITTALS:<br />
1.2.1 Samples: Samples of the following materials shall be submitted and<br />
approved in accordance with the specifications:<br />
a. Coarse Aggregate<br />
b. Fine Aggregate<br />
c. Mineral Filler<br />
d. Asphalt Cement<br />
1.2.2 Test Reports: Seven copies of the certified test reports required in<br />
referenced publications or specified herein for each lot of bitumen used<br />
for the project shall be approved by the Contracting Officer. The<br />
furnishing of the certified test reports for the bituminous materials shall<br />
not be interpreted as a basis for final acceptance. All such test reports<br />
shall be subject to verification by testing samples of materials received<br />
for use on the project.<br />
1.2.3 Job Mix Formula: A job mix formula shall be furnished by the<br />
Contractor, approved by the Contracting Officer prior to preparing and<br />
placing the bituminous mixture. The formula shall indicate the definite<br />
percentage of each sieve fraction, percentage of bitumen, the<br />
temperature of the mixture leaving the mixer, number of blows of<br />
compaction hammer per side of molded specimen, stability, flow,<br />
percent of voids total mix, percent of voids filled bitumen, the<br />
temperature viscosity relationship of the asphalt cement, and percent<br />
of aggregate by size from each source.<br />
SERIES 1800B Page 1 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
1.3 DELIVERY AND STORAGE: Materials delivered to the site shall be inspected<br />
for damage and stored with a minimum of handling. Aggregates shall be stored<br />
in such a manner as to prevent segregation.<br />
1.4 GENERAL REQUIREMENTS: The hot-mix pavement shall be constructed on<br />
a prepared base course. The new pavement shall consist of mineral aggregate<br />
uniformly mixed with hot bituminous material. The wearing course shall be<br />
constructed only during dry weather and on dry surfaces. Lines and grade<br />
stakes shall be provided as necessary for control. Grade stakes shall be<br />
placed in lanes parallel to the center of the areas to be paved and suitably<br />
spaced for string lining.<br />
PART 2 – PRODUCTS<br />
2.1 Aggregates: The grading and proportioning of aggregate and filler shall be<br />
such that the combined mineral aggregate conforms to the grading specified<br />
hereinafter.<br />
2.1.1 Coarse aggregates shall conform to ASTM D692/D692M, except for<br />
the soundness test requirements, as modified herein. Crushed gravel<br />
shall have at least 75 percent by weight of pieces having two or more<br />
fractured faces. Aggregates, which show stripping when tested in<br />
accordance with ASTM D1664, shall be rejected. Percentage wear<br />
shall be a maximum of 40 after 500 revolutions by ASTM C131.<br />
2.1.2 Fine aggregate shall conform to ASTM D1073, except for the<br />
soundness test requirements.<br />
2.1.3 Mineral Filler: Not less than two-thirds of material passing 200 mesh<br />
sieve shall be non-plastic material meeting the requirements of ASTM<br />
D242/D242M. The material passing a 200 mesh sieve may be<br />
limestone or other suitable non-plastic material and shall be<br />
supplemented as required by the addition of limestone, Portland<br />
cement, or non-plastic materials as required to obtain the composition<br />
specified.<br />
2.2 ASPHALT CEMENT: Asphalt cement shall conform to ASTM D946,<br />
penetration grade 60-70. The asphalt shall show a negative spot when tested<br />
in accordance with AASHTO method T102. The temperature-viscosity<br />
relationship of the asphalt cement shall be given to the Contracting Officer. The<br />
asphalt cement shall be heated and delivered to the mixer at the temperature<br />
required and shall provide a mixing viscosity of 20 & 120 centistokes, kinematic<br />
or 10 & 60 seconds, Saybolt-Furol.<br />
2.3 Composition of Mixtures: The gradation shall be in accordance with the<br />
typical gradations listed herein for the selected maximum aggregate size when<br />
tested in accordance with ASTM C 136 and ASTM C 117. The gradation shall<br />
be within the job mix formula tolerance limitations specified hereinafter. The<br />
combined aggregate and filler shall be graded smoothly from coarse to fine and<br />
shall not vary the low limit on one sieve to the high limit on the adjacent sieve.<br />
The grading is based on aggregates of uniform specific gravity, and the<br />
SERIES 1800B Page 2 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
percentages passing the various sieves are subject to appropriate correction<br />
when aggregates of varying specific gravities are used. For material passing<br />
the one-inch sieve, the stability and flow will be determined by ASTM D 1559<br />
and shall meet the following requirements.<br />
Tests/Criteria<br />
75 Blow Mix 50 Blow Mix<br />
Stability (Minimum), pounds 2150 1350<br />
Flow, 0.01 inch 8-16 8-18<br />
TSR, minimum percent 75 75<br />
The voids requirements shown herein shall be determined in accordance with<br />
the procedures described in MIL-STD-620, Test Methods 101, based on<br />
maximum specific gravity determined in accordance with ASTM D 2041.<br />
Test/Criteria<br />
Percent voids total mix 3 to 5<br />
Percent voids filled with bitumen 75 to 85<br />
2.4 JOB MIX:<br />
2.4.1 Composition of Mixture: The bituminous plant mix shall be<br />
composed of a mixture of aggregate filler and bituminous material<br />
within the ranges indicated in the following mix composition table,<br />
except that the percentages of asphalt shall be increased as<br />
necessary if the mineral aggregate is porous. The maximum size of<br />
the aggregates shall be 1/2-inch. The aggregate fractions shall be<br />
seized, uniformly graded, and combined in such proportions that the<br />
resulting mixture meets the grading requirements of the job mix<br />
formula.<br />
MIX COMPOSITIONS<br />
Sieve 1-Inch Max ¾-Inch Max ½ Inch Max<br />
3A 4A 5A<br />
1-inch 900 – 100 100 - -<br />
¾-inch - - 90-100 100<br />
½-inch 60 – 80 - - 90 – 100<br />
3/8-inch - - 60 – 80 - -<br />
No. 4 25 – 60 35 – 65 45 – 70<br />
No. 8 15 – 45 20 – 50 25 – 55<br />
No. 50 3 – 18 3 – 20 5 – 20<br />
No. 200 1 – 7 2 – 8 2 – 9<br />
Asphalt Cement 5 – 7 5 – 7 6 – 8<br />
Weight (Percent of total mixture)<br />
SERIES 1800B Page 3 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
2.4.2 Variations: Variations from the approved job mix formula shall not<br />
exceed the following:<br />
Aggregates<br />
½ inch<br />
3/8-inch to No. 4<br />
No. 8 to No. 16<br />
No. 30 and 50<br />
No. 100<br />
No. 200<br />
Asphalt<br />
Temperature of mixture as<br />
discharged<br />
Tolerance (Plus or Minus)<br />
3 percent<br />
3 percent<br />
3 percent<br />
2 percent<br />
1 percent<br />
1 percent<br />
0.4 percent<br />
25 degrees<br />
Adjustments of the bitumen content and aggregate gradation, within the limits<br />
specified herein, to improve the paving mixture shall be made as necessary by<br />
the Contractor and approved by the Contracting Officer without change in the<br />
contract price.<br />
2.5 CONSTRUCTION EQUIPMENT: All equipment shall be dependable and<br />
adequate for the purpose intended and shall be properly maintained in<br />
satisfactory and safe operating condition at all times. Calibrated equipment<br />
such as asphalt distributors, scales, batching equipment, spreaders, and similar<br />
equipment, shall have been recalibrated by a calibration laboratory<br />
recommended by the Contractor and approved by the Contracting Officer within<br />
12 months of commencing work. The Contractor in the presence of the<br />
Contracting Officer when required by the Contracting Officer shall do additional<br />
recalibration.<br />
2.5.1 Mixing Plant: The mixing plant shall be designed, coordinated, and<br />
operated to produce a mixture within the job mix formula tolerance and<br />
shall meet the requirements of ASTM D995 except as specified herein.<br />
The mixing plant shall be either weight-batch type or continuous mixing<br />
type. The mixing plant shall have a capacity capable of producing AC<br />
mixtures at rates meeting job specification requirements. Rotary-drum<br />
type may be substituted for the above types, provided the equipment is<br />
suitable for producing finished mixtures complying with the job mix<br />
formula specified herein. The paving plant and equipment shall remain<br />
accessible at all times for checking its adequacy, inspecting its<br />
operation, verifying weights, proportions, and character of materials,<br />
and checking mixture temperatures.<br />
2.5.1.1 Equipment for Preparation of Bituminous Material: Tank for<br />
storage of bituminous material shall be equipped with a heating<br />
system capable of heating the material under the effective and<br />
positive control, at all times, to the temperature requirements<br />
specified. Heating shall be accomplished by steam coils,<br />
electricity, or other means shall accomplish heating so that no<br />
flame will come in contact with the heating tanks. The circulating<br />
SERIES 1800B Page 4 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
system for the bituminous material shall be adequate size to<br />
insure proper and continuous circulation between storage tank<br />
and mixer during the entire operating period. All pipe lines and<br />
fittings shall be steam-jacketed or otherwise properly insulated to<br />
prevent heat loss. The storage tank capacity shall be sufficient for<br />
at least a one-day run. The storage tank capacity shall be free<br />
from accretions of foreign or caked bituminous materials or other<br />
substances, which could contaminate the bituminous mix<br />
materials or preclude an accurate inventory of quantities. Tanks<br />
shall be calibrated and charts indicating the depth to liquid-volume<br />
relationship shall be proved. The temperature of the asphaltic<br />
cement shall not exceed 325 degrees F at any time.<br />
2.5.1.2 Feeder for Dryer: The plant shall be provided with a accurate<br />
mechanical means for uniformly feeding the mineral aggregate<br />
into the dryer so that uniform production and uniform temperature<br />
will be secured. The feeder or feeders shall be capable for<br />
delivering the maximum number of aggregate sized required in<br />
their proper proportion. The feeder shall provide for adjustment of<br />
total and proportional feed and shall be capable of being locked in<br />
any position. When more than one cold elevator is used, each<br />
shall be fed as separated unit and individual controls shall be<br />
integrated with a master control.<br />
2.5.1.3 Dryer: A rotary dryer of satisfactory design for drying and heating<br />
the aggregates shall be provided. Dryer shall be capable of<br />
continuously supplying the mixing unit at its operating capacity<br />
with dried aggregates of the specified temperature. The<br />
aggregates delivered to the hot bins shall contain moisture to an<br />
extent that will cause foaming, segregation, or stripping during<br />
hauling and placing operations. The dyer shall be equipped with a<br />
heat-indicating device to measure the temperature of the<br />
aggregate as it leaves the dryer. The device shall be accurate<br />
within 10 degrees F and shall be installed in such manner that a<br />
10 degrees F change in aggregate temperature will be indicated<br />
within one minute.<br />
2.5.1.4 Plants screens capable of screening all dried aggregates to the<br />
specified sizes and proportions and having normal capacities<br />
slightly in the excess of the full capacity of the mixer or the dryer<br />
shall be provided. The screens shall be accurate and efficient and<br />
no bin shall be allowed to contain more than 10 percent oversize<br />
or undersize.<br />
2.5.1.5 Bins: The plant shall include storage bins of sufficient capacity to<br />
supply a mixer operating at full capacity. Bins shall be arranged to<br />
assure separate and adequate storage of appropriate fractions of<br />
the mineral aggregates. When used, separate dry storage shall<br />
be provided for filler or hydrated lime, and plant shall be equipped<br />
to feed such material into the mixer. Each pin shall be provided<br />
with overflow pipes of such size and at such location to prevent<br />
SERIES 1800B Page 5 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
back of material into the adjacent compartments or bins. Each<br />
compartment shall be provided with its individual outlet gate to<br />
prevent leakage. The gate shall cut off quickly and completely.<br />
Bins shall be equipped with adequate tell-tale devices, which<br />
indicate the position of the aggregates in the bins at the lower<br />
quarter points.<br />
2.5.1.6 Bituminous Control Units: Satisfactory means shall be provided<br />
to obtain the proper of bituminous material in the mix within the<br />
tolerances specified by the job mix formula, either by weighing,<br />
metering, or volumetric measurements. Suitable means shall be<br />
provided, either by steam-jacketing or other methods of insulation,<br />
for maintaining the specified temperature of the bituminous<br />
material in the pipelines, meters, weight buckets, spray bars, and<br />
other containers or flow lines.<br />
2.5.1.7 Thermometric Equipment: An armored thermometer with a<br />
range from 200 degrees to 400 degrees F shall be fixed in the<br />
bituminous feed line at a suitable location near the discharge<br />
valve at the mixer unit. The plant shall be further equipped with<br />
an approved dial-scale, mercury-actuated thermometer, an<br />
electric pyrometer, or other approved thermometric instrument so<br />
placed at the discharge chute of the dryer as to register<br />
automatically or indicate the temperature of the heated aggregate.<br />
The dial shall be in full view of the dryer fireman of feeder.<br />
2.5.2 Safety Requirements: Adequate and safety stairways to the mixer<br />
platform and sampling points shall be provided, and guarded ladders to<br />
other plant units shall be placed at all points where accessibility to plant<br />
operations is required. Accessibility to the top of the truck bodies shall be<br />
provided by a suitable device to enable the Contractor to obtain sampling<br />
and mixture temperature data. Means shall be provided to raise and lower<br />
scale calibration equipment, and other similar equipment between the<br />
ground and the mixer platform. All gears, pulleys, chains, sprockets, and<br />
other dangerous moving parts shall be thoroughly guarded. Ample and<br />
unobstructed passage shall be maintained at all times in and around the<br />
truck loading area. These areas shall be kept free of drippings from the<br />
mixing platform.<br />
2.5.3 Dust Control: The plant shall be equipped with a dust collector designed to<br />
waste or return in a constant flow to the hot elevator, by mechanical means,<br />
all or part of the material collected. The quantity recovered shall be as<br />
necessary to provide and maintain composition specified. The plant shall<br />
have a mixer cover such additional housing to insure the proper control of<br />
dust.<br />
2.5.4 Truck Scales: Unless an automatic batching plant with automatic printers<br />
is used, the bituminous mixture shall be weighted on approved scales<br />
furnished by the Contractor or on public scales at the Contractor’s expense.<br />
Scales shall be inspected for accuracy and sealed as often as the<br />
Contracting Officer deems necessary.<br />
SERIES 1800B Page 6 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
2.5.5 Testing Laboratory: The Contractor shall provide a testing laboratory for<br />
control and acceptance testing functions during periods of mix production,<br />
sampling, and testing and whenever materials subject to the provisions of<br />
these specifications are being supplied or tested. The laboratory shall<br />
provide adequate equipment, space, and utilities as required for the<br />
performance of the specified tests.<br />
2.5.6 Special Requirements for Batch Mixing Plants:<br />
2.5.6.1 Weigh Box or Hopper: The equipment shall include means for<br />
accurately weighing each bin size of aggregate in a weigh box or<br />
hopper suspended on scales, ample in size to hold a full batch without<br />
hand-raking or running over. The weigh box or hopper shall be<br />
supported on knife-edge fulcrums so constructed that they will not be<br />
thrown out of alignment easily. The gates on the bins and hopper shall<br />
prevent leakage of aggregate when closed.<br />
2.5.6.2 Scales for weigh box or hopper shall be of standard make and<br />
design and shall be of the beam or springless dial type sensitive to ½ of<br />
one percent of the maximum load that may be required. Beam type<br />
scales shall have a separate beam for each size aggregate, with a<br />
single tell tale actuated for each separate and a tare beam for<br />
balancing the hopper. Dial scales shall be designed, constructed and<br />
installed so that they will be free from vibration. All dials shall be<br />
located so as to be plainly visible to the operator at all times and of<br />
such size that the numerals can be read at a distance of 25 feet.<br />
At least ten standard 50-pound test weights shall be provided for<br />
checking the accuracy of the scales. Test weights will be kept clean<br />
and shall be stored near the scales.<br />
2.5.6.3 Asphalt bucket for weighing the bituminous material shall have<br />
sufficient capacity to hold not less than 15 percent of the rated capacity<br />
of the mixer. It shall be steam-jacketed or equipped with properly<br />
insulated electric heating units and shall be suspended on dial or beam<br />
scales which shall show the weight of the bucket, for each weighing,<br />
and the net weight of bituminous material to an accuracy within one<br />
percent of the weight of material required. The discharge system shall<br />
deliver the heated bituminous material in a thin, uniform sheet or in<br />
multiple streams the full width of the mixer, except that in the case of a<br />
rotary mixer, the bituminous material shall be sprayed into the mixer.<br />
2.5.6.4 Volumetric meter for automatically metering the bituminous<br />
material into each batch shall be provided with a dial to indicate the<br />
amount of asphalt and shall have a capacity of at least 10 percent in<br />
excess of the number of gallons of asphalt required in each batch.<br />
The meter shall be constructed so that it may be locked at any dial<br />
setting and will automatically reset to this reading after the addition of<br />
asphalt to each batch. The dial shall be in full view of the mixer<br />
operator. The flow of asphalt shall be automatically controlled, shall<br />
SERIES 1800B Page 7 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
begin when the dry mixing period ends, and all of the asphalt shall be<br />
discharged in not more than 15 seconds after the flow has started.<br />
Spray bar openings of sufficient size and spacing shall provide for the<br />
uniform application of asphalt for the full length of the mixer. A valve<br />
and outlet shall be provided between the charging valve and spray bar<br />
as a means for checking and testing the accuracy of the meter.<br />
2.5.6.5 Mixer: The batch mixer shall be an approved type capable of<br />
producing a uniform mixture within the job mix tolerances. If not<br />
enclosed, the mixer box shall be equipped with a dust hood to prevent<br />
loss of dust. The clearance of blades from all fixed and moving parts<br />
shall not exceed ¾ inch.<br />
2.5.6.6 Control of Mixing Time: The mixer shall be equipped with an<br />
accurate time lock to control the operations of complete mixing cycle.<br />
It shall lock the weigh-box gate after the charging of the mixer and<br />
keep cycle. It shall lock the bituminous material bucket throughout the<br />
dry mixing periods. The dry mixing period is defined as the interval of<br />
time between the opening of the weigh-box gate and the introduction<br />
of bituminous material. The wet mixing period is the interval of time<br />
between the introduction of bituminous material and the opening of the<br />
mixer gate. The timing control shall be flexible and shall be capable of<br />
settings of 5-seconds intervals or less throughout a 3-minute cycle. A<br />
mechanical batch counter shall be installed as part of the timing device<br />
and shall be designed to register only completely mixed batches. The<br />
setting of time intervals shall be at the direction of the Contracting<br />
Officer, who shall then lock the case covering the timing device until a<br />
change is made in the timing periods.<br />
2.5.7 Special Requirements for Continuous Mixing Plants:<br />
2.5.7.1 Aggregate Proportioning: The plant shall include means for<br />
accurately proportioning each size of aggregate. The plant shall have<br />
a feeder mounted under each compartment bin. Each compartment<br />
bin shall haven an accurately controlled individual gate to form an<br />
orifice for volumetrically measuring the material drawn form each<br />
compartment. The feeding orifice shall be rectangular with one<br />
dimension adjusted by positive mechanical means provided with a<br />
lock. Indicators shall be provided for each gate to show the respective<br />
gate opening in inches. The fine bin shall be equipped with a vibrating<br />
unit or other equipment, which shall effectively prevent any “hang-up”<br />
of material while the plant is operating. A positive system shall be<br />
provided to indicate the level of material in each bin, and as the level of<br />
material in one bin approaches the strike-off capacity of the feed gate,<br />
the device shall automatically close down the plant instantly. The plant<br />
will not be permitted to operate unless this automatic system is in good<br />
working condition.<br />
2.5.7.2 Weight Calibration of Aggregate Feed: The plant shall include a<br />
means for calibration of gate openings by weighing test samples.<br />
Provisions shall be made so that materials fed out of individual orifices<br />
SERIES 1800B Page 8 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
may be passed to individual test boxes. The plant shall be equipped to<br />
conveniently handle individual test samples weighing not less than 200<br />
pounds. Accurate scale of adequate capacities shall be provided by<br />
the Contractor to weigh such test samples.<br />
2.5.7.3 Synchronization of aggregate and Bituminous Feed: Satisfactory<br />
means shall be provided to afford positive interlocking control between<br />
the flow of aggregate from the bins and the flow of bituminous material<br />
form the meter or other proportioning device. This control shall be<br />
accomplished by interlocking mechanical means or any positive<br />
satisfactory to the Contracting Officer. Aggregate feeders that are<br />
mechanically driven shall be directly connected with the drive on the<br />
asphalt binder pump. The drive shaft on the feed shall be equipped<br />
with a revolution and with counter reading to 1/100 of a revolution and<br />
with sufficient capacity to register the total number of revolutions in a<br />
day’s run.<br />
2.5.7.4 Mixer: The plant shall include a continuous mixer of an approved<br />
type, adequately heated and capable of producing a uniform mixture<br />
within the job-mix tolerances. It will be equipped with a discharge<br />
hoper with dump gates, which will permit rapid and complete discharge<br />
of the mixture. The paddles shall be adjustable for angular position on<br />
the shafts and reversible to retard the flow of the mix. The mixer shall<br />
have a manufacturers plate giving the net volumetric contents of the<br />
mixer at the several heights inscribed on a permanent gage. Charts<br />
shall be provided showing the rate of feed of aggregate per minute for<br />
the aggregate being used.<br />
2.5.8 Paving Equipment:<br />
2.5.8.1 Spreading equipment: Spreading equipment shall be the selfpropelled<br />
type, equipped with hoppers, distributing screws, adjustable<br />
screeds, and equalizing devices capable of spreading hot bituminous<br />
mixtures without treating, shoving, or gouging, and of producing a<br />
finished surface of specified evenness. Spreaders shall operate, when<br />
laying mixtures, at a speed between 5 and 45 feet per minute, as<br />
directed by the Contracting Officer. They shall be equipped with a<br />
quick and efficient steering device and shall have a forward and<br />
reverse traveling speed of not less than 100 feet per minute.<br />
Spreaders shall be equipped with mechanical devices to adjust to<br />
grade and confine the edges of the pavement curbs, manholes, and<br />
similar structures shall be given a bituminous tack coat.<br />
2.5.8.2 Rolling equipment shall consist of self-propelled roller of the<br />
pneumatic-tired and/or the three-wheel tandem type and vibratory<br />
type. Three wheel and tandem rollers shall weigh not less than 9<br />
tons. Three wheel rollers shall have a minimum weight of 300 pounds<br />
per inch of rear wheel width. Pneumatic-tired rollers shall be of the<br />
double axle type equipped with pneumatic tires of equal size and<br />
diameter. Tires shall be uniformly inflated so that the air pressure in<br />
the several tires will not vary more than 5-pounds per square inch and<br />
SERIES 1800B Page 9 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
be so arranged that the tires on the axle will cover the gap between the<br />
tires on the other axle. Pneumatic-tired rollers shall be so constructed<br />
that the total weight of the rollers can be varied to produce an<br />
operating weight per tire from 1,000 pounds minimum to a maximum of<br />
4,500 pounds or as required to obtain the specified density. All rollers<br />
shall be suitable for rolling hot-mix bituminous pavements and shall be<br />
capable of reversing without backlash. Pneumatic-tired rollers shall be<br />
capable of being operated both forward and backward without turning<br />
on the mat, and without loosening the surface being rolled. Rollers<br />
shall be equipped with suitable devices and apparatus to keep the<br />
rolling surfaces wet and prevent adherence of bituminous mixtures.<br />
2.5.8.3 Hand Tampers: Hand tampers shall weigh not less than 25 pounds<br />
and shall have a tamping face of not more than 50-square inches.<br />
2.5.8.4 Mechanical Hand Tampers: Mechanical hand tampers shall be<br />
commercial type operated by pneumatic pressure or by internal<br />
combustion.<br />
2.5.8.5 Power Blowers and Power Brooms: Blowers and brooms shall be of<br />
the power type and shall be suitable for cleaning the surface to be<br />
paved.<br />
2.5.8.6 Scales: Scales shall be standard truck scales of the beam type. The<br />
scales shall be of sufficient size and capacity to accommodate all<br />
trucks to be used for handling bituminous mixtures with all wheels on<br />
the scale at the time. All scales shall be tested, as directed by the<br />
Contracting Officer, and the necessary number of standard weights for<br />
testing the scales shall be on hand at all times.<br />
2.5.8.7 Miscellaneous Equipment: Shall tools, including rakes, lutes,<br />
shovels, smoothing irons, pavement cutters, wheel-mounted wagons<br />
for heating small tools, wood sandals and stilts sandals type, and other<br />
small tools, shall be provided as necessary.<br />
PART 3 – EXECUTION<br />
3.1 Mixing: The bituminous mixture shall be produced in a suitable plant as<br />
specified hereinbefore. The fine and coarse aggregate shall be piled separately<br />
and fed to the dryer by separate mechanical feeders in a manner to produce a<br />
bituminous mixture within the tolerances specified for the job mix formula. The<br />
aggregates shall be heated and dried thoroughly before being placed in the<br />
plant hot bins. The temperature of the aggregate, mineral filler, and asphalt in<br />
the mixer shall be such that the viscosity of the asphalt in the mixture will be in<br />
the range of 20 & 120 centistokes kinematic or 10 & 60 seconds, Saybolt Furol<br />
The heated and dried aggregates shall be screened, separated into specified<br />
size conveyed to separate bins, and held ready for mixing with the bituminous<br />
material. Adequate dry storage shall be provided for mineral filler at the mixing<br />
plant. After the aggregates have been prepared properly, they shall be<br />
accurately weighted or measured and conveyed into the mixer in the<br />
proportionate amounts of each aggregate size required. Mineral filler shall be<br />
SERIES 1800B Page 10 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
weighted or fed by some accurate and uniform measurement, and added<br />
separately, and in a dry condition, as near as possible to the center of the<br />
mixer. The required amount of asphalt for each batch, or calibrated amount for<br />
continuous mixing, shall be introduced into batch, or calibrated amount for<br />
continuous mixing, shall be introduced into the mixer. In batch mixing, the<br />
aggregates shall be charged into the mixer, the asphalt added, and mixing<br />
continued for at least 25 seconds or longer as necessary to obtain<br />
homogeneous mixture. When a continuous mixer is used, the mixing time shall<br />
be not less than 30 seconds, as may be necessary to obtain homogeneous<br />
mixture. The additional mixing time, when required, shall be as directed by the<br />
Contracting Officer. The temperature of the asphalt at the time of mixing shall<br />
not exceed 325 degreed F. When prepared in a twin pugmill mixer, the depth<br />
of the mixture shall be not greater than the tips of the mixer blades when the<br />
blades are in a vertical position. All overheated and carbonized mixtures, and<br />
mixtures that foam, segregate, or strip shall be rejected. When excessive<br />
moisture causes foaming, segregation, or stripping, all aggregates in bins shall<br />
be removed and placed in their respective stockpiles.<br />
3.2 Transportation of Bituminous Mixtures: The bituminous mixture shall be<br />
transported from the paving plant to the site in trucks having tight, clean,<br />
smooth beds which have been painted or sprayed with a limewater, soap, or<br />
detergent solution at least once a day to prevent adhesion of the mixture to the<br />
truck bodies. Each load shall be covered with canvas or other suitable material<br />
of ample size to protect it from the weather and to control the loss of heat.<br />
Deliveries shall be made so that spreading and rolling of all the mixture<br />
prepared for a day’s run can be completed during daylight, unless satisfactory<br />
artificial light is provided. The mixture shall be delivered to the area to be<br />
paved in such a manner that the temperature at the time of the dumping the<br />
spreader will be not less than 250 degrees F. Any load that has been<br />
uncovered and contaminated by rainwater prior to placing shall be rejected.<br />
Hauling over freshly laid material will not be permitted.<br />
3.3 Placing: Prior to laying the wearing course, the underlying course shall be<br />
cleaned of all foreign or objectionable matter by power blowers, power brooms,<br />
or hand brooms in places inaccessible to power equipment, and will be<br />
inspected by the Contracting Officer for compaction and smoothness<br />
requirements. Asphalt mixture having a temperature less than 250 degrees F,<br />
when dumped into the hopper of the spreader, will be rejected. The mechanical<br />
spreader shall be adjusted and the speed regulated so that the surface of<br />
wearing course shall be smooth and when compacted shall conform to depth,<br />
cross section, grades, and contours indicated. The finished surface shall vary<br />
not more than 1/8-inch for wearing course when the test for smoothness is<br />
performed with a 10-foot straightedge. The thickness shall vary from the<br />
specified thickness by not more than ¼-inch for wearing course. When the<br />
irregularities of the surface or the deficiency in depth is more than the specified<br />
tolerances, the defective work shall be removed and replace with new material<br />
without additional cost to the Owner. Whenever possible, the mixture for the<br />
wearing course shall be placed in strips not less than 10 feet wide. After the<br />
first strip has been placed and rolled the second strip and succeeding strips<br />
shall be placed and rolled. Rolling shall overlap to the previously placed strip<br />
and shall be extended to overlap the first strip. The length of any strip laid<br />
SERIES 1800B Page 11 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
before placing the succeeding strip shall be as directed by the Contracting<br />
Officer. Placing of the mixture shall be as continuous as possible. A sufficient<br />
number of experienced shovelers and rakers shall follow the spreading<br />
equipment, adding hot mixture and raking as required to produce a course that,<br />
when completed, shall conform to all requirements specified. In areas wherein<br />
the use of machine spreading is impractical, the mixture may be spread by<br />
hand. The mixture shall be distributed into place from dump boards by means<br />
of hot shovels and spread with hot rakes in a uniformly loose layer of such<br />
thickness that, when compacted, it shall conform to the required grade and<br />
thickness. The loads shall not be dumped any faster than they can be handled<br />
properly by the shovelers and rakers. Contact surfaces of previously<br />
constructed curbs, manholes, and similar structures shall be painted with a thin<br />
coat of bituminous material prior to placing the bituminous mixture.<br />
3.4 Joints: All joints shall present the same textures, density, and smoothness as<br />
other sections of the course. The joints between old and new pavements or<br />
between successive day’s work shall be made carefully in a manner to ensure a<br />
thorough and continuous bond between old and new sections of the course. All<br />
contact surfaces of previously constructed pavements shall be coated with a<br />
uniform coat of hot bituminous material immediately before the fresh mixture is<br />
placed. Where required, fresh mixtures shall be raked against joints, thoroughly<br />
tamped, smoothed with hot smoothers, and rolled.<br />
3.4.1 Transverse: The roller shall pass over the unprotected end of the<br />
freshly laid mixture only when the laying of the course is to be<br />
discontinued. Except when a canvas-rope cloth is used, the edge of<br />
the previously, laid course shall be cut back to expose an even,<br />
vertical surface for the full thickness of the course. The fresh mixtures<br />
shall be raked against the joints, thoroughly tamped with hot tampers,<br />
and smooth with hot smoothers, followed by rolling.<br />
3.4.2 Longitudinal: When the edges of the longitudinal joints are irregular,<br />
honeycombed, or poorly compacted, all unsatisfactory section of the<br />
joint shall be cut back to expose an even, vertical surface for the full<br />
thickness of the course, and joint shall be repaired with new material.<br />
When required, fresh mixture shall be raked against the joints,<br />
thoroughly, tamped with hot tampers, and smoothed with hot<br />
smoothers, followed by rolling.<br />
3.5 Compaction of Mixture: Compaction shall be effected by rolling. Rolling shall<br />
begin as soon as after placing as the mixture will bear the roller without undue<br />
displacement. Delays in rolling freshly spread mixture will not be tolerated.<br />
Rolling shall start longitudinally at the extreme sides of the lanes and shall<br />
proceed toward the center of the pavement, overlapping on successive strips<br />
by at least one-half the width of the rear wheel of the roller. Alternate trips of<br />
the roller shall be slightly different lengths. The initial longitudinal rolling shall be<br />
effected by the use of a steel roller. Tests for conformity with the specified<br />
crown, grade, and smoothness shall be made immediately after initial<br />
compaction. Before continuing the rolling any variation shall be corrected by<br />
removing or adding materials as necessary. The course shall then be rolled,<br />
using pneumatic-tired rollers or tandem rollers, while the mixture is hot and in<br />
SERIES 1800B Page 12 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
condition suitable for proper compaction. The speed of the roller shall not<br />
exceed 3-miles per hour and shall at all times be slow enough to avoid<br />
displacement of the hot mixture. Any displacement of the mixture shall be<br />
corrected at once by the use of rakes and fresh mixture applied or mixture<br />
removed as required. Rolling shall be continued until all roller marks are<br />
eliminated and the course has a density of at least 96 percent of the density<br />
obtained in a laboratory specimen of the same mixture when subjected to 50<br />
blows per side in the Marshall mold. During rolling, rollers shall be moistened<br />
to prevent adhesion of the mixture to the rolling surfaces, but an excess of<br />
water shall not be permitted. Competent and experienced roller men shall<br />
operate the rollers. At least two rollers shall be provided for each spreading<br />
machine operation on the job. Additional 10-ton rollers shall be provided if the<br />
specific pavement density is not obtained by the operation of the minimum<br />
number of rollers. In all places not accessible to the rollers, the mixture shall<br />
be compacted thoroughly with hot mechanical or manual hand tampers. Skin<br />
patching of an area that has rolled will not be permitted. Any mixture that<br />
becomes mixed with foreign material or defective shall be removed, replaced<br />
with fresh mixture, and compacted to the density of the surrounding area. The<br />
roller shall pass over the unprotected edge of the course only when the laying<br />
of the course is to be discontinued for a length of time to permit the mixture to<br />
become cold. The Contractor shall provide competent workmen who are<br />
capable of performing all work incidental to the correction of all pavement<br />
irregularities. After final rolling, no vehicular traffic of any kind shall be<br />
permitted on the pavement until it has cooled and hardened, and in no case<br />
less than 6 hours.<br />
3.6 FIELD SAMPLING AND TESTING: Samples shall be supplied as specified<br />
herein by the Contractor at his expense. The Contractor at his expense will<br />
conduct testing. All materials and material sources shall be approved not less<br />
than 30 days prior to the use of such material in the work. Duplicate samples<br />
shall be approved to the Contracting Officer on an average of one sample a<br />
week. The duplicates samples shall be taken at the same time and in the same<br />
manner as the original ones.<br />
3.6.1.1 Sampling:<br />
3.6.1.1 Aggregates at Source: Prior to production and delivery of<br />
aggregates, at least one initial sample will be taken in accordance with<br />
ASTM D75/D75M at the source. Each sample shall be collected by<br />
taking three incremental samples at random from the source material<br />
to make a composite sample of not less than 50 pounds. Three<br />
random samples shall be taken from each 3,000 tons of material, or a<br />
day’s run, thereafter during the course of the project. Three increments<br />
shall be taken at random to make a composite sample of not less than<br />
50 pounds. A repetition of the above sampling shall be made when<br />
the source of material is changed or when unacceptable deficiencies<br />
or variation form the specified grading of materials are found in testing.<br />
3.6.1.2 Cold Feed Aggregate Sampling: Two samples shall be taken daily<br />
from the belt conveying materials from the cold feed. Materials shall<br />
be collected in three increments at random to make representative<br />
SERIES 1800B Page 13 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
composite sample of not les than 50 pounds. Samples shall be taken<br />
by a method approved by the Contracting Officer.<br />
3.6.1.3 Fine Aggregates: A 50-pound sample shall be taken form the cold<br />
feed at least two times daily for sieve analyses of fine aggregate and<br />
specific gravity tests. Additional samples may be required to perform<br />
more frequent tests on mineral fillers, or will be required when<br />
analyses show deficiencies, or unacceptable variances or deviations.<br />
Sampling can be reduced to once a day when test results show that<br />
the fines consistently meet specified requirements. The method of<br />
sampling shall be as described herein for aggregates.<br />
3.6.1.4 Bituminous Mix: One sample for each 400 tons, or fraction thereof, of<br />
the un-compacted shall be taken each day for the extraction test. The<br />
sample shall be taken form a truck behind the paver. The minimum<br />
sample shall be 20 pounds. One sample for each 400 tons, or fraction<br />
thereof, shall also be taken of the un-compacted mix each day for<br />
stability testing. The minimum sample shall be 15 pounds. The<br />
samples shall be taken in a clean scoop or shovel by the Contracting<br />
Officer. The size of the sample shall be governed by the maximum<br />
size of particle of mineral aggregate in the mixture in accordance with<br />
ASTM D979. Samples cores at least three inches in diameter shall be<br />
obtained at locations determined by random sampling method, Asphalt<br />
Institute Manual MS-1 (Appendix P) from the completed pavement, for<br />
density tests. Cores shall be carefully removed and shall be delivered<br />
undisturbed and undamaged to a laboratory selected by the Contractor<br />
and approved by the Contracting Officer, without delay<br />
3.6.1.5 Sample Identification: The sample shall be contained in a clean<br />
container, which shall be securely fastened to prevent loss of material.<br />
Each sample shall be tagged for identification. The tag shall contain<br />
the following information.<br />
Contract No. ______________________<br />
Sample No. ______________________<br />
Quality ______________________<br />
Date of Sample ______________________<br />
Sample ______________________<br />
Source ______________________<br />
Intended Use ______________________<br />
For Testing ______________________<br />
3.7 Testing:<br />
3.7.1 Aggregate Testing: Testing of aggregates shall be made on each<br />
sample without delay. Gradation tests shall be made on each sample<br />
in accordance with ASTM C136. Mineral filler shall be tested in<br />
accordance with ASTM D546.<br />
SERIES 1800B Page 14 of 16
NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />
TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />
3.7.1.1 Abrasion: The aggregate shall be tested for wear (Los Angeles<br />
test) in accordance with ASTM C131.<br />
3.7.1.2 Stripping Test: A stripping test in accordance with ASTM D1664<br />
shall be performed initially on all aggregate prior to incorporation<br />
into the work.<br />
3.7.2 BITUMINOUS MIX TESTING: One sample for entire project<br />
requirements of the un-compacted mix shall be tested for extraction in<br />
accordance with ASTM D2172 and sieve analysis in accordance with<br />
AASTO T30. One sample for entire project requirements shall be<br />
tested for stability and flow in accordance with ASTM D1559.<br />
3.7.3 TESTING OF PAVEMENT COURSE:<br />
3.7.3.1 The compacted surfaces of the wearing course shall be<br />
straightedge tested as the work progresses. The straightedge test<br />
shall be applied parallel with and at right angles to the centerline<br />
after final rolling. Variations in the wearing course shall not vary<br />
more than plus or minus 1/8-inch in ten feet. Any portion of the<br />
pavement showing irregularities greater than that specified shall<br />
be corrected as directed by the Contracting Officer.<br />
****** END OF SECTION ******<br />
SERIES 1800B Page 15 of 16