03.11.2014 Views

NYRIP ADDENDUM.pdf - Yap State Government

NYRIP ADDENDUM.pdf - Yap State Government

NYRIP ADDENDUM.pdf - Yap State Government

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Department of Public Works & Transportation<br />

Contracts & Engineering Management Division<br />

<strong>Yap</strong> <strong>State</strong> <strong>Government</strong>, Federated <strong>State</strong>s of Micronesia<br />

P.O. Box 327 Colonia, <strong>Yap</strong> FM 96943<br />

Tel. no: (691)350-4131, 350-3776 or 3877 Fax no: (691) 350-5225<br />

Email: contracts@mail.fm<br />

NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

<strong>ADDENDUM</strong> NO. 1<br />

November 29, 2010<br />

The following changes shall be incorporated into and shall become part of the plans,<br />

specifications, and contract documents for the project:<br />

A. Mobilization:<br />

The Mobilization Payments shall be made for costs associated with establishment of a<br />

camp, yard, and offices, shipment of equipments, personnel, supplies, and incidentals to<br />

the project site, and for all other work and operations that must be performed or cost<br />

incurred before beginning work on the project.<br />

1. The maximum amount of the mobilization item is limited to no more than twenty (20)<br />

percent of the total contract price.<br />

2. The minimum amount of the demobilization is limited to three (3) percent of the total<br />

contract amount and is within the different bid items.<br />

3. Payments for mobilization will made as follows:<br />

a) After the Contractor’s equipment which will be needed on this project, is on site,<br />

payment of forty (40) percent of the mobilization bid item will be allowed.<br />

b) After the Contractor’s materials which will be needed on this project, is on site,<br />

payment of forty (40) percent of the mobilization bid item will be allowed.<br />

c) After the Contractor’s camp, yard, and offices are established; payment of ten<br />

(10) percent of the mobilization bid item will be allowed.<br />

d) After five (5) percent of the contract work, exclusive of mobilization insurance and<br />

bonds, is complete, payment of the remaining portion is allowed.<br />

B. Utilities:<br />

The telephone lines and pedestals, sewerlines, and manholes, waterlines and their<br />

accessories are within the roadway project easement. The Contractor shall verify the<br />

location of the utilities prior to excavation on any part of the project. Damages to the<br />

utilities shall be borne by the Contractor.<br />

C. Coral Material Dredging:<br />

A dredge site for this project is located in Yyin, Fanif, <strong>Yap</strong>. The dredging activities shall<br />

comply with the agreement between the community of Yyin and DPW&T, <strong>Yap</strong> <strong>State</strong><br />

<strong>Government</strong>. Refer to copy of the Agreement.<br />

The law requires an Environmental Impact <strong>State</strong>ment report to be prepared and<br />

submitted to EPA Board for review and approval. The process for scrutiny of the report<br />

to the level of final approval is lengthy and can easily take up to 90 days.<br />

When the final approval is made, the mitigation measures shall be implemented<br />

immediately before and during the actual dredging operation. At this phase, three sets of<br />

plans shall be prepared and submitted to EPA Board for review and approval.<br />

Erosion Sediment Control Plan (ESCP) and Environmental Protection Plan (EPP) shall<br />

be prepared by the Contractor to base upon the approved final EIS. The Water Quality<br />

Page 1 of 5<br />

Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010


Monitoring Plan (WQMP) shall be prepared by the Contracting Officer. The Contractor<br />

shall comply with the recommendations derived from the WQMP.<br />

The following are the General Guidelines of said plans.<br />

1. Erosion and Sediment Control Plan (ESCP)<br />

The ESCP should include, but in not limited to, the following points:<br />

• Introduction/Purpose<br />

• Project Description<br />

• Project Site<br />

‣ Existing site description<br />

‣ Current plant/animal life and habitat<br />

‣ Current state of coral reef, fish population, other organisms<br />

‣ Water flow-tides, currents<br />

• Dredging Plan – Map, Quantity, Methodology, etc.<br />

• Dredging Schedule<br />

• Sediment/Turbidity control measures<br />

‣ Water Quality objectives<br />

‣ Sediment characterization<br />

‣ Predicted flow rates and direction<br />

‣ Control Measures<br />

o Dredging practices – equipments, methodology<br />

o Floating turbidity curtains<br />

o Silt fences – land-based activities<br />

o Dredging sequencing/timing<br />

o Berm Construction<br />

‣ Stockpiling of dredge material<br />

‣ Disposal of unsuitable material, including vegetation<br />

‣ Shoreline rock walls<br />

• Maintenance of protective measures<br />

‣ Turbidity curtains<br />

‣ Silt fences<br />

‣ Berms<br />

‣ Walls<br />

2. Environmental Protection Plan (EPP)<br />

The EPP should include, but is not limited to, the following points:<br />

• Introduction/Purpose<br />

• Project Description<br />

• Protection of natural resources<br />

‣ Water Resources<br />

‣ Historical, Cultural, and Archeological Resources<br />

‣ Biological Resources<br />

‣ Land Resources – including limits of activities<br />

• Petroleum hydrocarbon use and storage<br />

‣ Gasoline<br />

‣ Hydraulic fluid, diesel, lubricants, grease<br />

‣ Oily wastes<br />

‣ General requirements for motorized equipment<br />

• Erosion and sediment control measures & maintenance – land based only<br />

• Waste Management<br />

‣ Dredging/Construction and solid waste<br />

Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />

Page 2 of 5


‣ Sanitary waste<br />

‣ Chemical waste<br />

‣ Hazardous waste<br />

• Air Pollution<br />

‣ Particualates<br />

‣ Smokes<br />

‣ Motorized vehicles/machinery emissions<br />

• Noise Pollution<br />

• Typhoon/adverse weather contingency plan<br />

• Reference<br />

• Appendix – maps, erosion control measures, silt fence installation<br />

schematics, etc.<br />

3. Water Quality Monitoring Plan (WQMP)<br />

The WQMP should include, but is not limited to, the following points:<br />

• Introduction/purpose<br />

• Environmental setting<br />

‣ Site Description<br />

‣ Tides/currents<br />

‣ Sensitive receptors<br />

• Water Quality criteria and objectives<br />

• Baseline Sampling – pre dredging<br />

• Operational sampling – Sampling and Analysis Plan (SAP)<br />

‣ Sample Locations – weather, current, and tide related; up and down<br />

gradient<br />

‣ Sampling equipment and methodologies<br />

‣ Sample timing – regular and storm events<br />

‣ Quality Control/Quality Assurance<br />

• Reporting – format and frequency<br />

• Corrective measures implementation<br />

• Training requirements for sampling and testing staff<br />

• Appendix – Water classification map<br />

D. Project Sign:<br />

On commencement of work on this project, the Contractor shall furnish and erect a<br />

project sign identifying the project in accordance with the instructions of, and in a<br />

location selected by the Contracting Officer. The Contractor shall maintain the sign in<br />

good condition throughout the project construction period, and upon completion, remove<br />

the sign from the premises. No other signs other than those authorized in writing shall be<br />

allowed on the project.<br />

E. Unscheduled Items:<br />

This bill allows for the Contractor to list and price any unscheduled items, which are<br />

necessary for the completion of the works specified, but which have not been scheduled.<br />

Prices shall include the cost of all equipment, materials, labor, profit, and overheads for<br />

the completion of the unscheduled items.<br />

F. Existing Culverts/Bridges:<br />

The existing culverts/bridges throughout the entire length of the roadway, for those<br />

shown on the plans and the others not shown on the plan shall be cleared of vegetation<br />

and remove of accumulated soils and debris (de-clogging). A list of these culverts and<br />

bridges with condition of each shall be provided to the Contracting Officer during the first<br />

Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />

Page 3 of 5


month of field work. The cost of this work shall be fitted in the most appropriate item of<br />

work.<br />

G. Existing Pathways, Driveways, and Intersections:<br />

The existing road intersections, driveways, and pathways throughout the entire length of<br />

the roadway, for those shown on the plans and the others not shown on the plans shall<br />

remain and shall have improved access from the project roadway to every single one of<br />

them. The cost of this work shall be fitted in the most appropriate item of work.<br />

H. Quarry Site:<br />

If the Contractor needs quarry materials, it therefore shall find the source and make all<br />

preparatory works and pay any associated costs.<br />

I. Earth Moving Permit:<br />

The clearing, grubbing, earthwork, quarry work, dredging work, and hauling of soil<br />

materials shall have a valid Earth Moving Permit from EPA and shall be acquired by the<br />

Contractor prior to any earthmoving activities.<br />

J. Additional Technical Requirements:<br />

The following set of Technical Requirements shall be added to the project specifications<br />

and shall become part of the contract documents for the project. The Contractor shall<br />

carefully review and evaluate the additional provisions and requirements as stated<br />

herein and inform the Contracting Officer of any discrepancies and conflicting sections.<br />

The Contracting Officer shall review the issue(s) and shall come up with the<br />

Information/Instructions within 3 days from receipt of RFI.<br />

1. Series 100 – Preliminaries and General Description of Works.<br />

2. Series 200 – Environmental Protection<br />

3. Series 300 – Acheological Deposits and Recovery<br />

4. Series 500 – Maintaining of Traffic<br />

5. Series 900 – Subbase Coarse<br />

6. Series 1000 – Cement Treated Base Coarse<br />

7. Series 1100 – Bituminous Prime Coat<br />

8. Series 1800A – Bituminous Tack Coat<br />

9. Series 1800B – Bituminous Hot Mix Pavement<br />

K. Revisions on Final Elevation on Low-lying Areas as shown on Drawing Plans:<br />

The final road elevation on low-lying areas of the road shall be adjusted as follows:<br />

From STA 5+00 at Centerline Elevation of 10.10ft, the roadway<br />

shall be redesign to smoothly connect back to the proposed<br />

elevation at the preceding station and transition forward to the<br />

existing road elevation as per Standard Vertical Curve Design.<br />

Furthermore, the redesign of vertical curves along the Road<br />

Centerline to STA 68+00 at Elevation 15.63ft shall be treated<br />

for a uniform connection to proposed elevation at station ahead.<br />

Second low-lying area is from STA 95+00 at Elevation 8.88ft to<br />

STA 106+00 at Elevation 15.83ft with the same recommendation<br />

for redesign work as per indicated guidelines above.<br />

The third low-lying area is from STA 109+00 at Elevation 25.47ft<br />

to STA 124+00 at Elevation 23.26ft with the same recommendation,<br />

also for redesign work as indicated guidelines above.<br />

Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />

Page 4 of 5


Within the low-lying areas, the road superelevation shall remain<br />

as per original design. The existing ditches, existing sidewalks,<br />

existing sewer system, shore protection, existing water system<br />

shall be adjusted as required by the redesign requirements.<br />

The Contractor is responsible for the re-designing of, but not<br />

limited to, the Final Elevations, Vertical Curves<br />

(BVC, PIVC, EVC), Superelevations, Horizontal Curve, Elevation<br />

at Driveways, Pathways, and Road Intersections, Drainage,<br />

Concrete Ditch, Sidewalks, Volumes of Cut and Fill.<br />

The redesigning works shall be finalized prior to Earthwork Activites.<br />

L. Construction Term:<br />

The construction duration shall allow for project completion including the rainy months<br />

from April to December and the difficulties in Materials and Equipments shipment within<br />

twelve (12) months.<br />

M. Drainage Crossing at Carraigeway:<br />

Delete all proposed drainage crossings (culverts) at the following locations:<br />

1. STA 4+89.21<br />

2. STA 9+39.40<br />

3. STA 55+82.31<br />

4. STA 91+08.81<br />

5. STA 118+00.43<br />

6. STA 189+15.82<br />

N. Existing Retaining Walls:<br />

The following retaining walls shall not be removed at stations:<br />

1. STA 20.68 (driveway is located after the existing retaining wall)<br />

2. STA 106+74.83 to STA 108+44.08<br />

Northern <strong>Yap</strong> Road Improvements Project - Addendum No. 1 Date: 11-29-2010<br />

Page 5 of 5


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

DETERMINATION<br />

This Preliminary Environmental Impact <strong>State</strong>ment is prepared according to <strong>Yap</strong> <strong>State</strong><br />

Environmental Protection Agency (EPA) regulations Title II - Environmental Impact<br />

Assessment (EIA), Part II Preliminary Environmental Impact <strong>State</strong>ment, pursuant to the<br />

procedures set out in Environmental Quality Protection YSC, Title 18 Conservation and<br />

Resources.<br />

The purpose of the draft EIA process is intended to help the general public and government<br />

officials make decisions with the understanding of the environmental consequences of a<br />

proposed action, and take actions consistent with the goal of protecting, restoring, and<br />

enhancing the environment.<br />

In addition, this process is designed to: (a) integrate the EIA process into early planning of<br />

projects to ensure timely consideration of environmental factors and to avoid delay; and (b)<br />

identify at an early stage the significant environmental issues requiring further study and deemphasize<br />

insignificant issues, thereby defining the scope of the EPA.<br />

It is not the intent of this process to require an exhaustive EIA for all projects large and<br />

small. The degree of environmental assessment detail for a project depends upon the<br />

significance of its potential environmental impact.<br />

LYON ASSOCIATES<br />

i


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

ABREVIATIONS AND<br />

ACRONYMS<br />

BMP<br />

CBD<br />

CBO<br />

COM<br />

COP<br />

EIA<br />

EIS<br />

EPA<br />

ENSO<br />

FSM<br />

IUCN<br />

MAREPAC<br />

NBSAP<br />

NEMS<br />

NGO<br />

NTP<br />

SPREP<br />

TTPI<br />

UN<br />

WSO<br />

Best Management Practices<br />

Convention on Biological Diversity<br />

Community-based Organizations<br />

College of Micronesia<br />

Conference of the Parties<br />

Environmental Impact Assessment<br />

Environmental Impact <strong>State</strong>ment<br />

YAP <strong>State</strong> Environmental Protection Agency<br />

El Nino/Southern Oscillation Phenomena<br />

Federated <strong>State</strong>s of Micronesia<br />

International Union for the Conservation of Nature and Natural<br />

Resources<br />

Marine Resources Pacific Consortium<br />

National Biodiversity Strategy and Action Plan<br />

National Environmental Management Strategies<br />

Non-governmental Organization<br />

Notice to Proceed<br />

South Pacific Regional Environment Program<br />

Trust Territory of the Pacific Islands<br />

United Nations<br />

Weather Service Office<br />

LYON ASSOCIATES<br />

ii


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

TABLE OF CONTENTS<br />

1 BRIEF DESCRIPTION OF PROJECT ....................................................................................... 1-1<br />

1.1 Location ............................................................................................................................ 1-1<br />

1.2 Brief Description of the Existing Road ............................................................................. 1-2<br />

1.3 Proposed Road Improvements ........................................................................................ 1-2<br />

1.4 Scope of Work .................................................................................................................. 1-2<br />

1.5 Project Schedule .............................................................................................................. 1-2<br />

2 ENVIRONMENTAL SETTING OF PROJECT ............................................................................ 2-4<br />

2.1 Geology ............................................................................................................................ 2-4<br />

2.2 Physical Features ............................................................................................................. 2-6<br />

2.3 Climate ............................................................................................................................. 2-7<br />

2.4 Soils & Drainage ............................................................................................................... 2-8<br />

2.5 Wetlands ........................................................................................................................ 2-12<br />

2.6 Forests ........................................................................................................................... 2-12<br />

2.7 Noteworthy Fauna .......................................................................................................... 2-13<br />

2.8 Noteworthy Flora ............................................................................................................ 2-14<br />

2.9 Land Use ........................................................................................................................ 2-14<br />

2.10 Population ...................................................................................................................... 2-15<br />

2.11 Economic Issues ............................................................................................................ 2-17<br />

2.12 Cultural History ............................................................................................................... 2-22<br />

3 GENERAL DESCRIPTION OF PROJECT EFFECTS ............................................................... 3-1<br />

3.1 Problems with the Existing Road Segments .................................................................... 3-1<br />

3.2 Disturbances and Threats to Wetlands ............................................................................ 3-3<br />

3.3 Hydrological & Biophysical Values ................................................................................... 3-3<br />

3.4 Road Improvement Construction ..................................................................................... 3-3<br />

4 POSSIBLE ENVIRONMENTAL IMPACT CHECKLIST ............................................................. 4-4<br />

4.1 Initial Environmental Assessment Checklist .................................................................... 4-4<br />

4.2 Earth- Will the proposed project result in: ........................................................................ 4-4<br />

4.3 Air- Will the proposed project result in: ............................................................................ 4-5<br />

4.4 Water- Will the proposed project result in: ....................................................................... 4-6<br />

4.5 Plant Life- Will the proposed project result in: .................................................................. 4-7<br />

4.6 Animal Life- Will the proposed project result in: ............................................................... 4-7<br />

4.7 Noise- Will the proposed project result in: ....................................................................... 4-8<br />

4.8 Land Use- Will the proposed project result in: ................................................................. 4-8<br />

4.9 Natural Resources- Will the proposed project result in: ................................................... 4-8<br />

4.10 Risk of Upset- Will the proposed project result in: ........................................................... 4-8<br />

4.11 Population- Will the proposed project result in: ................................................................ 4-9<br />

4.12 Housing- Will the proposed project result in: ................................................................... 4-9<br />

4.13 Transpiration- Will the proposed project result in: ............................................................ 4-9<br />

4.14 Public Services ................................................................................................................. 4-9<br />

4.15 Utilities ............................................................................................................................ 4-10<br />

4.16 Human Health- Will the proposed project result in: ........................................................ 4-10<br />

4.17 Aesthetics- Will the proposed project result in: .............................................................. 4-10<br />

4.18 Recreation- Will the proposed project result in: ............................................................. 4-10<br />

4.19 Cultural Resources- Will the proposed project result in: ................................................ 4-10<br />

4.20 Others- Will the proposed project result in: .................................................................... 4-11<br />

5 ALTERNATIVES TO MITIGATE ADVERSE IMPACTS ........................................................... 5-12<br />

5.1 Design Considerations ................................................................................................... 5-12<br />

5.2 Erosion Control Plan ...................................................................................................... 5-13<br />

5.3 Monitoring Plan .............................................................................................................. 5-14<br />

5.4 Traffic Control Plan......................................................................................................... 5-14<br />

6 THE NEED FOR THE PROPOSED PROJECT ......................................................................... 6-1<br />

6.1 Summary .......................................................................................................................... 6-1<br />

7 REFERENCE ............................................................................................................................. 7-2<br />

LYON ASSOCIATES<br />

iii


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

ALL THE EXHIBITS<br />

Exhibit A Ziemer's Observations During Trip To FSM October 28 to November 8, 1990, <strong>Yap</strong><br />

Except<br />

LIST OF TABLES<br />

Table 2-1 Seasonal Precipitation Summary from 1953 to 2006 ..................................................... 2-7<br />

Table 2-2 Monthly Precipitation Summary from 1953 to 2006 ....................................................... 2-8<br />

Table 2-3 Population Distribution: 1930 to 2009 .......................................................................... 2-16<br />

Table 2-4 Total Employment by Sector: FY 2002 to FY 2006 ...................................................... 2-17<br />

Table 2-5 Registered Motor Vehicles in <strong>Yap</strong> ................................................................................ 2-20<br />

Table 2-6 Passenger Arrivals and Departures on Foreign Aircraft and Vessels: 2000 to 2007 .. 2-21<br />

LIST OF FIGURES<br />

Figure 1-1 Road Improvement Project Limits ................................................................................ 1-1<br />

Figure 2-1 Geological Map of <strong>Yap</strong> ................................................................................................. 2-4<br />

Figure 2-2 Soil Map of Project Region ........................................................................................ 2-10<br />

Figure 2-3 Soil Map Legend ........................................................................................................ 2-11<br />

Figure 2-4 Percentage of Land Ownership by <strong>State</strong>:2001 .......................................................... 2-15<br />

Figure 2-5 <strong>Yap</strong> <strong>State</strong> Population Distribution by Age .................................................................. 2-16<br />

Figure 2-6 Dollar Value of Local Markets' Purchases of Agricultural Products by <strong>State</strong> ............ 2-18<br />

Figure 2-7 Copra Production by Volume (Tons), FSM: 1997 to 2006 ......................................... 2-18<br />

Figure 2-8 Annual Inflation Rates: 4th Qtr 2004 to 4th Qtr 2006 ................................................. 2-19<br />

Figure 2-9 Registered Motor Vehicles is FSM: 1999-2006 ......................................................... 2-20<br />

Figure 2-10 <strong>Yap</strong> Communication services: 1997 to 2006 ............................................................. 2-22<br />

Figure 3-1 Existing Watershed Map Along the Project ................................................................. 3-2<br />

Figure 4-1 Slope Stabilization Matting ........................................................................................... 4-4<br />

Figure 4-2 Slope Stabilization with Mulching ................................................................................. 4-5<br />

Figure 4-3 Watering Trucks for Dust Control ................................................................................. 4-6<br />

Figure 4-4 Secondary Containment .............................................................................................. 4-9<br />

Figure 5-1 Silt Fencing for Sediment Control .............................................................................. 5-12<br />

Figure 5-2 Silt Fencing for Cross Section .................................................................................... 5-12<br />

Figure 5-3 Stormwater Outlet Protection ..................................................................................... 5-13<br />

LYON ASSOCIATES<br />

iv


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

1 BRIEF DESCRIPTION OF PROJECT<br />

1.1 Location<br />

1.1.1 The project is located in central to northern <strong>Yap</strong> <strong>State</strong> in the Federated <strong>State</strong>s of<br />

Micronesia. The beginning of the project (BOP) is at the hospital intersection with<br />

the main road to Keng. It proceeds north and end of the project (EOP) terminates<br />

at the western edge of Tagireeng Bridge. This segment of the road travels along<br />

the coastline through the villages of Dogor, Makal, Tafgif, Rumuu, and Garfey. The<br />

approximate length of this road segment is 4.06 miles (6.55 kilometers). See<br />

Figure 1-1 below.<br />

Figure 1-1<br />

Road Improvement Project Limits<br />

Source: USGS<br />

LYON ASSOCIATES 1-1


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

1.2 Brief Description of the Existing Road<br />

1.2.1 The existing road was constructed in the late 1980’s. The <strong>Yap</strong> Road Improvements<br />

- Phase V Soil Investigation Report was in draft form 18 August 1986 by<br />

Geotesting Inc. It was prepared for GMP Associates, Guam. The As-Built Drawings<br />

HT-A-01 through HT-A-15 (presumably) prepared by GMP at the same time.<br />

1.2.2 This project will begin from <strong>Yap</strong> Memorial Hospital to Tangireeng Bridge. This<br />

segment of the road is about 4.06 miles (6.53 k) with 2 inches (5 cc) asphalt<br />

pavement, two-way 9 foot (2.7 m) wide traveling lanes, intermittent concrete<br />

shoulder on both sides and 4 ft sidewalk on the right side only, reinforced concrete<br />

culverts, 4 ft (1.2 m) wide concrete line ditch and about 1.4 miles (2.3 k) of slope<br />

protection. <strong>Yap</strong> <strong>State</strong> replaced the asphalt pavement with portland concrete<br />

pavement in segments of the road particularly that had deteriorated. Most of these<br />

segments were along the shoreline. The lowest elevation of the existing road is<br />

apparently 6 feet (1.8 m) above mean sea level.<br />

1.3 Proposed Road Improvements<br />

1.3.1 The project scope of work include surface road milling, sub-grade preparation,<br />

resurfacing of the 4.06 miles (6.53 k) long, 18 feet (5.5 m) wide roadway (no<br />

widening), elevating the road level to a minimum of 8.00 feet (2.4 m) above Mean<br />

Sea Level in respect to the global warming effects and upgrade of drainage<br />

system, walkways, shoulders, curbs, driveways and effected utilities.<br />

1.4 Scope of Work<br />

1.4.1 The <strong>State</strong> of <strong>Yap</strong>, Department of Public Works and Transportation selected and<br />

signed a contract with Lyon Associates Inc., based in Honolulu, Hawaii with offices<br />

in nearby Pohnpei, FSM and Manila, Philippines.<br />

1.4.2 In part this contract encompasses establishment of ground control, complete<br />

topographic survey of existing ground conditions, existing road condition,<br />

location/elevations of all surface and drainage structures and reduction of all field<br />

data, including, plotting onto plan/profile sheets, preparation of plans,<br />

specifications, cost estimates, basis of design and design calculations.<br />

1.4.3 Furthermore, the Consultant shall prepare the preliminary environmental impact<br />

statement, a climate change report and construction documents.<br />

1.5 Project Schedule<br />

1.5.1 The <strong>State</strong> of <strong>Yap</strong>, Department of Public Works and Transportation issued the<br />

Notice to Proceed (NTP) for the design services for this project was issued on<br />

December 9, 2009. The completion date is September 8, 2010.<br />

1.5.2 Work shall begin no later than twenty-one (21) calendar days from the issuance of<br />

the “Notice to Proceed”;<br />

1.5.3 35% submittal sixty (60) calendar days after commencement of work;<br />

1.5.4 60% submittal forty-five (45) calendar days after receipt of 35% review comments;<br />

LYON ASSOCIATES 1-2


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

1.5.5 90% submittal forty-five (45) calendar days after receipt of 60% review comments;<br />

and<br />

1.5.6 Final submittal thirty (30) calendar days after receipt of 90% review comments.<br />

LYON ASSOCIATES 1-3


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2 ENVIRONMENTAL SETTING OF PROJECT<br />

2.1 Geology<br />

2.1.1 <strong>Yap</strong> Islands are located in the western zone of Federated <strong>State</strong>s of Micronesia,<br />

and comprise four main islands: <strong>Yap</strong>, Map, Tomil, and Rumong. <strong>Yap</strong> Islands are<br />

composed mainly of accretional metamorphic rocks and volcanic rocks,<br />

accompanied by coral sand and mangrove mud. <strong>Yap</strong> Islands comprise an island<br />

arc system on the eastern convergent margin of Philippine Plate, connecting to the<br />

Palau island arc southward, and to Izu-Mariana arc northward. There are many<br />

Micronesia islands in the east of <strong>Yap</strong> islands, such as Ulithi, Woleai, Satawal and<br />

Ifalik, which are located in the Pacific Ocean plate region, and are oceanic<br />

volcanics or atolls developed on the descending volcano.<br />

2.1.2 Basement Rocks in the <strong>Yap</strong> Islands The geological map in Figure 2-1 is cited from<br />

(Johnson et al. 1960). The pre-Quaternary rocks are divided into <strong>Yap</strong> formation,<br />

Map formation, and Tomil volcanics in order of formation age (Tayama, 1935). The<br />

<strong>Yap</strong> formation constitutes the basement and is exposed all over the four islands.<br />

The <strong>Yap</strong> formation is composed mainly of greenschist and amphibolite of basalt<br />

origin.<br />

2.1.3<br />

Figure 2-1<br />

Geological Map of <strong>Yap</strong><br />

Source: Johnson et al., 1960<br />

2.1.4 The metamorphic grade increases eastward from greenschist facies (western<br />

coast of <strong>Yap</strong> island) to amphibolite facies (eastern coast of Tomil island). Among<br />

three island arcs; Izu-Mariana, <strong>Yap</strong> and Palau, the metamorphic rocks occur only<br />

on the <strong>Yap</strong> arc. Both tholeiite and calc-alkaline rock series common in island arc<br />

LYON ASSOCIATES 2-4


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

region are observed in the Palau arc, but no metamorphic rocks (Nedachi et al.,<br />

1996). The <strong>Yap</strong> formation is derived from melange trapped in the <strong>Yap</strong> trench.<br />

Ultramafic rocks intrude into the amphibolite. The rock is clinopyroxinite to olivine<br />

websterite, and the main rock-forming mineral is clinopyroxene, associated with<br />

olivine, orthopyroxene, plagioclase and magnetite. The rocks are not<br />

metamorphosed and the serpentinization is so weak.<br />

2.1.5 The Map formation postdates the <strong>Yap</strong> formation and is composed mainly of<br />

tectonic breccia with the fragments of metamorphic rocks of the <strong>Yap</strong> formation and<br />

other igneous rocks. Cole et al. (1960) described foraminifera in the sandstones<br />

and siltstones of Map formation, suggesting Miocene as the formation age.<br />

Johnson et al. (1960) thought that the igneous fragments in the Map formation<br />

were of Miocene melange, but the metamorphic grade of these fragments is far<br />

lower than that of the <strong>Yap</strong> formation. Even if the formation might be accretional<br />

member, the thrusting mechanism is different from that of the <strong>Yap</strong> formation.<br />

2.1.6 Previous workers have reported that the Tomil formation was deeply weathered.<br />

The was confirmed by Nedachi et al (1996) with strong and wide alteration by<br />

hydrothermal solution, although the rocks were overprinted by weathering. At<br />

almost all area of the four islands, we observed the network veins of hydrothermal<br />

argillization. Kaolinite is dominant, and in some places alunite can be detected.<br />

The fluid inclusions of quartz in the hydrothermal vein are homogenized at the<br />

temperature less than 200℃. Rytuba and Miller (1989) reported the gold<br />

mineralization at the northeastern end of the Tomil island, which might have been<br />

produced by a series of hydrothermal activity. The hydrothermal alteration play a<br />

role in accelerating the strong weathering, which differ slightly from ordinary<br />

laterite, characterized by the depletion of Fe2O3, Al2O3 and SiO2, and by soil<br />

poor in nutrients. These soil materials generally are not suitable for vegetation and<br />

agriculture, but kaolinite is used for ceramics. Hence a highly concentrated area of<br />

kaolinite might be a mineral resource.<br />

2.1.7 Island arcs along convergent boundary of plates often repeat to rise and escend.<br />

Then raised coral reefs are well developed in tropical and sub-tropical zone.<br />

However, it is a unique characteristic that there is no big raised coral reef nor big<br />

limestone in the <strong>Yap</strong> islands. Recent raised coral reef of small scale is observed in<br />

the offing, and 2 meters top of coral reef is exposed at low tide.<br />

2.1.8 Nedachi et al (1996) collected samples from the 35 sites in the lagoon, also<br />

included measurement of temperature of sea water, pH, Eh, content of dissolved<br />

oxygen, dielectric constant and salinity. In the laboratory, heavy minerals and clay<br />

minerals were analyzed using X-ray Diffraction, and sulfur isotopic composition<br />

were measured by VG optima isotope ratio mass spectrometer. Based on field<br />

observations, the results are as follows:<br />

2.1.9 The detrital material transported from the land area is not so abundant. Mangrove<br />

forest could have played an important role in precipitating detrital material from the<br />

land area. Almost all fragments from the outer zone of the lagoon are coral<br />

materials. The intense deposition of fragments from basement rock is observed in<br />

some places. Rather deep (20-50m) sea floor of small hollow lagoon near the<br />

western coast of the <strong>Yap</strong> island is occupied by thick mud layer transported from<br />

basement rock. The reason might be that the transportation by the current of<br />

seawater is very low, and that large fragments may not have been transported<br />

from both land and reef. On the other hand, pebble, granule and sand are<br />

predominant in the channels near Colonia harbor, and man-made channel<br />

LYON ASSOCIATES 2-5


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

between <strong>Yap</strong> and Tomil islands. The amount of organic material increases in the<br />

channel closest to the coast. Even in the channel near the coast, the activity of<br />

sulfate reducing bacteria is not so strong, and there is no stench of hydrogen<br />

sulfide. Under the microscope, framboidal pyrite can be observed in the mud<br />

samples in the channel near the coast.<br />

2.1.10 Clay mineral assemblage of sediments reflects directly the geology in the land<br />

area. Chlorite and smectite are predominant in the surrounding lagoon of the <strong>Yap</strong><br />

and Map formations, and kaolinite and gibbsite are frequently recognized around<br />

the Tomil volcanics. The sediments contain sulfur up to about 6000ppm. The<br />

sulfur isotopic ratios were measured and decreases with increasing S content of<br />

the sediment. The relationship between the sulfur isotope and S content suggests<br />

that S is fixed by bioactivity; sulfate reducing bacteria, as pyrite in detrital<br />

sediments.<br />

2.1.11 On the other hand, the values of coral sand are similar to that of sea water.<br />

Although we could not confirm the S species in the coral sediments, it can be<br />

pointed that sulfate reducing bacteria do not survive in the reef zone and coral<br />

sand. Clearly sediments in the channel near the coast line show lower sulfur<br />

isotopic ratio value, due to biogenic pyrite. Notably, the chlorite-smectite-organic<br />

matter mud in the small depression on coral near Tageegiin Village. The S content<br />

is 6100ppm.<br />

2.1.12 Although the content of dissolved oxygen of sea water is not low, the bottom of the<br />

hollow might be suitable reducing environment for sulfate reducing bacteria to<br />

survive actively. Since the human population is low, the natural environments<br />

might be suitable for bioactivity. Low sulfur isotope values are also obtained from<br />

the channel near Keeng and Makai, and the southern entrance of artificial channel<br />

between <strong>Yap</strong> and Tomil islands. Many people are living near these areas, and the<br />

sediments contain abundant organic matters, which maintain the reducing<br />

environment. The sulfur isotope value and S content might be good indicator of<br />

impact caused by human activity. On the other hand, sulfate reducing bacteria<br />

does not survive in the outer zone of the lagoon.<br />

2.1.13 In summary the <strong>Yap</strong> islands are composed mainly of metamorphic rocks of<br />

greenschist to amphibolite derived from oceanic tholeiite, and a lack of raised coral<br />

reef. These geological features might be related to the slow ascending history of<br />

<strong>Yap</strong> island arc system. Strong hydrothermal alteration is observed everywhere,<br />

and might have played a role in producing poor soils for vegetation or for other<br />

agriculture. However kaolinite might become a useful resource for ceramics if high<br />

concentration areas would be discovered. Sulfur isotopic ratio might be useful to<br />

evaluate the natural environment, or to determine the anthropogenic impact on the<br />

environment.<br />

2.2 Physical Features<br />

2.2.1 <strong>Yap</strong> <strong>State</strong> consists of 134 islands and atolls of which 22 are populated, stretching<br />

across more than 100,000 square miles of total area. The main island of <strong>Yap</strong> is<br />

made up of four high volcanic islands and accounts for 38 % of <strong>Yap</strong>’s total 49.7<br />

square miles of land area. Colonia, the <strong>State</strong>'s Capital and commercial center is<br />

located here. Most of the outer islands, stretching nearly 600 miles east of <strong>Yap</strong><br />

Island, are coral atolls.<br />

LYON ASSOCIATES 2-6


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.2.2 The landscape consists of rolling hills and lowlands covered with thick jungle like<br />

vegetation. Most of the coastal areas are mangroves with occasional coral<br />

beaches.<br />

2.2.3 Mangrove forest occurs widely around the coasts of all four of the main islands,<br />

and is especially well developed on mudflats at the mouths of drainage systems.<br />

Sheltered coasts and embayments support broad continuous belts of mangrove<br />

150-450 m wide, but along exposed shorelines, the mangrove stands become<br />

much narrower and discontinuous. The largest stands are found in Munguuy Bay<br />

and Yunearawey Passage between Maap and Tamil-Gagil, near Gachpar on the<br />

southeast coast of Tamil-Gagil, around the inner margin of Qatliirow Embayment<br />

and in the northern portion of the Tagireeng Canal between Tamil-Gagil and <strong>Yap</strong><br />

Proper, along the east coast of <strong>Yap</strong> Proper from Peelaek Channel south to<br />

Dechumur village, and along the west coast of <strong>Yap</strong> Proper between the villages of<br />

Qokaaw and Raeng. A continuous belt of mangroves, on average about 450 m<br />

wide, lines almost the entire coastline of southeastern <strong>Yap</strong> Proper, and is most<br />

extensive between the villages of Yinuuf and Luweech, where it penetrates 1.5 km<br />

inland. The mean tidal variation in <strong>Yap</strong> is 0.9 m.<br />

2.3 Climate<br />

2.3.1 The climate is humid tropical with an average annual rainfall of 3,087 mm (122<br />

inches) and a mean annual temperature of 27 o C (81 o F) . Relative humidity ranges<br />

from 65 to 100 percent, with an annual average of 83 percent.<br />

2.3.2 A season of trade winds and drought extends from December to April. The wet<br />

season, between July and October, accounts for about half of the annual rainfall.<br />

Typhoons are especially prevalent in May-June and November. The average<br />

number of typhoons is three per year and severe storms can wreak massive<br />

devastation in the Outer Islands .<br />

2.3.3 A seasonal summary of precipitation data from Station number 914951<br />

for <strong>Yap</strong> Island Weather Service Office (WSO) at the airport is presented<br />

below in Table 2-1.<br />

Table 2-1 Seasonal Precipitation Summary from 1953 to 2006<br />

>= >= >= >=<br />

Mean High Year Low Year 1 Day Max.<br />

0.01<br />

in.<br />

0.10<br />

in.<br />

0.50<br />

in.<br />

1.00<br />

in.<br />

in. in. - in. - in. Date # Days<br />

Annual 121.99 164.24 1996 88.84 1983 13.17 19820621 257 171 73 35<br />

Winter 23.11 50.16 1997 8.28 1973 8.96 19580114 61 35 13 6<br />

Spring 21.19 39.41 1999 3.16 1998 9.09 19670509 56 33 12 5<br />

Summer 42.52 69.6 2002 25.27 1995 13.17 19820621 72 53 26 13<br />

Fall 35.17 50.72 2003 21.62 1994 8.91 19601130 68 49 22 10<br />

Source Western Regional Climate Center mailto:wrcc@dri.edu<br />

LYON ASSOCIATES 2-7


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.3.4 A monthly summary of precipitation data from Station number 914951<br />

for <strong>Yap</strong> Island Weather Service Office (WSO) at the airport is presented<br />

below in Table 2-2.<br />

Table 2-2 Monthly Precipitation Summary from 1953 to 2006<br />

>= >= >= >=<br />

Mean High Year Low Year 1 Day Max.<br />

0.01<br />

in.<br />

0.10<br />

in.<br />

0.50<br />

in.<br />

1.00<br />

in.<br />

in. in. - in. - in. Date # Days<br />

Jan 7.76 23.08 1955 1.25 1983 8.96 14/1958 21 12 4 2<br />

Feb 5.63 13.36 1962 0.27 1983 5.77 8/1/62 18 9 3 1<br />

Mar 5.87 14.21 1972 0.54 1998 5.09 1/1/63 18 9 3 2<br />

April 6.06 18.15 1956 0.21 1998 6 3/1/67 18 10 3 1<br />

May 9.25 22.14 2003 1.47 1993 9.09 9/1/67 21 14 6 2<br />

June 12.63 32.01 1982 4.69 1959 13.17 21/1982 24 17 8 4<br />

July 14.77 34.71 1969 6.51 1953 8.79 18/2003 24 18 9 4<br />

Aug 15.12 29.44 1953 5.13 1973 6.69 28/1987 24 18 9 5<br />

Sept 13.28 21.16 1996 6.41 1984 6.85 14/1978 23 17 8 4<br />

Oct 12.22 22.43 1992 2.59 1976 5.5 8/1/89 23 17 8 4<br />

Nov 9.68 20.66 1960 1.96 1957 8.91 30/1960 23 15 6 2<br />

Dec 9.73 26.89 1996 2.22 1990 5.67 24/1996 22 14 6 3<br />

Source Western Regional Climate Center mailto:wrcc@dri.edu<br />

2.4 Soils & Drainage<br />

2.4.1 According the soils map in Figure 2-2 upland soils underlain by volcanic materials<br />

(areas 1 & 3), upland soils underlain by shist (areas 4 & 5) and soils on bottom<br />

lands (areas 6, 8 &10).<br />

2.4.2 Tropical climate causes rapid rock weathering that results in subgrade materials<br />

that are very high in clays. Such materials alone are low in bearing strength and<br />

are inadequate for even light-use traffic. Therefore, ballast and/or surfacing is<br />

required to prevent rutting and to maintain trafficability. This is especially true on<br />

<strong>Yap</strong> where the bedrock consists of weathered sedimentary rocks. By far the most<br />

serious and pervasive erosion problems exist on the secondary roads. Such roads<br />

are developed by individuals. Lack of knowledge about proper road construction<br />

practices the desire to minimize costs, and problems with land ownership often<br />

lead to serious erosion problems. We saw numerous examples where road grades<br />

were too steep for the type of road construction used. Landholders were<br />

constructing roads straight up the slope to minimize construction costs or to avoid<br />

problems with land ownership. In general, subgrade and surfacing procedures on<br />

the arterial roads appear to be appropriate for the intended road uses in the FSM<br />

states. On <strong>Yap</strong>, a chemical treatment called Condor SS is being used to stabilize<br />

the subgrade. This is overlain with crushed rock aggregate which is covered with a<br />

rubberized asphalt surface. (Ziemer & Megahan 1991).<br />

2.4.3 Ziemer (1991) states that a major part of the problem on secondary roads is the<br />

direct result of the lack of subgrade stability. Use of normal practices to construct<br />

stable subgrades is not practical on these roads because of high costs. However,<br />

the chemical stabilization techniques presently being used on the arterial road in<br />

LYON ASSOCIATES 2-8


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

<strong>Yap</strong> may be effective on secondary roads. We suggest that controlled tests of the<br />

Condor SS material be attempted on secondary roads on <strong>Yap</strong>. Trials of this<br />

material may also be appropriate in the other FSM states. However, such trials<br />

should be done in cooperation with the manufacturer because of possible<br />

problems caused by the volcanic parent materials. Escobar (1984) provides<br />

background information on the use, costs, and application of Condor SS. Condor<br />

SS is a mixture of ion exchange resins and sulfuric and sulfonic acids that is<br />

designed to remove the water of hydration from subgrade clays. This allows the<br />

subgrade to be compacted to a dense, highly stable state. The mixture is applied<br />

by ripping and sprinkling or by injection into the subgrade, followed by compaction<br />

with a vibrating roller (Escobar, 1984). The material is extremely acidic (pH 1.25)<br />

so care should be used to avoid spills and to prevent overland flow runoff from<br />

treated areas immediately after application. The injection procedure minimizes the<br />

opportunity for offsite pollution and is recommended for that reason.<br />

2.4.4 The inherent strength of slopes in the FSM is relatively low because of the high<br />

weathering of the bedrock that has occurred. Ziemer (1991) did see a few areas<br />

where small slope failures (landslides) had occurred on large cut slopes on the<br />

arterial roads in <strong>Yap</strong> and in Kosrae. The report continues to state that better<br />

design of dump areas for excess fill materials on <strong>Yap</strong> could have avoided some<br />

excessive erosion problems. In areas of lagoon encroachment on all states,<br />

considerable direct supply of sediments to the lagoon could be avoided by the<br />

proper installation of filter curtains to contain sediments.<br />

2.4.5 Ziemer (1969) saw a number of sites where slope protection measures were<br />

needed to help reduce both surface, and sometimes, mass erosion hazards. A<br />

variety of practices are available to accomplish this (FAO chapter 5, p. 148-166).<br />

Natural revegetation occurs rapidly in the FSM and is very effective for erosion<br />

control, but short-term measures are often needed to protect disturbed soils before<br />

natural revegetation occurs. This is especially true in areas where the potential for<br />

downslope delivery of water and sediments is high. Transplanting woody<br />

vegetation and use of various types of mulches are effective for accomplishing<br />

this.<br />

2.4.6 As a general rule, Ziemer ( recommends bridges at all channel crossings on<br />

arterial roads rather than culverts in order to minimize the possibility of clogging by<br />

debris. Channel crossings should be designed to carry at least the 25-year flow<br />

event for a given design life and chance of failure (FAO, 1989 -- p. 99).<br />

2.4.7 The soil map legend is presented in Figure 2-3. The green area represent soils on<br />

bottom lands. They are characteristically deep poorly drained soils.<br />

LYON ASSOCIATES 2-9


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Figure 2-2<br />

Soil Map of Project Region<br />

Source U.S Dept of Agriculture, Compiled in 1981<br />

LYON ASSOCIATES 2-10


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Figure 2-3<br />

Soil Map Legend<br />

Source U.S Dept of Agriculture, Compiled in 1981<br />

LYON ASSOCIATES 2-11


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.5 Wetlands<br />

2.5.1 Only these four islands possess significant wetlands, although there are some<br />

unusual stands of mangrove in the interior lagoons of some of the outer atolls.<br />

Much the most extensive wetland type is mangrove forest, which covers about<br />

1,171 ha or approximately 32.2% of the total forested area of <strong>Yap</strong>.<br />

2.5.2 Other types of wetland are very limited in extent. There are a few small saline<br />

marshes, generally along the coast adjacent to mangroves. Small stands of<br />

swamp forest occur in low wet areas just inland of mangroves (above tidal<br />

influence), in low areas along streams and in areas of impeded drainage. Many<br />

areas which probably once supported swamp forest have been converted into taro<br />

patches, and the remaining forests are now heavily disturbed, with about 85% of<br />

the forest containing secondary vegetation or agro-forest inclusions. There are<br />

also a number of small freshwater marshes in water-logged areas slightly above<br />

sea level landward of the mangroves and in depressions in upland areas. Other<br />

wetlands include a number of streams, most of which are intermittent, several<br />

small ponds, a small water storage reservoir near the capital, Colonia, and<br />

numerous small taro patches. Only one of the ponds, Machbaab Pond near the old<br />

airport in southern <strong>Yap</strong>, is permanent.<br />

2.5.3 The mangrove forest dominated by Rhizophora mucronata occurs in a broken<br />

band of variable width around all four of the main islands of <strong>Yap</strong> <strong>State</strong> and forms<br />

extensive stands in sheltered embayments.<br />

2.6 Forests<br />

2.6.1 The mangrove forests of <strong>Yap</strong> are more diverse than those of Chuuk, Pohnpei and<br />

Kosrae, and include three species which are not known to occur on the other<br />

islands Schypiphora hydrophyllacea, Ceriops tagal and Dolichandrone spathacea.<br />

The most conspicuous species in the mangrove forests are Rhizophora<br />

mucronata, R. apiculata, Bruguiera gymnorrhiza and Sonneratia alba. Rhizophora<br />

mucronata is dominant along the seaward fringe, with R. apiculata occurring<br />

behind this fringe in areas where the forest is fairly wide. Sonneratia alba becomes<br />

common along channels and towards the leeward edge of the mangrove forest,<br />

while Bruguiera gymnorrhiza and Xylocarpus granatum tend to dominate along the<br />

landward edge of the mangrove. Other species which generally occur along the<br />

landward edge of the mangrove forests are Lumnitzera littorea, Ceriops tagal and<br />

Dolichandrone spathacea. Nypa fruticans is generally found in the more brackish<br />

areas, in narrow bands along the margins of channels (Falanruw et al., 1987b).<br />

2.6.2 Species characteristic of swamp forest adjacent to mangrove forest include<br />

Dolichandrone spathacea, Heritiera littoralis, Pongamia pinnata, Cynometra<br />

ramiflora, Dalbergia candenatensis, Derris trifoliata and Acrostichum aureum. A<br />

few almost pure stands of Dolichandrone spathacea can be found, and<br />

Barringtonia racemosa is common in wetter areas. In the of swamp forests along<br />

streams and in wet inland depressions, characteristic tree species include<br />

Barringtonia racemosa, Hibiscus tiliaceus, Semecarpus venenosus, Inocarpus<br />

fagifer, Ficus tinctoria, Pandanus japensis, Cerbera manghas, Ixorea casei and<br />

Derris elliptica (Falanruw et al., 1987b).<br />

2.6.3 The plant community of the saline marshes includes Acrostichum aureum, Cyperus<br />

javanicus, Eleocharis geniculata, Fimbristylis cymosa, Paspalum distichum,<br />

LYON ASSOCIATES 2-12


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Ipomoea pes-caprae, Excoecaria agallocha, Derris trifoliata and Clerodendron<br />

inerme (Stemmermann & Proby, 1978). The vegetation of the freshwater marshes<br />

may consist of tall reeds, especially Phragmites karka, sedges, and herbaceous<br />

species such as Ludwigia hyssopifolia, L. octovalvis and Hanguana malayana<br />

(Falanruw et al., 1987b). Most of the ponds are in open savannah and support<br />

considerable rooted vegetation, including emergent species, such as Eleocharis<br />

ochrostachys, Eriocaulon sexangulare and Ischaemum polystachum, and the<br />

submerged species Blyxa sp. I. polystachum dominates the stream flora in open<br />

areas and mosses are common in cascades, but rooted vegetation is very<br />

restricted (Lobban et al., 1990). Lobban et al. (1990) collected periphyton and<br />

other visible algae from the streams and ponds, and found 12 blue-green algae,<br />

two red algae, two charophytes, seven genera of filamentous green algae and five<br />

flagellates. No endemic species were found, and it was concluded that the<br />

freshwater algal flora of the <strong>Yap</strong> Islands did not show characteristics of the biota of<br />

"oceanic" islands.<br />

2.6.4 The four main islands of <strong>Yap</strong> have long been densely populated, and most natural<br />

terrestrial ecosystems have been extensively modified, with reduction in species<br />

diversity and degradation of forests to savanna grasslands or conversion to agroforests.<br />

2.7 Noteworthy Fauna<br />

2.7.1 The mangrove forests provide habitat for a wide variety of marine organisms as<br />

well as many birds and fruit bats. They provide shelter and feeding habitat for reef<br />

fish, the most conspicuous families being Chaetodontidae (butterfly fish),<br />

Lutjanidae (snappers), Apogonidae (cardinal fish), Acanthuridae (surgeon fish),<br />

Siganidae (rabbit fish), Pomacentridae (damsel fish), Gobidae (gobies) and<br />

Gerreidae (mojarras). Gastropods such as the periwinkle Littorina scabra, the<br />

cerithiid Clypeomorus pellucida and the muricid snails Naquetia capucina and<br />

Thais aculeata are common, as are land crabs (Cardisoma sp.) and mangrove<br />

crabs (Scylla serrata) (U.S. Army Corps of Engineers, Pacific Ocean Division,<br />

1989b).<br />

2.7.2 The pond and stream fauna includes at least 50 species of aquatic insects, eight<br />

species of decapod crustacean, and 14 species of gastropods (Nelson, 1989). The<br />

most abundant fishes in the stream environments are the eleotrids Eleotris fuscus<br />

and Ophieleotris aporos, and the freshwater eel Anguilla marmorata. Other stream<br />

fishes include the mudskipper Periophthalmus vulgaris, the flagtail perch Kuhlia<br />

rupestris and the spotted scat Scatophagus argus. The introduced tilapia<br />

Oreochromis mossambicus, which escaped from an aquaculture project in the<br />

1970s, is now well established and is abundant in some of the freshwater ponds,<br />

streams and estuarine habitats (Nelson & Hopper, in Nelson, 1989).<br />

2.7.3 There are only three resident species of waterbirds on <strong>Yap</strong>; the Yellow Bittern<br />

(Ixobrychus sinensis), Pacific Reef Heron (Egretta sacra) and White-browed Crake<br />

(Porzana cinerea). The Yellow Bittern is particularly common, occurring in a wide<br />

variety of wet habitats. Situated only 1,300 km east of Mindanao in the Philippines<br />

and only 1,250 km north of western Irian Jaya, <strong>Yap</strong> lies sufficiently close to the<br />

continental island systems of eastern Asia to serve as a staging area for significant<br />

numbers of migratory shorebirds using the East Asian/Australasian flyway. Twentysix<br />

species of shorebirds have been recorded, and at least 12 of these are fairly<br />

common on migration and/or in winter. These are Pacific Golden Plover (Pluvialis<br />

LYON ASSOCIATES 2-13


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

fulva), Mongolian Plover (Charadrius mongolus), Greenshank (Tringa nebularia),<br />

Wood Sandpiper (T. glareola), Wandering Tattler (Heteroscelus incanus), Greytailed<br />

Tattler (H. brevipes), Common Sandpiper (Actitis hypoleucos), Whimbrel<br />

(Numenius phaeopus), Ruddy Turnstone (Arenaria interpres), Sanderling (Calidris<br />

alba), Rufous-necked Stint (C. ruficollis) and Sharp-tailed Sandpiper (C.<br />

acuminata) (Pratt et al., 1987). At least 175 shorebirds of 17 species were<br />

recorded during a brief survey of two islands in early September 1990 (D.A. Scott,<br />

unpublished). Other migratory waterbirds from eastern Asia which have been<br />

recorded on the islands include four species of herons and egrets, two ducks and<br />

the Whiskered Tern (Chlidonias hybrida).<br />

2.7.4 The only indigenous mammal is the Marianas Fruit Bat (Pteropus mariannus),<br />

which frequently forages in the mangrove and swamp forests. Two endemic<br />

subspecies occur in <strong>Yap</strong> P. m. yapensis on the main islands and P. m. ulithiensis<br />

on Ulithi atoll.<br />

2.8 Noteworthy Flora<br />

2.8.1 Most of the mangrove forests are still in relatively pristine condition. Mangrove<br />

species include seven species shared with the other islands of FSM Rhizophora<br />

mucronata, R. apiculata, Bruguiera gymnorrhiza, Xylocarpus granatum, Lumnitzera<br />

littorea, Nypa fruticans and Sonneratia alba, and three species of more westerly<br />

distribution Schypiphora hydrophyllacea, Ceriops tagal and Dolichandrone<br />

spathacea.<br />

2.8.2 The U.S. Forest Service has carried out a vegetation survey of <strong>Yap</strong> in cooperation<br />

with the <strong>State</strong> <strong>Government</strong> (Falanruw et al., 1987b). Detailed studies of <strong>Yap</strong>'s<br />

inland aquatic habitats were carried out by a team of aquatic biologists from the<br />

University of Guam Marine Laboratory, <strong>Yap</strong> <strong>State</strong> Department of Natural<br />

Resources and the College of Micronesia in 1988. The limn logical characteristics<br />

of the streams and ponds, the vegetation and the freshwater fishes, aquatic<br />

insects, decapod crustaceans and freshwater gastropods were investigated<br />

(Nelson, 1989). Lobban et al. (1990) have described the periphyton of <strong>Yap</strong>,<br />

excluding the diatoms and desmids.<br />

2.9 Land Use<br />

2.9.1 No conventional protected areas have been established on <strong>Yap</strong>. However, in the<br />

past, the use of land and marine resources, including mangroves, was traditionally<br />

subject to many regulations and restrictions. A complex system of ownership and<br />

rights of usage established limitations and helped to prevent over-exploitation<br />

(Yinug et al., 1989). There has been some replanting of mangroves in Nimpal<br />

Embayment on the west coast of <strong>Yap</strong> Proper to protect fishing grounds from<br />

salutation caused by construction work.<br />

2.9.2 <strong>Yap</strong> <strong>State</strong> Marine Resources Management Division is working on a Marine<br />

Resources and Coastal Management Plan incorporating traditional customs and<br />

laws (IUCN, 1991). This is likely to include recommendations for the protection of<br />

specific areas.<br />

2.9.3 The overall land area in the FSM is about 271 square miles. Pohnpei had the<br />

largest land area followed by Chuuk, <strong>Yap</strong> and then Kosrae. In 2001 , about 68 %<br />

LYON ASSOCIATES 2-14


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

of the land in FSM was privately owned. As depicted in Figure 2-3 below, <strong>Yap</strong> has<br />

the least amount of privately owned land.<br />

Figure 2-4<br />

Percentage of Land Ownership by <strong>State</strong>:2001<br />

Source Statistical Yearbook FSM 2007<br />

2.10 Population<br />

2.10.1 The total population of <strong>Yap</strong> state, based on the 2000 Census data, stands at<br />

11,241 which is a 0.6% increase over the 1994 data. The <strong>Yap</strong> population<br />

comprises 10.5% of the total population of the Federated <strong>State</strong>s of Micronesia.<br />

The median age for <strong>Yap</strong> is 20.9 years and is the highest median age among the<br />

fours states and comparatively higher that the median age of the FSM, which is 19<br />

years. The age distribution of the population in <strong>Yap</strong> is presented in Figure 2-5. It<br />

graphically shows the age distribution. Approximately 48% of the population is<br />

under 20 years of age (5,438 persons); there are 2,775 women between 15-44<br />

years of age, the child-bearing years which is 48% of the total female population.<br />

2.10.2 Table 2-1 presents the population distribution among the FSM islands. Based on<br />

the 2000 Census data <strong>Yap</strong> <strong>State</strong> has less than 11% of the FSM population.<br />

Furthermore <strong>Yap</strong> Proper contains 52% (5,870 persons) of the population of <strong>Yap</strong><br />

<strong>State</strong>. Table 2-1 also shows the change in population from 1930 and its relation to<br />

other FSM states.<br />

LYON ASSOCIATES 2-15


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Table 2-3 Population Distribution: 1930 to 2009<br />

Source: FSM Office of Statistics<br />

2.10.3 Figure 2-5 graphically presents the age distribution in <strong>Yap</strong> <strong>State</strong>. It is<br />

characterized by the large percentage of youth under 20 years of age.<br />

Figure 2-5<br />

<strong>Yap</strong> <strong>State</strong> Population Distribution by Age<br />

Source Statistical Yearbook FSM 2007 Table 2.5<br />

LYON ASSOCIATES 2-16


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.11 Economic Issues<br />

2.11.1 The four main islands are densely populated, with the 10,000 inhabitants living in<br />

over 100 villages. A subsistence lifestyle dominates; fishing is important and<br />

tourism is still a relatively minor industry. The mangrove forests are widely utilized<br />

for construction materials, wood for handicrafts, firewood and fishing, and land<br />

crabs and mangrove crabs are harvested in large numbers in some areas. In most<br />

areas, the cutting of mangrove for local building projects continues on a small<br />

scale as it has done for centuries, but in one area south of Peelaek Channel, there<br />

has been some commercial logging. Many of the freshwater swamp forests and<br />

marshes have been converted to taro fields (Colocasia esculenta and Cyrtosperma<br />

chamissonis), and in recent years, shallow ponds have also been used for the<br />

cultivation of the introduced aquatic plant Ipomoea aquatica (Nelson, 1989).<br />

2.11.2 Transportation on <strong>Yap</strong> Proper is becoming easier because of the development and<br />

improvement of paved roads; however, there are clusters of villages that are still<br />

difficult to access because of unpaved dirt roads. The outer islands are also<br />

difficult to reach because of the infrequent cargo ships. The regular field trip on the<br />

ship takes place once a month to each of the outer islands bringing supplies and<br />

health personnel to deliver goods and services.<br />

2.11.3 In the <strong>State</strong> of <strong>Yap</strong>, in the 2000 census, of the 2,030 households, 1,578 reported<br />

some cash income with a median household income of approximately $6,484 and<br />

a mean household income of $10,344. By region, the median household income<br />

was $7,299 in <strong>Yap</strong> Proper and about $4,242 in the outer islands. During this<br />

reporting year, over 50% of the population aged 15 years and over reported<br />

receiving cash income. These 3,254 income recipients represented 62% of the<br />

5,174 persons in the working age population. The median individual income for<br />

<strong>Yap</strong> was $3,368 with individual income on <strong>Yap</strong> Proper higher that income in the<br />

outer islands. Out of the total 2,030 households in FSM, 77% (1,578) reported<br />

having cash income with an average income of $10,344 and a median income of<br />

$6,489. This represents half of a percent (.5%) increase from the 1994 Census.<br />

However, there is still a disparity of income level among the <strong>Yap</strong> proper population<br />

and the outer island population. The average household income in <strong>Yap</strong> proper is<br />

$11,462 with a median income of $7,299 where as in the outer islands the average<br />

household income is $4,900 with a median income of $4,242<br />

2.11.4 Table 2-1 presents employment in <strong>Yap</strong> <strong>State</strong> from 2002 to 2006. Overall<br />

employment dipped in 2006 from its high in 2003 due to the closing of garment<br />

factories. <strong>Government</strong> employment peaked in 2005 and then fell in 2006 due to<br />

federal funding for the recovery efforts for Typhoon Sudal.<br />

Table 2-4 Total Employment by Sector: FY 2002 to FY 2006<br />

Source <strong>Yap</strong> <strong>State</strong> Annual Statistical Yearbook 2007 Table 4.1<br />

LYON ASSOCIATES 2-17


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.11.5 <strong>Yap</strong> generally shows a increase of agriculture produce by local markets between<br />

1997 to 2006 as shown below in Figure 2-6. The unusually high value were the<br />

result of banana and papaya export.<br />

Figure 2-6 Dollar Value of Local Markets' Purchases of<br />

Agricultural Products by <strong>State</strong><br />

Source Statistical Yearbook FSM 2007<br />

Figure 2-7 Copra Production by Volume (Tons), FSM: 1997 to 2006<br />

Source Statistical Yearbook FSM 2007<br />

LYON ASSOCIATES 2-18


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.11.6 Figure 2-7 shows that <strong>Yap</strong> and Pohnpei were the major copra producers in the<br />

years before 2001.<br />

2.11.7 The decline in <strong>Yap</strong> production is subsequent years resulted from natural disasters.<br />

In 2006, <strong>Yap</strong> and Pohnpei continued to be the only copra producers, <strong>Yap</strong><br />

produced 50 tons. The staple foods of the island are taro, yam, breadfruit, sweet<br />

potatoes, and coconut. The main sources of protein are fish, crabs, clams, and<br />

pork.<br />

2.11.8 The FSM annual inflation rate of the fourth quarter 2006 was 4.9%, which was a<br />

one percent increase from the same quarter in 2005. Figure 2-8 shows the steady<br />

decline in the annual inflation rates by quarter in <strong>Yap</strong>. The decrease is generally<br />

attributed to the lower prices of alcohol, tobacco, sakau, betel nut, fuel and utilities<br />

(e.g. electricity and water).<br />

Figure 2-8 Annual Inflation Rates: 4th Qtr 2004 to 4th Qtr 2006<br />

Source Statistical Yearbook FSM 2007<br />

2.11.9 In ten years from 1997 to 2006 registered motor vehicles increased 31 % in <strong>Yap</strong><br />

<strong>State</strong>, from 1,323 to 1,739. As presented in Table 2-3, sedans increased by 56%<br />

and pick-ups decreased by 34 for the same ten year period. In 2006 <strong>Yap</strong> <strong>State</strong><br />

had 21 % of the total motor vehicle registered in FSM. Pohnpei recorded 60%,<br />

Chuuk, 13% and Kosrae 9%.<br />

LYON ASSOCIATES 2-19


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Table 2-5<br />

Registered Motor Vehicles in <strong>Yap</strong><br />

1997 1998 1999 2000 2001 2002 2003 2004 2005 2006<br />

Sedan 485 605 612 644 633 605 685 701 803 759<br />

Pick-ups 453 514 526 415 394 374 369 328 327 297<br />

Jeep 54 36 38 38 38 36 108 104 64 71<br />

Station wag 72 105 112 125 126 134 138 149 158 164<br />

Vans 103 139 141 146 148 138 146 160 170 169<br />

Flatbed trk 51 66 61 58 52 49 60 61 70 78<br />

Dump truck 26 45 51 47 44 46 39 46 38 25<br />

Ambulance 2 3 3 2 1 2 3 2 3 3<br />

Fire truck 1 1 1 2 1 1 1 1 1 1<br />

Fuel tanker 3 5 5 3 3 2 3 4 2 2<br />

Bus 12 11 10 14 14 13 14 13 12 11<br />

Motorcycle 26 31 13 15 11 11 25 52 22 18<br />

Other 35 40 106 101 99 145 90 62 151 141<br />

TOTAL 1,323 1,601 1,679 1,610 1,564 1,556 1,681 1,683 1,821 1,739<br />

Source Statistical Yearbook FSM 2007<br />

2.11.10 Figure 2-9 shows that the number of registered motor vehicles in FSM peaked in at<br />

9,731 in 2003. In 2006, it dropped to 8,121.<br />

Figure 2-9 Registered Motor Vehicles is FSM: 1999-2006<br />

Source Statistical Yearbook FSM 2007<br />

LYON ASSOCIATES 2-20


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

2.11.11 According to Table 2-4, for the period of 2000 to 2008 the passenger counts from<br />

those arriving and departing <strong>Yap</strong>, the majority of the travel is due to foreigners.<br />

The majority of those traveling to <strong>Yap</strong> arrive and depart by airplane.<br />

Table 2-6 Passenger Arrivals and Departures on Foreign Aircraft<br />

and Vessels: 2000 to 2007<br />

Source <strong>Yap</strong> <strong>State</strong> Annual Statistical Yearbook 2007 Table 8.8<br />

2.11.12 FSM Telecommunications Corporation is the only telecommunication company that<br />

services all of the states in FSM. Figure 2-10 shows the recent growth and then<br />

decline of telephone, fax and internet services for the period from 1997 to 2006.<br />

LYON ASSOCIATES 2-21


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Figure 2-10 <strong>Yap</strong> Communication services: 1997 to 2006<br />

Source FSM Office of Statistics<br />

2.12 Cultural History<br />

2.12.1 There are four indigenous languages in <strong>Yap</strong>: <strong>Yap</strong>ese, Ulithian, Woleian, and<br />

Satawalese. English is the common language of the FSM and is commonly spoken<br />

and understood. Many elderly <strong>Yap</strong>ese are fluent in Japanese.<br />

2.12.2 <strong>Yap</strong>ese society is based on a highly complex caste system involving at least seven<br />

tiers of rank. Historically, the caste rank of an entire village could rise or fall in<br />

comparison to other villages depending on how it fared in inter-village conflicts.<br />

Winning villages would rise in rank while losing villages would have to accept<br />

decline in comparative rank. In many cases lower ranked villages were required to<br />

pay tribute to higher ranked villages. Dietary taboos might be imposed on lower<br />

ranking villages, i.e. they might be prohibited from harvesting and eating the more<br />

desirable fish and animals of the sea. Within each village each family had its own<br />

rank comparative to the others. Until the arrival of the German colonializers, the<br />

caste ranking system was fluid and the ranks of villages and families changed in<br />

response to inter-village intrigues and confrontations. In the late 19th century,<br />

however, the German colonial administration "pacified" <strong>Yap</strong> and enforced a<br />

prohibition against violent conflict. The caste rank of each village in modern <strong>Yap</strong><br />

thus remains the same as it was when the system was frozen in place by the<br />

Germans.<br />

2.12.3 <strong>Yap</strong> is notable for its stone money, known as Rai: large donut-shaped, carved<br />

disks of (usually) calcite, up to 12 ft (4 m) in diameter (most are much smaller). The<br />

smallest known one is only 3 inches in diameter. Many of them were brought from<br />

other islands, as far as New Guinea, but most came in ancient times from Palau.<br />

Their value is based on both the stone's size and its history. Historically the<br />

LYON ASSOCIATES 2-22


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

<strong>Yap</strong>ese valued the disks because of the difficulty and hazards involved in obtaining<br />

them. To quarry the stones, <strong>Yap</strong>ese adventurers had to sail to distant islands and<br />

deal with local inhabitants that were sometimes hostile. Once quarried, the disks<br />

had to be transported back to <strong>Yap</strong> via rafts towed behind wind-powered canoes.<br />

The scarcity of the disks, and the effort and peril required to obtain them, made<br />

them valuable to the <strong>Yap</strong>ese. However, in 1874, an enterprising Irishman named<br />

David O'Keefe hit upon the idea of employing the <strong>Yap</strong>ese to import more "money"<br />

in the form of shiploads of large stones, also from Palau. O'Keefe then traded<br />

these stones with the <strong>Yap</strong>ese for other commodities such as sea cucumbers and<br />

copra. Although some of the O'Keefe stones are larger than the canoe-transported<br />

stones, they are less valuable than the earlier stones due to the comparative ease<br />

in which they were obtained. Approximately 6,800 of them are scattered around<br />

the island. As no more disks are being produced or imported, this money supply is<br />

fixed (Washington Post, 1984). The islanders know who owns which piece, but do<br />

not necessarily move them<br />

2.12.4 <strong>Yap</strong> Proper (known as Wa'ab or Waqab) was initially settled by ancient migrants<br />

from the Malay Peninsula, the Indonesian Archipelago, New Guinea, and the<br />

Solomon Islands. The <strong>Yap</strong>ese language is related to the Malay languages of<br />

Southeast Asia, though with strong New Guinean influences. In contrast, the<br />

people of <strong>Yap</strong>'s outer islands are descendants of Polynesian settlers, and as such<br />

have significant ethnic dissimilarities from the people of <strong>Yap</strong> Proper. Their culture<br />

and languages (Ulithian and Woleaian) are closely related to those of the<br />

neighboring islands of Chuuk.<br />

2.12.5 <strong>Yap</strong> was under Spanish control from the late 17th century until sold to Germany in<br />

the late 19th century. Germany held the islands until they were seized by Japan in<br />

World War I. Despite protests by the United <strong>State</strong>s, the League of Nations<br />

mandated <strong>Yap</strong> to Japan after the war. The Japanese operated military bases here<br />

during World War II. The United <strong>State</strong>s took possession after the war, and in 1947<br />

<strong>Yap</strong> became part of the Trust Territory of the Pacific Islands under United <strong>State</strong>s<br />

administration. In 1986 <strong>Yap</strong> became part of the self-governing Federated <strong>State</strong>s of<br />

Micronesia.<br />

2.12.6 In summary the relationship between human activity and the environment is<br />

dynamic and complex. This setting of this project in this environment is no<br />

exception. The highlights of this section indicates a population, dollar value of<br />

local market purchases of agricultural products and registration of vehicles has<br />

increased in recent years. Employment, interstate and international travel, copra<br />

production by volume, the rate of annual inflation and communication services has<br />

fallen in recent years. These factors individually or combined have not driven the<br />

need for this project nor the scope of the project. The project will not significantly<br />

increase the capacity of this roadway but simply decrease the operations and<br />

maintenance cost and increase public safety and reliability in using the existing<br />

road. There is not a economic viable alternative for the people and vehicles that<br />

use this road. The characteristic and location of deep poorly drained soils, the<br />

frequency and height of storm surges and issues caused by drainage have<br />

contributed to the need for this project. The object of this project is to better<br />

understand and make improvements to the existing roadway and its environment.<br />

LYON ASSOCIATES 2-23


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

3 GENERAL DESCRIPTION OF PROJECT EFFECTS<br />

3.1 Problems with the Existing Road Segments<br />

3.1.1 Although the road from beginning of the project (BOP) at the hospital intersection<br />

with the main road to Keng to the end of the project (EOP) at the western edge of<br />

Tagireeng Bridge was constructed in the mid 1980s, the following problems have<br />

been sited:<br />

• The existing road surface is rubberized asphalt pavement . It has deteriorated<br />

in several segments of the road particularly along the shoreline. <strong>Yap</strong> <strong>State</strong> has<br />

replaced the asphalt pavement in these areas with portland concrete<br />

pavement.<br />

• The construction of this road segment changed the pre-existing drainage<br />

system resulting in changing upland forest into upland marshes and altering<br />

flow patterns to downstream both freshwater and saltwater wetland.<br />

3.1.2 The premature deterioration of the asphalt pavement can be attributed to three<br />

issues:<br />

• As the soil map of the project region depicts in Figure 2-2, the green area<br />

beneath this section of the road are characterized as deep poorly drained soils;<br />

• Segments of the road are subjected to flooding by storm surges; and<br />

• Segments of the road are subjected to flooding by stormwater runoff.<br />

3.1.3 The cause and effect mechanisms are two fold: the saturation of the road bed<br />

reduces the strength and bearing capacity; and secondly, the wheel loads provide<br />

energy to accelerate the water within the saturated road bed which forces<br />

structural changes and has the capacity to transport soil particles. This<br />

mechanism is often referred to as pumping. It creates voids which results in the<br />

reduction of support to the pavement.<br />

3.1.4 The water velocity caused by the flooding subjects it path to forces that can<br />

transport material. This process can both undermine the road by erosion or carry<br />

away the broken pieces of the asphalt pavement. As mentioned above both<br />

waves from storm surges and stormwater runoff provides velocity to the water.<br />

3.1.5 In summary the design of a road bed capacity to carry or support wheel loads is<br />

based on non-saturated strength of the material. The pavement is one of the ways<br />

to protect the road bed from being saturated. In overall drainage system is needed<br />

to assure the road be is not subjected to ponding along the road or raising the<br />

ground water level into the road bed,<br />

3.1.6 This project was commissioned by the <strong>State</strong> of <strong>Yap</strong>, Department of Public Works<br />

and Transportation in order to address these problems. The scope of work for this<br />

project encompasses this preliminary environmental impact statement, a climate<br />

change report and construction documents. A separate preliminary environmental<br />

impact statement is being prepared for the quarry (borrow) site and dredging site.<br />

3.1.7 The climate change report will focus on the reviewing the existing literature as it<br />

pertains to height and frequency of the sea level on the <strong>Yap</strong>'s shoreline. This will<br />

provide information to determine the most cost effective and environmentally<br />

sound elevation of the road along the shoreline.<br />

LYON ASSOCIATES 3-1


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

3.1.8 As part of the basis of design Lyon Associates will analyze and evaluate the<br />

drainage system that surrounds the road. This analysis and evaluation will also be<br />

presented in report form.<br />

Figure 3-1 shows the watershed map along the project.<br />

Figure 3-1<br />

Existing Watershed Map Along the Project<br />

Source: Drainage Assessment, Draft Lyon Associated 2010<br />

3.1.9 As a summary, the basis of design for the Northern <strong>Yap</strong> Improvements Project will<br />

encompass the findings of this preliminary environmental impact statement, the<br />

climate change report and the drainage assessment and the road design<br />

standards from the <strong>Yap</strong> <strong>State</strong> Department of Public Works and Transportation in<br />

order to recommend the most cost effective and environmentally sound<br />

improvements to the existing road.<br />

LYON ASSOCIATES 3-2


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

3.2 Disturbances and Threats to Wetlands<br />

3.2.1 Freshwater wetlands have been extensively modified for agricultural use, and<br />

some mangrove areas are threatened by uncontrolled harvesting of timber, filling<br />

to create land for houses and other development, and the dumping of rubbish and<br />

toxic materials. Some mangroves were destroyed by salutation during the<br />

construction of a new airport, but there has been some recovery since then. The<br />

construction of roads with too few drainage culverts has resulted in localized<br />

impoundment of mangroves, and the building of a solid causeway between Gagil-<br />

Tamil and Maap islands has resulted in the death of mangroves along part of the<br />

Yunearawey Passage. A small amount of commercial logging has been reported,<br />

but a proposal (with Taiwanese backing) to undertake commercial logging in the<br />

mangroves on a large scale has been rejected. At least two proposals to clear<br />

mangroves for aquaculture and a proposal to utilize mangrove wood as fuel to<br />

smoke fish have also been rejected, but a proposal to use mangrove areas as<br />

rubbish dumps is still under discussion. Oil spills and pesticides have had localized<br />

impact, although Mowbray (1988) has reported a leakage of endrin and sodium<br />

arsenite into a freshwater stream and coastal lagoon which caused a large-scale<br />

kill of fish, wildlife and domestic animals. The greatest threat to the sustainable use<br />

of mangrove forests and other natural resources in <strong>Yap</strong> is the removal of traditional<br />

limitations on their exploitation, generally as a result of new technologies, outside<br />

inputs and commercialized exploitation (Yinug et al., 1989).<br />

3.2.2 One of the objectives in the road improvement project is to analyze and evaluate<br />

the drainage system along the road. Where the existing road has significantly<br />

blocked or reduced stormwater runoff to areas downstream or significantly reduce<br />

salt water circulation to mangrove forest landward of the road, the design is<br />

intended to rectify this problems.<br />

3.3 Hydrological & Biophysical Values<br />

3.3.1 Mangroves serve as natural filtering and nutrient buffering systems between the<br />

islands and the adjacent fringing reefs, protecting the reefs from sedimentation and<br />

providing for a slow sustained release of nutrients. The mangrove forests afford<br />

some protection against storm damage, and may also be important in stabilizing<br />

the shoreline against erosion. They play a critical role as nursery habitat for larval<br />

and juvenile fishes and thereby help to maintain the coastal fishery.<br />

3.4 Road Improvement Construction<br />

3.4.1 The improvements to existing road although temporary has the potential to cause<br />

or effect the many possible environmental impacts. <strong>Yap</strong> <strong>State</strong> Environmental<br />

Protection Agency has promulgated regulations requiring this preliminary<br />

environmental impact statement. They have provided an initial environmental<br />

Assessment checklist in appendix A of the regulations. This check list will be<br />

addressed in the following section of this report.<br />

LYON ASSOCIATES 3-3


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

4 POSSIBLE ENVIRONMENTAL IMPACT CHECKLIST<br />

4.1 Initial Environmental Assessment Checklist<br />

4.1.1 The content of this checklist is was taken form Appendix A. The questions of the<br />

checklist are present in italic font larger than the normal font.<br />

4.2 Earth- Will the proposed project result in:<br />

4.2.1 Destruction, covering or modification of any unique geologic or<br />

physical features? No. The project is to make improvements to the existing<br />

road.<br />

4.2.2 Creation of steep slopes or other unstable earth conditions? No. Any<br />

new slopes will be designed in accordance to the geotechnical report for the<br />

project. The recommend slope design will not exceed the ratio of 1 vertical to 2<br />

horizontal. BMPs shall be incorporated into the design documents e.g. Seeding of<br />

grasses and plantings of trees, shrubs, vines and ground covers provide longterm<br />

stabilization of soil. The type of vegetation, site and seedbed preparation, planting<br />

time, fertilization and water requirements will be specified for each application.<br />

Mattings may also be designated on disturbed soils and where existing vegetation<br />

has been removed. The following organic matting materials provide temporary<br />

protection until permanent vegetation is established, or when seasonal<br />

circumstances dictate the need for temporary stabilization until weather or<br />

construction delays are resolved: Jute or straw mattings. The following synthetic<br />

mattings may be used for either temporary or post-construction stabilization, both<br />

with and without vegetation: Excelsior matting, Glass fiber matting, Staples and<br />

Mulch nettings. Note that the seeding procedure will be included in the<br />

specifications.<br />

Figure 4-1<br />

Slope Stabilization Matting<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

4.2.3 Any potential for increase wind or water erosion of soils, either on of<br />

the site? Yes. The temporary construction activities will generate dust and loosen<br />

LYON ASSOCIATES 4-4


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

soil and pavement particles. The construction plans and specifications will include<br />

best management practices (BMPs) such as filter curtains to mitigate sediment<br />

transport into the water ways and silt fencing and/or using watering trucks for dust<br />

control. The design documents will include mulching to temporarily and<br />

permanently stabilize cleared or freshly seeded areas. Note the filter curtain will be<br />

included in the project specifications.<br />

Figure 4-2<br />

Slope Stabilization with Mulching<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

4.2.4 Changes in the channel of stream, or the bed of the ocean? Maybe.<br />

The scope of work calls for analyzing the existing drainage system within the<br />

project limits. It is possible that the existing drainage structures are not adequate<br />

or additional drainage structure will be required. In these cases the drainage<br />

channel may be modified. The construction plans and specifications will include<br />

BMP cover requirements to mitigate sediment during construction within the<br />

drainage channels or embankments along the bays and channel.<br />

4.2.5 Exposure of people or property to geological hazards such as<br />

landslides, ground failure, or similar hazards? Maybe. The scope of work<br />

calls analyzing the steep cuts, embankments and slope protection on the existing<br />

road. It is possible that the existing slopes or slope protection are deemed unsafe<br />

and efforts maybe necessary to correct the existing condition. The construction<br />

plans and specifications will include BMP cover requirements to prevent landslide.<br />

4.3 Air- Will the proposed project result in:<br />

4.3.1 Substantial air emissions or deterioration of existing air quality? No. The<br />

temporary construction activities will generate dust and increase the hydrocarbon<br />

emissions in the area where construction equipment is operating. The<br />

construction plans and specifications will include best management practices<br />

(BMPs) to mitigate dust and to control dust, e.g. using water trucks to spray water<br />

on areas of unstabilized soil.<br />

LYON ASSOCIATES 4-5


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Figure 4-3<br />

Watering Trucks for Dust Control<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

4.3.2 Creation of objectionable odors? Maybe. The temporary construction<br />

activities may pike the levels of hydrocarbon emissions in the localized areas<br />

where construction equipment is operating or in asphalt paving. Typically many of<br />

the construction equipment have diesel engines. The exhaust from these may<br />

temporarily create objectionable odors.<br />

4.4 Water- Will the proposed project result in:<br />

4.4.1 Changes in currents, or the course or direction of water movements,<br />

in marine or fresh waters? Maybe. The scope of work calls for analyzing<br />

and evaluating the existing drainage system within the project limits. It is possible<br />

that the existing drainage structures are not adequate or additional drainage<br />

structure will be needed. In these cases the drainage course or direction may be<br />

modified. The construction plans and specifications will include BMPs to mitigate<br />

sediment transfer during temporary construction within the drainage course or<br />

embankments along the bays and channel.<br />

4.4.2 Changes in absorption rates, drainage patterns, or the amount of<br />

surface runoff? Maybe. Reportedly, the construction of the existing road did<br />

change the infiltration rates, drainage patterns, the amount and path of surface<br />

runoff. The scope of work calls for analyzing and evaluating the existing drainage<br />

system within the project limits. It is possible that the existing drainage structures<br />

are not adequate or additional drainage structure will be required. In these cases<br />

the changes in one or all three topics may be modified.<br />

4.4.3 Alterations to the course or flow of flood waters? Maybe. Similarly, The<br />

scope of work calls for analyzing and evaluating the existing drainage system<br />

within the project limits. It is possible that the existing drainage structures are not<br />

adequate or additional drainage structure will be required. In these cases the<br />

drainage course or direction may be modified. The construction plans and<br />

specifications will include BMPs to mitigate sediment during temporary<br />

construction within the drainage course or embankments along the bays and<br />

channel.<br />

LYON ASSOCIATES 4-6


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

4.4.4 Discharge into surface waters or any alteration of surface water<br />

quality including but not limited to temperature, dissolved oxygen,<br />

bacteria, or turbidity? Maybe. Temporary construction activities has the<br />

potential to discharge contaminates into the surface waters. These temporary<br />

construction activities will require the contractor to implement BMPs to prevent or<br />

at least mitigate the discharges from construction activities. Industrial activities are<br />

not anticipated for the site.<br />

4.4.5 Contamination of ground waters or wells, from salt water intrusion or<br />

surface activities? No.<br />

4.4.6 Changes in the quantity of ground waters, through direct additions or<br />

withdrawal, or through interception of an aquifer by cuts or<br />

excavation? Maybe. As mentioned above, The scope of work calls for<br />

analyzing and evaluating the existing drainage system within the project limits.<br />

Existing ponding of stormwater along the roadside is likely to be drained in order to<br />

reduce it contribution to temporarily increasing the groundwater level and<br />

subjecting the road bed to saturation by the groundwater. Furthermore, roadway<br />

cuts into the terrain may occur in order to stabilize the slope. Water seepage from<br />

these cuts and springs may redirected in order to reduce ponding along or above<br />

the roadway.<br />

4.4.7 Substantial reduction in the amount or quality of water otherwise<br />

available for public water supplies? No.<br />

4.4.8 Exposure of people or property to water related hazards such as<br />

flooding or tidal waves? No. One of the objectives in this project is to reduce<br />

the risk of water related hazards from flooding or tidal waves to the people using<br />

and depending on the roadway.<br />

4.5 Plant Life- Will the proposed project result in:<br />

4.5.1 Destruction of any upland or mangrove forest communities? Maybe. It<br />

is likely that the elevation of the existing roadway will be raised in order to deduce<br />

the effects and/or the frequency of storm surges and tidal action. The act of<br />

raising the roadway may require the embankment to be raise thus likely extending<br />

its footprint in order to maintain a stable slope on the embankment. It is possible<br />

that fringes of existing upland or mangrove forest communities may be affected.<br />

4.5.2 Destruction of other important plant communities, such as sea<br />

grasses or plants having potential commercial value? No.<br />

4.5.3 Reduction of the numbers of any unique, rare or endangered plant<br />

species? No.<br />

4.5.4 Introduction of new species of plants into an area, or resultant barrier<br />

to the normal replenishment of existing species? No.<br />

4.5.5 Reduction in acreage of any agricultural crop? No.<br />

4.6 Animal Life- Will the proposed project result in:<br />

LYON ASSOCIATES 4-7


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

4.6.1 Destruction of any coral reef areas? No.<br />

4.6.2 Reduction of the numbers of any unique, rare or endangered animal<br />

species? No.<br />

4.6.3 Introduction of new animal species into an area, or result in a barrier<br />

to the migration or movement of animals? No.<br />

4.6.4 Substantial deterioration of fish or wildlife habitat? No.<br />

4.7 Noise- Will the proposed project result in:<br />

4.7.1 Increase in existing noise levels or exposure of people to severe noise<br />

levels? No, industrial or other activities that will create severe noise levels are<br />

anticipated at the site after the completion of the road improvement project.<br />

4.8 Land Use- Will the proposed project result in:<br />

4.8.1 Substantial alteration of the present or planned land use of an area?<br />

No. This project will make improvements to the existing road.<br />

4.9 Natural Resources- Will the proposed project result in:<br />

4.9.1 A noticeable increase in the rate of use of any natural resources? No.<br />

4.9.2 Substantial depletion of any non-renewable natural resources? No.<br />

4.10 Risk of Upset- Will the proposed project result in:<br />

4.10.1 A risk of an explosion or the release of hazardous substances<br />

including but not limited to oil, pesticides, chemicals, or radiation, in<br />

the event of an accident or upset conditions? No. The design process to<br />

date has not selected to chemical treatment such as Condor SS unless the <strong>State</strong><br />

of <strong>Yap</strong>, Department of Public Works and Transportation recommends otherwise.<br />

Condor SS is a mixture of ion exchange resins and sulfuric and sulfonic acids that<br />

is designed to remove the water of hydration from subgrade clays. This allows the<br />

subgrade to be compacted to a dense, highly stable state. The mixture is applied<br />

by ripping and sprinkling or by injection into the subgrade, followed by compaction<br />

with a vibrating roller (Escobar, 1984). The material is extremely acidic (pH 1.25)<br />

so care must be used to avoid spills and to prevent overland flow runoff from<br />

treated areas immediately after application. In order to prevent or reduce the<br />

discharge of pollutants e.g. liquid petroleum products to storm water from material<br />

delivery and storage by minimizing the storage of hazardous materials on-site,<br />

storing materials in a designated area, installing secondary containment,<br />

conducting regular inspections, and training employees and subcontractors.<br />

LYON ASSOCIATES 4-8


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Figure 4-4 Secondary Containment<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

4.10.2 Possible interference with an emergency response plan? No.<br />

4.11 Population- Will the proposed project result in:<br />

4.11.1 Relocation or altered distribution, density, or growth rate of the human<br />

population of an area? No.<br />

4.12 Housing- Will the proposed project result in:<br />

4.12.1 Changes in existing housing or create a demand for additional<br />

housing? No.<br />

4.13 Transpiration- Will the proposed project result in:<br />

4.13.1 Generation of substantial additional vehicular movement? No.<br />

4.13.2 Substantial impact on roads and existing transportation system? Yes.<br />

Traffic patterns should remain the same. Temporary disruptions to the traffic is<br />

expected during construction activities. As a result of the road improvement, the<br />

roadway operation and maintenance costs for this segment of the road will be<br />

reduced.<br />

4.13.3 Alteration to present patterns of movement of people and/or goods?<br />

No.<br />

4.14 Public Services<br />

4.14.1 Will the proposed project result in or affect the need for new or altered<br />

services in Police or fire protection? No.<br />

4.14.2 Will the proposed project result in or affect the need for new or altered<br />

services in Schools? No.<br />

LYON ASSOCIATES 4-9


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

4.14.3 Will the proposed project result in or affect the need for new or altered<br />

services in Parks or other recreational facilities? No.<br />

4.14.4 Will the proposed project result in or affect the need for new or altered<br />

services in Hospital? No.<br />

4.14.5 Will the proposed project result in or affect the need for new or altered<br />

services in Other government services? No.<br />

4.15 Utilities<br />

4.15.1 Will the proposed project result in the need for new systems, or<br />

substantial changes in the Power? No.<br />

4.15.2 Will the proposed project result in the need for new systems, or<br />

substantial changes in Communications? No.<br />

4.15.3 Will the proposed project result in the need for new systems, or<br />

substantial changes in Water? Yes. There will be adjustments to the<br />

existing waterlines at those existing culverts to be added-on the new culverts.<br />

4.15.4 Will the proposed project result in the need for new systems, or<br />

substantial changes in Sewage disposal? No.<br />

4.15.5 Will the proposed project result in the need for new systems, or<br />

substantial changes in Solid waste disposal? No.<br />

4.16 Human Health- Will the proposed project result in:<br />

4.16.1 Creation of any health hazard or potential health hazard? No.<br />

4.16.2 Improvement of human health? No.<br />

4.17 Aesthetics- Will the proposed project result in:<br />

4.17.1 Obstruction of any scenic vista? No.<br />

4.18 Recreation- Will the proposed project result in:<br />

4.18.1 Changes in the quality or amount of existing recreational<br />

opportunities? No.<br />

4.19 Cultural Resources- Will the proposed project result in:<br />

4.19.1 Alteration or destruction of archaeological sites? No.<br />

4.19.2 Adverse physical or aesthetic impacts on a historic site? No.<br />

LYON ASSOCIATES 4-10


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

4.19.3 Potential to cause a physical change which would affect unique<br />

cultural values? No.<br />

4.19.4 Restriction of existing religious or sacred uses within the affected<br />

area? No.<br />

4.20 Others- Will the proposed project result in:<br />

4.20.1 Please specify. None<br />

LYON ASSOCIATES 4-11


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

5 ALTERNATIVES TO MITIGATE ADVERSE IMPACTS<br />

5.1 Design Considerations<br />

5.1.1 As stated above in this report, the objective of the project is to mitigate adverse<br />

impacts on and around the existing road. Project design considerations will<br />

encompass:<br />

• Design project to integrate into existing land contours.<br />

• Significant regrading of a site will require more costly erosion and<br />

sedimentation control measures and may require that on-site drainage facilities<br />

be installed e.g. silt fencing as shown in Figures 5-1 and 5-2. Note these<br />

figures will be included in the project construction plans and specifications<br />

Figure 5-1<br />

Silt Fencing for Sediment Control<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

Figure 5-2 Silt Fencing for Cross Section<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

LYON ASSOCIATES 5-12


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

• Carefully planned preservation of existing vegetation minimizes the potential of<br />

removing or injuring existing trees, vines, shrubs and/or grasses that serve as<br />

erosion controls.<br />

• Clearly mark, flag or fence vegetation or areas where vegetation should be<br />

preserved.<br />

• Prepare landscaping plans which include as much existing vegetation as<br />

possible and state proper care of this vegetation both during and after<br />

construction.<br />

• Define and protect with berms, fencing, signs, etc., a setback area from<br />

vegetation to be preserved. Setback area size should be based on the location,<br />

species, size, age and potential impact of adjacent construction activities or<br />

permanent improvements.<br />

• Proposed landscaping plans which do not include plant species that compete<br />

with the existing vegetation.<br />

• Do not locate construction traffic routes, spoil piles, etc., where significant<br />

adverse impact on existing vegetation may occur.<br />

• Rock outlet protection is a physical device composed of rock, grouted riprap, or<br />

concrete rubble which is placed at the outlet of a pipe to prevent scour of the<br />

soil caused by high pipe flow velocities, and to absorb flow energy to produce<br />

non-erosive velocities.<br />

Figure 5-3<br />

Stormwater Outlet Protection<br />

Source: Best Management Practices Manual for Const. City & County of Honolulu<br />

5.2 Erosion Control Plan<br />

5.2.1 However, during the construction of improvements best management practices<br />

(BMP) in the design documents shall be implemented by the contractor.<br />

5.2.2 The contractor shall prepare and submit to <strong>Yap</strong> <strong>State</strong> EPA for approval.<br />

Sequencing the construction project to reduce the amount and duration of soil<br />

exposed to erosion by wind, rain, runoff, and vehicle tracking. The design team is<br />

aware that construction scheduling to reduce erosion may increase other<br />

LYON ASSOCIATES 5-13


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

construction costs due to reduced economies of scale in performing site grading.<br />

Note that the erosion control will be included in the specifications. The cost<br />

effectiveness of scheduling techniques should be compared with the other, less<br />

effective erosion and sedimentation controls to achieve a cost-effective balance.<br />

Recommended approaches shall include:<br />

• Avoid rainy periods: Schedule major grading operations during dry months.<br />

• Allow enough time before rainfall begins to stabilize the soil with vegetation or<br />

physical means or to install temporary sediment trapping devices<br />

• Sequence construction so that haul roads and stockpiles are buffered with<br />

planted areas prior to discharging offsite.<br />

• Separate offsite runoff where possible, so that it flows through the construction<br />

site without going through bare ground.<br />

• Locate stockpiles away from waterways or low spots.<br />

• Maintain swales and natural drainage ways in vegetated condition.<br />

• Save trees and other existing vegetation. Vegetation along the perimeter of the<br />

site provides an effective buffer against sediment leaving the construction site.<br />

• Use naturally level area for parking during construction.<br />

• Maintenance and inspect erosion control BMPs daily and log the findings.<br />

• Provide mulching, grassing other ground cover to reduce bare areas.<br />

• Minimize soil exposed at one time: Schedule projects to disturb only small<br />

portions of the site at any one time. Complete grading as soon as possible.<br />

Immediately stabilize the disturbed portion before grading the next portion.<br />

Practice staged seeding. Revegetate cut and fill slopes as the work<br />

progresses.<br />

• Trenching: Close and stabilize open trenches as soon as possible. Sequence<br />

trenching projects so that most open portions of the trench are closed before<br />

new trenching is begun.<br />

5.3 Monitoring Plan<br />

5.3.1 The design team recommends and will include a monitoring plan in the<br />

specifications that <strong>Yap</strong> EPA require the contractor to prepare and conduct a<br />

surface water monitoring program for construction activities within water ways.<br />

5.4 Traffic Control Plan<br />

5.4.1 The design team will prepare a traffic control plan in order to mitigate traffic delays<br />

during construction and to enhance public safety and will include traffic control plan<br />

requirements in the specifications.<br />

LYON ASSOCIATES 5-14


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

6 THE NEED FOR THE PROPOSED PROJECT<br />

6.1 Summary<br />

6.1.1 Although the existing was only constructed in the mid 1980s, the following<br />

problems have been sited:<br />

• The asphalt pavement has deteriorated in several segments of the road<br />

particularly along the shoreline. <strong>Yap</strong> <strong>State</strong> has replaced the asphalt pavement<br />

in some of these areas with portland concrete pavement but the problem<br />

persists.<br />

• The original construction of this road segment in this project changed the preexisting<br />

drainage system resulting in changing upland forest into upland<br />

marshes and altering flow patterns to downstream both freshwater and<br />

saltwater wetland.<br />

6.1.2 The <strong>State</strong> of <strong>Yap</strong>, Department of Public Works and Transportation defined the<br />

scope of this project and published a request for proposal (RFP). Lyon Associates<br />

was selected and was issued the Notice to Proceed (NTP) for the design services<br />

for this project December 9, 2009. The document was prepared in accordance to<br />

the contract.<br />

LYON ASSOCIATES 6-1


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

7 REFERENCE<br />

Buden, D.W. 1996. Rediscovery of the Pohnpei Mountain Starling (Aplonis pelzelni). The<br />

Auk 113(1):229-230.<br />

Buden, D.W. 2000. A comparison of 1983 and 1994 bird surveys of Pohnpei, Federated<br />

<strong>State</strong>s of Micronesia. Wilson Bull. 112(3):403-410.<br />

City and County of Honolulu, Dept. of Environmental Services 1999. Best Management<br />

Practices Manual for Construction Sites in Honolulu, pp 144.<br />

Cole, W.S. 1960 Bull Am Pal., 41 pp 77-83<br />

Devoe, N. 1991. Interim Report: Mangrove Areas Use Classification, Pohnpei, FSM.<br />

Institute of Pacific Islands Forestry, U.S.D.A. Forest Service, Honolulu, Hawaii 96813.<br />

28 pp. Unpublished manuscript.<br />

Engbring J., F.L. Ramsey and V.J. Wildman 1990. Micronesian forest bird surveys, the<br />

federated states: Pohnpei, Kosrae, Chuuk and <strong>Yap</strong>. U.S. Fish and Wildlife Service.<br />

Department of the Interior, Washington D.C.<br />

Escobar, R. 1984. Electrochemical soil stabilization. Joint publication of the Organization<br />

Condor, Apartado 80565, Caracas '1080A Venezuela and Earth Science Products<br />

Corp. 1960 S. W. 16th Ave, Portland, Oregon, 97201, USA. 110 p.<br />

Falanruw, M., Cole, T., Ambacher, A., McDuffie, K. & Maka, J. 1987a. Vegetation Survey of<br />

Moen, Dublon, Fefan and Eten, <strong>State</strong> of Truk, Federated <strong>State</strong>s of Micronesia. Resour.<br />

Bull. PSW-20. Pacific Forest and Range Experiment Station, U.S. Department of<br />

Agriculture, Berkeley, California. 6 pp + 3 maps.<br />

Falanruw, M., Whitesell, C., Cole, T., MacLean, C. & Ambacher, A. 1987b. Vegetation<br />

Survey of <strong>Yap</strong>, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-21. Pacific Forest<br />

and Range Experiment Station, U.S. Department of Agriculture, Berkeley, California. 9<br />

pp + 4 maps.<br />

Falanruw, M.V.C., T. Cole, A.H. Ambacher, K.E. McDuffie & J.E. Maka. 1987. Vegetation<br />

Survey of Moen, Dublon, Fefen and Eten, <strong>State</strong> of Truk, Federated <strong>State</strong>s of<br />

Micronesia, USDA Forest Service, Resource Bull. PSW-20, 6pp+ 3 maps.<br />

Falanruw, M.V.C. 1988. On the status, reproductive biology and management of fruit bats<br />

of <strong>Yap</strong>. Micronesica 21 (1-2), pp. 39-51.<br />

Food and Agricultural Organization of the United Nations. 1989. Watershed management<br />

field manual - Road design and construction in sensitive watersheds. FAO<br />

Conservation Guide, 13/5. 196 p.<br />

Fosberg, F.R., M-H. Sachet and R. Oliver 1979. Geographical checklist of the Micronesian<br />

Dicotyledonae. Micronesica 18(1):23-82.<br />

Fosberg, F.R., M-H. Sachet and R. Oliver 1982. Geographical checklist of the Micronesian<br />

Pteridophyta and Gymnospermae. Micronesica 18(1):23-82.<br />

Fosberg, F.R., M-H. Sachet and R. Oliver 1987. Geographical checklist of the Micronesian<br />

Monocotyledonae. Micronesica 18(1):23-82.<br />

Fosberg, F.R. 1947. Micronesian Mangroves. New York Bot. Gard. Jour. 48: 128-138.<br />

Fosberg, F.R. 1975. Phytogeography of Micronesian Mangroves. Proc. International<br />

Symposium on Biological Management of Mangroves. 1: 23-42.<br />

FSM 1999. Proceedings of the 2 nd FSM Economic Summit. Pohnpei, FSM<br />

FSM 2000. Coastal Fisheries Consortium Report of Proceedings. FSM Department of<br />

Economic Affairs, Pohnpei.<br />

FSM <strong>Yap</strong> Branch Statistics Office, Division of Statistics, Department of Economic Affairs,<br />

2002. <strong>Yap</strong> <strong>State</strong> Census Report, 2000 FSM Census of Population and Housing.<br />

FSM <strong>Yap</strong> Branch Statistics Office, Division of Statistics, Department of Economic Affairs,<br />

2002. <strong>Yap</strong> <strong>State</strong> Annual Statistical Yearbook, 2007.<br />

LYON ASSOCIATES 7-2


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

FSM Statistical Unit, Division of Statistics, Department of Economic Affairs, 2007.<br />

Statistical Yearbook, FSM 2007.<br />

Gawel, M.J. 1993. The Federated <strong>State</strong>s of Micronesia <strong>State</strong> of the Environment Report.<br />

SPREP<br />

Geotesting Inc. 1986. The <strong>Yap</strong> Road Improvements - Phase V Soil Investigation Report.<br />

Holthus, P.F. 1987. Pohnpei Coastal Resources: Proposed Management Plan. Draft<br />

Report. South Pacific Regional Environment Programme, Noumea, New Caledonia.<br />

101 pp.<br />

Hosokawa, T. 1954. On the Campnosperma Forests of <strong>Yap</strong>, Ponape and Kusaie in<br />

Micronesia. Mem. Fac. Sci. Kyushu Univ. Ser. E. 1: 219-243.<br />

Hosokawa, T. 1957. Outline of the Mangrove and Strand Forests of Micronesian Islands.<br />

Mem. Fac. Sci. Kyushu Univ. Ser. E. 2(3): 101-118.<br />

Hosokawa, T. 1971. On the tropical rainforest conservation to be proposed in Micronesia.<br />

In: Proc. Symposium on Planned utilization of the lowland tropical forests: 150-164.<br />

Pre-Congress Conference in Indonesia.<br />

Hosokawa, T., Tagawa, H. & Chapman, V.J. 1977. Mangrove of Micronesia, Taiwan,<br />

Japan, the Philippines and Oceania. In: Chapman, V.J. (ed.) 1977, Wet Coastal<br />

Ecosystems: 271-291. Elsevier Publishing Co., Amsterdam.<br />

IUCN 1991. IUCN Directory of Protected Areas in Oceania. Prepared by the World<br />

Conservation Monitoring Centre. IUCN, Gland, Switzerland and Cambridge, U.K.<br />

Johnson, C., Alvis, R., Hetzter, R and Blumestock, D., 1960 U.S. Army Pacific APO 958, pp<br />

168<br />

Kogo, M., Miyagi, T. & Musahino, Y. 1985. Final Report on Mangrove Research in Truk<br />

Islands, April 19 - May 10 1985. Prepared for the UNDP/UNESCO Regional Project:<br />

Mangrove Ecosystems of Asia and Pacific RAS/79/002. Al Gurm Research Centre,<br />

Tokyo, Japan. 80 pp.<br />

Koyama, T. 1964. The Cyperaceae of Micronesia. Micronesica 1(1): 59-112.<br />

Laird, W.E. 1982. Soil Survey of Island of Ponape, Federated <strong>State</strong>s of Micronesia. USDA<br />

Soil Conservation Service, Washington, D.C. 81 pp + 1 map and 43 aerial photos.<br />

Laird, W.E. 1983a. Soil Survey of Islands of Truk, Federated <strong>State</strong>s of Micronesia. USDA<br />

Soil Conservation Service, Washington, D.C. 65 pp + 3 maps and 16 aerial photos.<br />

Laird, W.E. 1983b. Soil Survey of Island of Kosrae, Federated <strong>State</strong>s of Micronesia. USDA<br />

Soil Conservation Service, Washington, D.C. 67 pp + 1 map and 12 aerial photos.<br />

Lal, P.N. 1989. Utilization and Management of Coastal Wetland Resources in Kosrae.<br />

Unpublished manuscript. University of Hawaii Sea Grant, Honolulu, Hawaii. 39 pp.<br />

Lobban, C.S., Daily, F.K., Daily, W.A., Hoshaw, R.W. & Schefter, M. 1990. Periphyton,<br />

Excluding Diatoms and Desmids, from <strong>Yap</strong>, Caroline Islands. Micronesica 23(1): 27-40.<br />

Lyon Associates, 2010. Draft Drainage Assessment, pp 13.<br />

MacLean, C., Cole, T., Whitesell, C., Falanruw, M. & Ambacher, A. 1986. Vegetation<br />

Survey of Pohnpei, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-18. Pacific<br />

Forest and Range Experiment Station, U.S. Department of Agriculture, Berkeley,<br />

California. 9 pp + 11 maps.<br />

MacLean, C., Cole, T., Whitesell, C. & McDuffie K. 1988. Timber Resources of Kosrae,<br />

Pohnpei, Truk and <strong>Yap</strong>, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-24. Pacific<br />

Forest and Range Experiment Station, U.S. Department of Agriculture, Berkeley,<br />

California. 8 pp.<br />

Miyagi, T. & Kiyoshi, F. 1989. Geomorphological Situation and Stability of Mangrove Habitat<br />

of Truk Atoll and Ponape Island in the Federated <strong>State</strong>s of Micronesia. Science<br />

Reports of the Tohuku University, 7th Series (Geography) 39 (1): 25-52.<br />

Mowbray, D.L. 1988. Pesticide use in the South Pacific. UNEP Regional Seas Reports and<br />

Studies No.89; SPREP Topic Review No.26. UNEP, Nairobi.<br />

LYON ASSOCIATES 7-3


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Nedachi, M., Meada, T., Shigeyoshi, R., Inoue, A., Shimada, K., Higashi, M., Habano, A.,<br />

Azuma, T. and Hatta, A. 1999 Taktai, K.M., Nedachi, Y., Yamanouchi, H. and<br />

Matsumura, K., 2001. Geology of Environments on <strong>Yap</strong> Islands, Micronesia. Occa.<br />

Paper Kagoshima Univ. Research Center for the South Pacific, 34, 69-76 pp<br />

Nedachi, M., Taktai, K.M., Nedachi, Y., Yamanouchi, H. and Matsumura, K., 1996 Occa.<br />

Paper Kagoshima Univ. Research Center for the South Pacific, 32, 24-29 pp<br />

Nelson, S.G. (ed.) 1989. The Inland Aquatic Habitats of <strong>Yap</strong>. University of Guam Marine<br />

Laboratory Technical Report No.92. Mangilao, Guam. 78 pp.<br />

Pettys, E., Peter, S., Rugg, R. & Cole, T. 1986. Timber Volumes in the Mangrove Forests of<br />

Pohnpei, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-19. Pacific Forest and<br />

Range Experiment Station, U.S. Department of Agriculture, Berkeley, California.<br />

Pratt, H.D., Bruner, P.L. & Berrett, D.G. 1987. A Field Guide to the Birds of Hawaii and the<br />

Tropical Pacific. Princeton University Press, Princeton, U.S.A. 409 pp.<br />

Smith, C.M. 1983. Soil Survey of Islands of <strong>Yap</strong>, Federated <strong>State</strong>s of Micronesia. USDA<br />

Soil Conservation Service, Washington, D.C. 90 pp + 1 map and 18 aerial photos.<br />

SPREP 1993. The Federated <strong>State</strong>s of Micronesia Nationwide Environmental Management<br />

Strategies. Apia, Western Samoa.<br />

Stemmermann, L. 1981. A guide to Pacific wetland plants. U.S. Army Corps of Engineers,<br />

Honolulu, Hawaii. 118 pp.<br />

Stemmermann, L. & Proby, F. 1978. Inventory of Wetland Vegetation in the Caroline<br />

Islands (2 volumes). U.S. Army Corps of Engineers, Pacific Ocean Division, Fort<br />

Shafter, Hawaii. 93 pp + 61 maps (Volume 1); 382 pp (Volume 2).<br />

Trustrum, N.A. 1996. Pohnpei’s Watershed Spatial Plan and Management Guidelines.<br />

Landcare Research, New Zealand, Ltd. Palmerston North, New Zealand.<br />

Tsuda, R.T., Fosberg, F.R. & Sachet, M.H. 1977. Distribution of Seagrasses in Micronesia.<br />

Micronesica 13 (2): 191-198.<br />

UNEP/IUCN 1988. Coral Reefs of the World. Volume 3: Central and Western Pacific. UNEP<br />

Regional Seas Directories and Bibliographies. IUCN, Gland, Switzerland and<br />

Cambridge, U.K./UNEP, Nairobi, Kenya.<br />

U.S. Army Corps of Engineers, Pacific Ocean Division 1988. <strong>Yap</strong> Coastal Resource Atlas.<br />

Manoa Mapworks, Honolulu, Hawaii. 67 pp.<br />

U.S. Army Corps of Engineers, Pacific Ocean Division 1989b. <strong>Yap</strong> Islands Coastal<br />

Resource Inventory. U.S. Army Corps of Engineers, Pacific Ocean Division, Fort<br />

Shafter, Hawaii. 355 pp.<br />

U.S. Department of Agriculture, Soil Conservation Service, Forest Service, U.S. Department<br />

of Interior, Office of the High Commissioner, Trust Territory of the Pacific Islands,<br />

University of Hawaii at Manoa, College of Tropical Agriculture and Human Resources<br />

1981. General Soil Map, Islands of <strong>Yap</strong>, FSM.<br />

Western Regional Climate Center 2007. Summary Precipitation <strong>Yap</strong> WSO Station.<br />

Whitesell, C., MacLean, C., Falanruw, M., Cole, T. & Ambacher, A. 1986. Vegetation<br />

Survey of Kosrae, Federated <strong>State</strong>s of Micronesia. Resour. Bull. PSW-17. Pacific<br />

Forest and Range Experiment Station, U.S. Department of Agriculture, Berkeley,<br />

California. 8 pp + 1 map.<br />

Wiles, G.J., D.W. Buden and D.J. Worthington 1999. History of introduction, population<br />

status, and management of Philippine deer (Cervus mariannus) on Micronesian<br />

Islands. Mammalia, t.63,n o 2: 193-215<br />

Wilson, A. Meriwether & Hamilton, L.S. (eds) 1992. Kosrae Island Integrated Coastal<br />

Resources Assessment for Biodiversity/Cultural Conservation and Nature-Based<br />

Tourism. The East-West Center, Environment and Policy Institute, Honolulu, Hawaii.<br />

121 pp.<br />

LYON ASSOCIATES 7-4


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

<strong>Yap</strong> <strong>State</strong> Environmental Protection Agency, c. 1995. Title II Environmental Impact<br />

Assessment.<br />

Ziemer, R.R., & Megahan, W.F. 1991. Erosion and Sedimentation Control on Roads and<br />

Construction Sites in the Federated <strong>State</strong>s of Micronesia.<br />

LYON ASSOCIATES 7-5


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

This preliminary environmental impact statement was prepared by Terry Kearney, PE, Civil<br />

and Environmental Engineer. Mr. Kearney has reviewed and/or prepared environmental<br />

documents for 38 years. He has a masters degree in public health with a specialty in<br />

environmental heath and a masters degree in urban and regional planning. He has worked<br />

for Lyon Associates for eight years.<br />

LYON ASSOCIATES 7-6


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Appendix A<br />

OBSERVATIONS DURING TRIP TO FSM<br />

October 28 to November 8, 1990<br />

Robert R. Ziemer & Walter F. Megahan<br />

YAP<br />

We drove the length of the cross-island road that was being constructed by You One<br />

Construction Company from Korea. The new road runs from Colonia through Tomil to the<br />

northeastern coast of Maap. Construction began in Maap and is proceeding to Colonia.<br />

Construction is nearing completion in Maap and Tomil, but paving had not yet begun. Rightof-way<br />

clearing is just beginning near Colonia. The road seems to be well-designed. The<br />

subgrade is being stabilized using injected Condor SS. This is designed to chemically<br />

extract water from the clay lattice, allowing the lattice to collapse and the clay to be<br />

compacted. There was local concern about the environmental safety of Condor SS. There<br />

was an unverified report that about 500 gallons of the material had recently been spilled,<br />

but we did not see the location.<br />

The road surface is crowned, directing drainage to poured-in-place concrete V-shaped<br />

drainage ditches on both sides of the road. We were unable to obtain information on the<br />

design flow of the ditches, but they appear in some cases to be too small to carry intense<br />

storm runoff. In several cases, the ditches are so constructed that runoff will probably jump<br />

the turn at the downhill end and continue down the road rather than be diverted from the<br />

road as expected.<br />

The road near Colonia is intended to encroach into the mangrove and lagoon margin. We<br />

recommend that during construction, a silt; fence be installed to limit migration of sediment<br />

into the lagoon. And, upon completion of the subgrade, the road fill be protected by a sea<br />

wall or rip-rap.<br />

At the bridge site between Tomil and Maap, the channel has been filled and an extensive<br />

soil disposal site has been constructed on the Tomil side of the channel. All flow within the<br />

channel has been blocked by the fill and the mangrove appears to be stressed and the<br />

leaves seem to be yellowing. A burlap silt fence has been constructed near the disposal<br />

site, but it seems to be ineffective. The plan is to construct a bridge and to eventually<br />

remove the fill. Construction costs are probably lowered by this method, but the amount<br />

of sediment introduced to the channel is very large. The environmental consequences of<br />

this additional sediment is unknown.<br />

About 1 mile from the bridge site on Maap, there is a large fill and disposal site containing<br />

about 30,000 cubic yards of soil. This material appears to be uncompacted and poor<br />

surface drainage has caused severe gullying on the fill face. Eroded material is being<br />

transported to and down a small drainage basin to be discharged into the lagoon about 1/4<br />

mile away. Surface drainage here should be controlled and routed to a hardened and safe<br />

location. The fill should be quickly revegetated with woody plants to provide some<br />

LYON ASSOCIATES 7-7


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

strength to the weak fill. Revegetation will assist in stabilizing the fill, but since the entire fill<br />

was not compacted there is little internal strength and vegetation can not be expected to<br />

solve the problem. Unless surface water is directed away from the fill face, a serious<br />

gullying problem can be expected at this location for years. In addition, a silt fence: or<br />

barrier should be installed at the base of the fill to catch eroded material.<br />

Although the road itself seems to have been well-designed, the provision for dealing with<br />

water once it leaves the road is poorly planned. Apparently, concern for off-road<br />

environmental damage was not part of the road design. For example, it is not uncommon<br />

for roadside ditches to carry water for up to 1600 feet before discharging into a stream or<br />

scale. At such discharge points, inadequate provision has been made to protect the slope<br />

or stream channel from the volume or force of the water that will be discharged. For a 40-<br />

foot wide roadway, the ditch discharge for a 1600-foot run during a 1-inch storm would be<br />

20x1600x(1/12)=2667 cubic feet of water. In this climate, it is perhaps not unusual to have a<br />

1-inch rainfall in 10 minutes. It is important to calculate expected 5- and 10-minute<br />

intensities for different return intervals, and further to calculate anticipated peak discharges<br />

from the road surface and surrounding right-of-way that contributes to ditch flow. The NOAA<br />

Weather Service collects such intensity data, but discussions with the local NOAA offices in<br />

<strong>Yap</strong>, Chuuk, Pohnpei, Kosrae, Guam, and Honolulu did not yield the records.<br />

Where energy dissipation and channel lining is provided, it is too small an effort to be very<br />

effective during storm flows. Across the road from the Maap fill disposal site is an example<br />

of poorly designed discharge of road drainage. The road drainage ditch runs for about 1100<br />

feet to a drop inlet where a box culvert discharges into a small grass and fern vegetated<br />

swale. Although water has been directed onto this scale for only about a month, there is<br />

evidence that a deep gully will form within a short time. The shallow grass-fern root system<br />

has already been penetrated by the incipient gully and there is little soil resistance to<br />

prevent accelerated gullying. It is important to control the force of water leaving the culvert<br />

and as it travels down this steep swale. We suggested that this would be an ideal place to<br />

demonstrate erosion control techniques. It is important to get some woody vegetation<br />

established to provide a fibrous root system and strengthen the soil. Marjorie Falanruw<br />

suggested that hibiscus can be established by simply pushing cuttings into the ground. It<br />

would be useful to test several types of vegetation for effective erosion control. The<br />

vegetation should be quick to establish and produce a deep and dense network of fibrous<br />

roots. In addition, the vegetation must be capable of withstanding the force of high velocity<br />

running water. The force of water could be reduced by placing and staking logs across the<br />

slope, creating a series of check dams as the water is routed down the slope. Had the water<br />

been routed about another 50 feet down the road, it could have been discharged onto a<br />

small ridge, rather than into the swale, and the runoff would have tended to disperse rather<br />

than concentrate.<br />

The question of the effectiveness of Vetiver grass was raised. There is<br />

concern in <strong>Yap</strong> that if introduced, Vetiver may escape and become a pest. In general, it is<br />

preferable that native rather than introduced species be used for three reasons: the ready<br />

availability of native materials, the cost of exotics, and the hazard of exotics becoming a<br />

pest.<br />

Not only has off-road erosion control not had high priority in the road<br />

design, there are no funds budgeted for continued road maintenance, let alone<br />

off-site erosion control.<br />

LYON ASSOCIATES 7-8


NORTHERN YAP ROAD IMPROVEMENTS PRELIMINARY EIS<br />

Unfortunately, without some local responsibility and technical direction, it is doubtful that<br />

any preventative action will be taken and large scale gullies will become common at the<br />

outfalls of many road ditches. Once the gullies form, repair or control will be extremely<br />

expensive and probably beyond the financial and technical capabilities of <strong>Yap</strong> <strong>State</strong>. To the<br />

direct costs of erosion control must be added the additional environmental damage to<br />

hill slopes, streams, taro patches, and lagoon ecology.<br />

Although we spent much of our time observing the major cross-island road, there are<br />

numerous secondary and agricultural roads that are constructed with little or no planning or<br />

erosion maintenance. In total, these roads produce a large and dispersed source of<br />

continuing sedimentation to agriculture, streams, and lagoon. Some of these secondary<br />

roads are constructed by the Seabees, sometimes as a favor to the local chief or<br />

landowner. It is common for <strong>Yap</strong> EPA to be excluded from review or notification. There<br />

should be some central clearing house agency or procedure for requesting and reviewing<br />

road construction plans.<br />

We visited the NOAA Weather Station on <strong>Yap</strong>, Chuuk, Pohnpei, and Kosrae. The story<br />

was the same at each location: the local station does not retain weather data, but sends it<br />

all to the National Climate Data Center in Ashville, NC. Each station records the time of<br />

each tip of the tipping-bucket rain gage (0.01-inch). Rainfall intensities of 24-hour and 1-<br />

hour have been published for the past 30+ years, but the 1-hour intensities are on the datatapes<br />

for only the past 3 or so years. NOAA states that previous years have not been<br />

"digitized". For estimating erosion hazard from small drainages, it is important to develop<br />

intensity curves for time periods as short as 5 minutes. The time of concentration for peak<br />

discharge from the road ditches will be 5 to 10 minutes.<br />

We visited the USGS gauging stations at Burong Stream and Eyeb Stream. We found the<br />

concrete weirs, but the gage housing had been removed. When we arrived in Guam, we<br />

telephoned Greg Ikehara, USGS Guam (339-5293). He stated that in August the <strong>Yap</strong> <strong>State</strong><br />

Legislature did not vote funds to continue data collection. Ikehara has been working<br />

primarily with Charles Chieng, Director of <strong>Yap</strong> Public Works. Adrian Gimed has been the<br />

streamgager on <strong>Yap</strong> for many years. He has not been employed since funding was<br />

terminated. Funding for gaging stations is shared equally between each FSM <strong>State</strong> and the<br />

USGS. Earlier in the year, Ikehara and Bill Meyer of the USGS Honolulu office (808-541-<br />

2654) visited <strong>Yap</strong> to explain to the Governor, Legislature, and Public Works Director Chiang<br />

the importance of the hydrologic record. Ikehara thought that their arguments were wellreceived<br />

and that funding would be restored, but as of November there has been no further<br />

communication with <strong>Yap</strong>. Ikehara also mentioned that streamgages were discontinued and<br />

removed from Chuuk <strong>State</strong> "several years ago" after a couple years of continued nonpayment<br />

of the Chuuk <strong>State</strong> funding share. Ikehara stated that funding was continuing in<br />

Pohnpei and Kosrae and the stream gages were still operating there. However, when we<br />

arrived in Kosrae we were told by Bruce Howell that the Kosrae legislature had recently<br />

voted to terminate funding for the Kosrae gauging station network. Howell stated that the<br />

Kosrae share of the cost was $5000 per year.<br />

LYON ASSOCIATES 7-9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

SERIES 100<br />

PRELIMINARIES AND GENERAL DESCRIPTION OF WORKS<br />

101. INTRODUCTION<br />

101. The <strong>Government</strong> of <strong>Yap</strong> <strong>State</strong> as part of their road development program<br />

proposes to rehabilitate and improve approximately 4.06 miles of road known<br />

as Northern <strong>Yap</strong> Road Improvements Project.<br />

102. LOCATION<br />

102.1 The project is located in central to northern <strong>Yap</strong> <strong>State</strong>, Federated <strong>State</strong>s of<br />

Micronesia.<br />

103. DETAILS OF PROJECT<br />

103.1 The beginning of the project is at the Hospital Intersection with the main road to<br />

Keng. It proceeds north and terminates at the western edge of Tagireeng<br />

Bridge. This segment of the road travels along the coastline through the villages<br />

of Keng, Dugor, Makal, Tafgif, Rumuu, Gargey, and Daboch.<br />

104. WORKS INCLUDED IN THIS CONTRACT<br />

104.1 The scope of Works includes:<br />

a) Site clearing of shrubs and undergrowth, grubbing, demolition of<br />

obstructions on the site in the way of or otherwise affected by the Works as<br />

shown in the drawing plans and specifications.<br />

b) Drainage works including culverts, concrete ditches and interceptor drains.<br />

c) Repair of gabion type seawall construction for road embankment protection<br />

in low areas.<br />

d) Subbase preparation, base and wearing course for the pavement.<br />

e) Asphalt paving works.<br />

f) Maintain all roads or access affected by construction in a motorable<br />

condition at all times.<br />

g) Payment of all costs including royalty for borrow materials from borrow pit<br />

outside the construction limit.<br />

h) All works incidental to the project including adjustment or relocation of<br />

services carried out within the terms of the Contract.<br />

SERIES 100 Page 1 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

105 WORKS UNDER WATER<br />

105.1 Certain of the Works may have to be carried out under water, and the rates and<br />

prices named by the Contractor in his bid shall include for all extra costs and<br />

changes whatsoever arising out of such work including the effects of<br />

exceptionally high flood levels and including any cost involved in working<br />

outside normal working hours or on rest days.<br />

106 WORKS TO BE COMPLETED<br />

106.1 This Specification has been drawn up with all possible care and is intended to<br />

cover supply of all materials and the execution of all works necessary to<br />

complete the Works (except as otherwise provided in this Specification). In<br />

case there are any details of construction or materials which have not been<br />

referred to in this Specification and Drawings but the necessity of which may<br />

reasonably be implied or inferred from the Specification or Drawings or which<br />

are usual or essential to the completion of all works in all trades, the same shall<br />

be deemed to be included in the Bid Price tendered by the Contractor.<br />

107. BID DOCUMENT AND VISIT SITE<br />

107.1 The Contractor shall be deemed to have read the Bid Documents for the Works<br />

and have visited the site before bidding and acquainted himself with any item or<br />

contingency liable to affect his bid price. No claims for extra remuneration or<br />

extension of the Contract time on the ground of ignorance of the working<br />

conditions or of his contractual obligations will be entertained.<br />

107.2 The accuracy of any particulars given or records referred to in the Contract<br />

Documents or supplied to the Contractors for their information is not in anyway<br />

guaranteed. The Contractor shall take into consideration all available records<br />

with regard to water levels, water courses, drains and all other physical features<br />

of the site in submitting his bid.<br />

108. MATERIALS PLANTS AND WORKMANSHIP<br />

108.1 Materials and workmanship throughout the works shall be of the highest quality<br />

of their respective kinds and it shall be understood that no superior class of the<br />

specified materials or workmanship is available in <strong>Yap</strong>.<br />

108.2 Unless otherwise specified, all materials and workmanship shall comply with<br />

<strong>Yap</strong> Standard and Codes of Practice where applicable and unless these are not<br />

available, American Standards and Codes of Practice shall apply.<br />

The Bidder may propose other Standards or Codes of Practice provided that<br />

the Standards or Codes are equivalent or superior to the relevant <strong>Yap</strong> or<br />

American Standards or Codes. Two copies of each Standard or Code<br />

proposed by the Bidder shall be provided by the Bidder with this bid. The<br />

Contractor shall as far as possible deploy labor, materials and plant available in<br />

<strong>Yap</strong> <strong>State</strong> in the execution and completion of the Work under this Contract.<br />

SERIES 100 Page 2 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

108.3 Due consideration in the award of bids will be given to Contractors who will<br />

make use of local resources in respect of labor, plant and materials.<br />

108.4 Wherever in this Specification any proprietary goods or materials are specified,<br />

goods or materials of alternative manufacturer may be considered for<br />

acceptance provided they comply in all respects as regards appearance and<br />

quality and are approved by the Contracting Officer.<br />

108.5 Wherever in this Specification any goods or materials are specified such is to<br />

be considered as being the minimum standard acceptable. In the event of the<br />

Contracting Officer allowing the substitution of any of these materials during the<br />

course of the contract, such substitution shall be accompanied by a<br />

corresponding deduction in cost unless the Contracting Officer directs<br />

otherwise.<br />

109. MATERIALS OF YAP ORIGIN<br />

109.1 The materials of <strong>Yap</strong>-origin where applicable must be used by the Contractor to<br />

the exclusion of imported materials and he shall allow for this special<br />

requirement in his bid.<br />

109.2 Under no circumstances will the Contractor be permitted to use imported<br />

materials unless he proves to the satisfaction of the Contracting Officer that<br />

local materials are not available, or if available are not of an acceptable<br />

standard or obtained practically.<br />

110. SUPPLY OF MATERIALS<br />

110.1 The Contractor shall place orders for specified materials at the earliest possible<br />

date after the acceptance of his bid.<br />

110.2 If the Contractor’s failure to supply any material causes any interruption or<br />

delay in the progress of the work, the Owner may supply any portion or all of<br />

the materials and the cost will be borne by the Contractor and shall be either as<br />

calculated at the current market rates or the actual cost to the Owner at the<br />

date of supply, including overheads and any other charges, whichever is the<br />

greater.<br />

110.3 Any costs incurred under the proceeding paragraphs shall be deducted from<br />

the Contract Sum by means of a Variation Order, but in the case of sub-clause<br />

110.2 above only, such Variation Order shall not be taken into account in<br />

computing the final sum on which the Retention Fund is based and no claim for<br />

loss profit under the conditions of this Contract shall be deemed to have risen.<br />

No action taken under these clauses shall in any way affect or modify the right<br />

of Owner to claim for damages in the event of the Contractor’s failure to<br />

complete the wok by the agreed date.<br />

111. SAMPLES<br />

111.1 The Contracting Officer shall be at liberty to call for submission of samples of<br />

materials or the execution of samples of workmanship for approval, and for<br />

SERIES 100 Page 3 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

further samples as are required until the samples submitted or executed are, in<br />

his opinion, in accordance with this Specification.<br />

112. INSURANCE AND LICENSES<br />

112.1 The Contractor shall ensure and provide evidence to the Owner that all his<br />

plant operators and lorry drivers do posses valid driving licenses and all earthmoving<br />

plant and vehicles shall be covered by third party insurance policies.<br />

The Contractor shall comply with the requirements of the <strong>Yap</strong> <strong>State</strong> Road<br />

Traffic Ordinance in all respects.<br />

113. WORKMEN’S ACCOMMODATIONS<br />

113.1 The Contractor shall provide, maintain and remove on completion of the works<br />

any necessary temporary accommodation and living facilities including all<br />

necessary services for water supply, drainage and lighting for his staff.<br />

113.2 Before any work is commenced on temporary accommodation the Contractor<br />

shall submit to the Contracting Officer a location plan and details of the<br />

proposed accommodations and services for his approval. The Contractor shall<br />

also comply with any statutory obligations and obtain any necessary approval<br />

from Statutory Authorities in writing, a copy of which shall be sent to the<br />

Contracting Officer.<br />

114. MEDICAL SERVICES<br />

114.1 The Contractor shall provide adequate medical services and first aid facilities<br />

suitable to the size and composition of his staff and labor force. The Contractor<br />

shall afford the Contracting Officer’s site staff full use of the services and<br />

facilities when required.<br />

115. EVERYTHING AT CONTRACTOR’S RISK<br />

115.1 All buildings, structures, furniture, equipment, plant, and things whatsoever<br />

which the Contractor is required by this Section of the Specification or<br />

elsewhere in the Contract Documents to provide shall at all time be at the risk<br />

of the Contractor, who shall at his own cost maintain them and renew anything<br />

as necessary notwithstanding any use of or damage thereto caused by the<br />

Contracting Officer’s site staff.<br />

116. REVERSION TO CONTRACTORS<br />

116.1 On completion of the Contract Works all buildings, structures, furniture,<br />

equipment, plant, and things provided and maintained under the terms of this<br />

Section of the Specification unless otherwise stated shall revert to the<br />

Contractor, who shall dismantle and remove all such things from the site and<br />

leave the site clean and reinstated to the approval of the Contracting Officer.<br />

SERIES 100 Page 4 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

117. PROGRAM TO BE PROVIDED<br />

117.1 The Contractor shall submit with his bid a preliminary program outlining his<br />

working methods, expected times or completion for the various parts of the<br />

work, details of any temporary structures he proposes to use and a schedule of<br />

plants and equipment.<br />

117.2 As soon as possible after the acceptance of his bid, the Contractor shall, if<br />

required, submit to the Contracting Officer for his approval, a detailed program<br />

showing the method of working, full details of any temporary structures and<br />

expected dates for completion of the various parts of the work. Refer to sub-<br />

Clause 4.5, Additional General Requirements.<br />

117.3 Once a program has been approved or agreed, the Contractor shall make every<br />

effort to maintain this program.<br />

117.4 The program may be revised subject to approval by the Contracting Officer.<br />

118. CONTRACTOR’S SUPERINTENDENCE<br />

118.1 The Contractor shall provide all necessary superintendents during the execution<br />

of the Works and as long thereafter as the Contracting Officer may consider<br />

necessary for the proper fulfillment of the Contractor’s obligations under the<br />

Contract.<br />

118.2 Without prejudice to sub-clause 7.17 of the General Requirements, the<br />

Contractor shall appoint a Site Agent who must be a qualified Engineer having<br />

sufficient relevant experience and he shall be approved by the Contracting<br />

Officer in writing (which approval may at any time be withdrawn). He shall have<br />

an aptitude for organizing and controlling men, be able to think quickly and<br />

decisively, and deal courteously and tactfully with other members of the<br />

Construction Team. He shall be constantly on the Works and shall devote the<br />

whole of his time to the superintendence of the same. If such approval is<br />

withdrawn by the Contracting Officer, the Contractor, as soon as is practicable<br />

after receiving written notice of such withdrawal shall remove the Agent from<br />

the site and shall not employ him again on the site in any capacity. Another<br />

Site Agent approved by the Contracting Officer shall replace him to take over<br />

his duties.<br />

119. DIMENSIONS AND LEVELS<br />

119.1 Before the Works or any part thereof are commenced the Contractor shall verify<br />

the dimensions and levels shown on the drawings and shall notify the<br />

Contracting Officer of any discrepancy which may affect the dimensions or<br />

levels of any part of the works. Such notification by the Contracting shall be<br />

given sufficient time to allow the Contracting Officer to prepare drawings or<br />

schedules showing his amended requirements.<br />

119.2 The Contractor shall in particular verify the levels of the existing ground<br />

surfaces within areas earthworks are to be performed and the locations and<br />

SERIES 100 Page 5 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

bed levels of watercourses. These may differ from the locations and levels<br />

shown on the drawings depending on the extending of erosion of the banks and<br />

beds are which has taken place during the interval between survey and<br />

construction. Existing roadway has been maintained by grading and there may<br />

be slight variations in the existing elevations with that shown on the drawings.<br />

120. SETTING OUT<br />

120.1 The Contractor shall be responsible for the true and proper setting out of the<br />

works and for the correctness of the position levels, dimensions and alignment<br />

of all parts of the works and for the provision of all necessary instruments,<br />

appliances and labor in connection therewith. If at any time during the progress<br />

of the works any errors shall appear or arise in the position levels dimensions or<br />

alignment of any part of the works the Contractor on being required so to do by<br />

the Contracting Officer unless such error is based on incorrect data supplied in<br />

writing by the Contracting Officer in which case the expense of rectifying the<br />

same shall be borne by the Owner. The checking of any setting-out of any line or<br />

level by responsibility for the correctness thereof and the Contractor shall<br />

carefully protect and preserve all benchmarks, sight rails, pegs and other things<br />

used in setting out the Works. The Contractor shall establish all horizontal curve<br />

points of intersection (PI’s), beginning of curve (BC’s), and end of curve (EC’s),<br />

and establish ties for these.<br />

120.2 Before commencing earthmoving at any location, the Contractor shall provide<br />

and install pre-cast concrete reference beacons on both sides of the road<br />

centerline at a spacing of 1,000 feet. The beacons shall be firmly sited at right<br />

angles to the centerline offset 50 feet or such other distance as directed by the<br />

Contracting Officer. The beacons shall not be less than 4 inch square in plan<br />

and shall take all practicable steps to safeguard the beacons including fencing<br />

and concreting in where necessary in the opinion of the Contracting Officer and<br />

shall replace any damaged beacons.<br />

120.3 The Contractor shall place slope stake at 50-foot intervals, where possible, on<br />

both sides of the roadway for the entire length of the project. The slope stakes<br />

shall consist of a wooden hub driven flush to the existing ground at the catch<br />

point with a four- foot lathe with a ribbon tied to the lathe. The appropriate fill or<br />

cut data shall be clearly written on the lathe. These shall be replaced as<br />

necessary and shall remain in place until the slope has been checked and<br />

approved by the Inspector.<br />

120.4 The Contractor shall place grade stakes at 50-foot intervals, where possible.<br />

Grade stakes shall be wooden hubs driven to the elevation of the edge of<br />

pavement and offset from the edge of pavement by a standard distance. The<br />

stakes shall remain in place, and shall be replaced if destroyed, until not longer<br />

needed.<br />

120.5 The Contractor shall place finish grade stakes at 50-feet interval. The<br />

Contractor shall demonstrate to the Contracting Officer that the various<br />

structural sections comply with allowable grade tolerances.<br />

SERIES 100 Page 6 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

121. TEMPORARY ACCESS, BRIDGES, CULVERTS, ROAD, ETC.<br />

121.1 The Contractor shall provide and maintain as long as required temporary road<br />

deviations, access roads, culverts, bridges, etc. as required facilitating the<br />

transport of materials and for the smooth construction of the work.<br />

121.2 On completion of the whole work and as directed by the Contracting Officer<br />

such temporary culverts, bridges, etc. that may have been constructed shall be<br />

removed by the Contractor and he shall make good any work disturbed during<br />

the removal.<br />

122. PUBLIC SERVICES<br />

122.1 The services identified on the drawings for adjustment or relocation are not<br />

based on field survey data. The Contractor shall verify the exact locations of<br />

these services and all other services that may exist along or across or adjacent<br />

to the works before beginning excavation work. The Contractor shall obtain<br />

permission from the C.O. and the respective <strong>Yap</strong> authority before adjusting or<br />

disturbing services of any utilities. Construction schedule shall have been<br />

approved before any work may begin on service relocation.<br />

122.2 Any damage that may occur to such services due to the negligence on the part<br />

of the Contractor or his employees, or to the improper execution of the<br />

Contracting Officer’s instruction shall be the responsibility of the Contractor who<br />

shall bear all costs for making good such damage.<br />

123. LIMITATIONS OF SITE<br />

123.1 The Contractor shall ensure that all his plant, materials, temporary workshops,<br />

store and offices shall be kept within the areas allotted to him by the<br />

Contracting Officer.<br />

123.2 Should the Contractor require additional land, outside the site for his workyards,<br />

workshops, stores, offices, temporary haul roads or any other temporary<br />

structures he shall make his own arrangements to acquire or rent so much as<br />

he may need subject to the approval by the Contracting Officer.<br />

124. COVERING UP OF WORK<br />

124.1 The Contractor shall not cover up, cast over, backfill or otherwise put out of<br />

view any work without the permission of the Contracting Officer and where<br />

directed by the Contracting Officer he shall take finish levels of the work and<br />

record these on Drawings to be signed as agreed by the Contractor and the<br />

Contracting Officer. The Contractor shall give due notice to the Contracting<br />

Officer whenever such works or foundation are ready for examination and the<br />

Contracting Officer shall attend without unreasonable delay for the purpose of<br />

examining and measuring unless he considers it unnecessary and advises the<br />

Contractor accordingly.<br />

SERIES 100 Page 7 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

124.2 If the Contractor cover up any works without the Contracting Officer’s<br />

permission, the Contractor at his own expense shall uncover or make openings<br />

in any parts of the work as and when directed by the Contracting Officer for the<br />

purpose of examination and shall reinstate and make good those parts to the<br />

satisfaction of the Contracting Officer.<br />

125. PROTECTION OF MATERIALS AND WORKS<br />

125.1 The Contractor shall provide at his own cost all things necessary for the proper<br />

protection and storage of materials to be used in the works and shall comply<br />

with manufacturer’s instructions and such directions as may be given by the<br />

Contracting Officer in this respect.<br />

125.2 The Contractor shall also his own cost provide all things necessary for the<br />

proper protection of completed works and works in progress and shall comply<br />

with such directions as may be given by the Contracting Officer in this respect.<br />

126. EXISTING ROADS AND CONVEYANCE OF PLANT AND MATERIALS<br />

126.1 The Contractor shall be responsible for any damage cause by his construction or<br />

construction traffic to any existing roads or culverts from whatsoever cause<br />

arising and shall repair and reinstate same to their original conditions to the<br />

satisfaction of the Contracting Officer and in addition shall keep such roads clear<br />

of slurry, boulders and loose earth resulting from the works.<br />

126.2 Should the Contractor not maintain, repair or reinstate the effected roads the<br />

cost of such maintenance and restoration shall be deducted from any monies<br />

due to or to become due to the Contractor under this contract.<br />

126.3 The Contractor shall arrange for the conveyance of materials and plant so as to<br />

cause a minimum of damage to existing roads and culverts and a minimum of<br />

inconvenience to the public and shall not deposit any earth, rubbish or materials<br />

upon any road, street, pavement or footway to the hindrance or obstruction of<br />

vehicles or pedestrians.<br />

127. CLEARING THE SITE ON COMPLETION<br />

127.1 On completion of the works and before the Contracting Officer issues the<br />

completion certificate, the Contractor shall dismantle and remove from the site<br />

all plant, temporary staging, traffic signs etc., temporary buildings, latrines,<br />

temporary water pipes and electricity cables and anything else not included in<br />

the works that is on site and as may be directed by the Contracting Officer.<br />

127.2 All areas shall be made good and all rubbish, debris and surplus materials shall<br />

be removed from the site and whole of the site and works shall be left in a clean<br />

and tidy condition to the satisfaction of the Contracting Officer.<br />

128. RESERVED<br />

SERIES 100 Page 8 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

129. PHOTOGRAPHS<br />

129.1 The Contractor shall supply progress photographs of a size not less that 4 X 6<br />

inches of such portions of the works in progress and completed as may be<br />

directed by the Contracting Officer each month. The camera used shall be of<br />

the SLR type and to the approval of the Contracting Officer. Photographs shall<br />

be supplied to the Contracting Officer within 14 days of the photograph being<br />

taken. The original copies of these photographs shall be the property of the<br />

Owner and no prints may be supplied to any person or persons except with the<br />

authority of the Owner or the Contracting Officer. A suitable typed subject and<br />

date taken must be visible in all the printouts. The Contractor and the<br />

Contracting Officer shall sign one copy of each photograph.<br />

130. EMPLOYMENT OF LOCAL LABOR, SUB-CONTRACTORS AND<br />

SUPPLIERS<br />

130.1 All labors, sub-contractors and suppliers used in connection with the works<br />

shall be employed from within the <strong>State</strong> where the works are situated. The<br />

Contractor shall immediately after taking possession of site, arrange with the<br />

local Labor Office or chief to affect such employment. Under no circumstances<br />

will Contractor be permitted to use imported laborers, sub-contractors and<br />

suppliers unless the Division of Manpower is satisfied that these are not<br />

available within the <strong>State</strong> of District concerned.<br />

131. EARTHMOVING AND DREDGING PERMITS<br />

131.1 Earthmoving Permit: The Contractor will not be allowed to execute any<br />

earthwork until the Contractor has procured an Earthmoving Permit. The<br />

Contractor is advised to procure the said Earthmoving Permit as soon as<br />

possible. Currently the Earthmoving Permit applications are processed by the<br />

Environmental Protection Agency (EPA), <strong>Yap</strong> <strong>State</strong>, and require approximately<br />

two months for approval.<br />

131.2 Dredging Permit: Dredge site is indicated on maps of Yyin Dredging Site. The<br />

Contractor shall supply all labor and equipments necessary to remove any<br />

deleterious materials and to obtain corals from the dredge site. The site shall<br />

be dredged in such a way that a navigable canal will be formed. The canal shall<br />

be at least one hundred (100) feet width and minimum ten (10) feet depth at<br />

mean low tide (dimensions will depend on the final environmental study).<br />

Should more dredged corals be required after the excavation of this canal, the<br />

canal may be widened to the extent approved by the C.O. The Contractor is<br />

not expected to pay royalties for dredging corals at the designated dredge site.<br />

However, it is recommended to verify before any dredging activity commences.<br />

No dredging will be allowed until the Contractor has procured an Earthmoving<br />

Permit. The Contractor is advised to consult C.O. for Dredging Permit.<br />

Currently the Dredging Permit applications are processed at the Environmental<br />

Protection Agency, <strong>Yap</strong> <strong>State</strong>.<br />

****** END OF SECTION ******<br />

SERIES 100 Page 9 of 9


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

SERIES 200<br />

ENVIRONMENTAL PROTECTION<br />

201. APPLICABLE PUBLICATIONS: The following publications listed below,<br />

including amendments and extensions effective as of the date of bid opening,<br />

but referred to thereafter by basic designation only, form a part of this<br />

specification to the extent indicated by references.<br />

201.1 <strong>Yap</strong> Environmental Protection Agency:<br />

201.1.1 Environmental Protection as amended or extended effective on date of bid<br />

opening.<br />

201.1.2 Regulations concerning the Control of Earthmoving and Sedimentation.<br />

201.1.3 Standards of Water Quality for the Waters.<br />

201.1.4 Earthmoving Permit (to be obtained by Contractor)<br />

(Note: This document will be made a part of the contract documents.)<br />

201.2 United <strong>State</strong>s <strong>Government</strong>:<br />

201.2.1 Federal Water Pollution Control Act, P.L. 92-500 as amended or extended<br />

effective on date of bid opening.<br />

202. ENVIRONMENT PROTECTION PLAN<br />

202.1 The Contractor shall be responsible for the preparation and submittal of an<br />

Environmental Protection Plan. After the contract is awarded, prior to the<br />

commencement of the work, the Contractor shall meet with the Contracting<br />

Officer, or his representative, and discuss the proposed Environmental<br />

Protection Plan. The meeting shall develop mutual understanding relative to<br />

details of environmental protection, including required reports and measures to<br />

be taken should the Contractor fail to provide adequate environmental<br />

protection in an adequate and timely manner. Not more than 14 days after the<br />

meeting, the Contractor shall submit for approval his proposed Environmental<br />

Protection Plan. The Contracting Officer before start of work by the Contractor<br />

shall approve this plan.<br />

202.2 The Contractor’s Environmental Protection Plan shall reflect the logical<br />

utilization of his available equipment, his scheme of operation, and the use of<br />

environmental protection devices specified herein.<br />

202.3 The plan must contain features that will satisfy the requirements of this Section<br />

and regulations concerning the control of earthmoving and sedimentation.<br />

Provisions shall be made in the plan for protecting existing trees which are to<br />

remain and which may be injured, bruised, defaced, or otherwise damaged by<br />

construction operations. Rocks that are displaced into un-cleared areas shall<br />

be removed. Monuments, markers, and works of art shall be protected before<br />

beginning operations. A pre-construction survey including photographs shall be<br />

SERIES 200 Page 1 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

accomplished by the Contractor and a report of survey furnished when required<br />

by the Contracting Officer.<br />

203. GENERAL REQUIREMENTS<br />

203.1 All applicable environmental protection measures of the F.S.M. and <strong>Yap</strong><br />

<strong>Government</strong>s are hereby incorporated in and made a part of these<br />

Specifications. All work performed by the Contractor and his subcontractors<br />

shall comply with the intent of all applicable publications.<br />

203.2 The Contractor shall provide and maintain environmental protection during the<br />

life of the contract as defined herein. Environmental protection shall be<br />

provided to correct conditions that develop during the construction period prior<br />

to the construction of permanent environmental protection features. Except<br />

where specifically exempted in this Contract, the Contractor’s operations shall<br />

comply with all federal and local regulations pertaining to water, air, solid waste<br />

and noise pollution. In the event that temporary additional environmental<br />

protection measures, over and above those described in the Environmental<br />

Protection Plan, are required due to the Contractor’s negligence, carelessness,<br />

or failure to provide permanent protection as part of the work scheduled, the<br />

Contractor shall take remedial action to correct the deficiencies at no additional<br />

cost. Failure to comply with all environmental protection measures outlined in<br />

this Section or as ordered by the Contracting Officer will be cause for<br />

suspension of work.<br />

204. DEFINITIONS<br />

204.1 Environmental Pollutions: Environmental pollution is defined as the presence<br />

of chemical physical or biological elements or agents that adversely affect<br />

human health or welfare; unfavorably alter ecological balances of importance to<br />

human life; affect other species of importance to man; or degrade the utilization<br />

of the environment for aesthetic and recreational purposes.<br />

204.2 Sediment: Sediment is soil that has been eroded and transported by runoff<br />

water. Sediment is also all water-borne and settled particles resulting from<br />

dredging operations including drag lining, handling, placing and disposal of<br />

dredged materials.<br />

204.3 Degradable Debris: Degradable debris is debris from demolition, clearing and<br />

construction, which can undergo biodegradation, combustion or be dissolved or<br />

suspended by water; including, but not limited to wood, paper, gypsum, unset<br />

cement, lime and natural vegetation and organic matter.<br />

204.4 Non-Degradable Debris: Non-degradable debris is inorganic or organic<br />

material from the demolition, clearing and construction that will not disintegrate<br />

nor dissolve when exposed to moisture or water and does not contain nor has<br />

been contaminated by any of the materials described under chemicals.<br />

204.5 Chemicals: Chemicals include petroleum products, bituminous materials,<br />

salts, acids, alkalies, and herbicides and pesticides.<br />

SERIES 200 Page 2 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

204.6 Sanitary Wastes: Sanitary waste consists of sewage and garbage. Sewage is<br />

defined as what is normally considered as domestic sanitary sewage. Garbage<br />

s defined as refuse and scraps resulting from preparation, cooking, dispensing<br />

and consumption of food.<br />

204.7 Project Limits: The project limits are generally defined as being within 20’ of<br />

either side of the work or to be within the road right of way. Construction<br />

activity shall be confined within these limits.<br />

204.8 Water Quality Boundary: The boundary where construction occurs beyond<br />

the shoreline, and at the dredge site is located 200 feet outside the project or<br />

dredge limits.<br />

205. PROTECTION OF NATURAL RESOURCES<br />

205.1 General: It is intended that the natural resources within the project boundaries<br />

and outside the limits of permanent work performed under this contract be<br />

preserved in their existing condition or be restored to an equivalent or improved<br />

condition upon completion of the work. The Contractor shall confine his<br />

construction activities to areas defined by the work schedule, drawings and<br />

specifications. Where there are no regulations covering specific protection of<br />

environment, United <strong>State</strong>s <strong>Government</strong> regulations shall apply.<br />

205.2 Land Resources: Except in areas indicate to be cleared, the Contractor shall<br />

not remove, cut, deface, or destroy trees or shrubs without special permission<br />

from the Contracting Officer. No ropes, cables, or guys shall be fastened to or<br />

attached to any existing nearby trees for anchorages unless specifically<br />

authorized. Where such special emergency use is permitted, the Contractor<br />

shall be responsible for any damage resulting from such use.<br />

205.2.1 Repair of Restoration: All trees or other landscape features scarred or<br />

damaged by the Contractor’s equipment or operations shall be repaired and/or<br />

restored to their original condition at the Contractor’s expense, to the<br />

satisfaction of the Contracting Officer.<br />

205.2.2 Temporary Construction: The Contractor shall obliterate all signs of temporary<br />

construction facilities such as haul roads, work areas, structures, foundations of<br />

temporary structures, stockpiles of excess or waste materials and all other<br />

vestiges of construction. Temporary roads, parking areas and similar temporary<br />

use areas shall be graded in conformance with surrounding areas, tilled and<br />

seeded. Seeding shall include topsoil and/or nutriment as necessary to<br />

establish a suitable stand of grass.<br />

205.3 Water Resources: All work under this contract shall be performed in such a<br />

manner that all adverse environmental impact is reduced to a level that is<br />

acceptable to the Contracting Officer.<br />

205.3.1 Stream Crossing: Stream crossings by fording with equipment shall be limited<br />

so as to control turbidity, and in areas of frequent crossings, temporary culverts<br />

or bridge structures shall be removed upon completion of the project and the<br />

SERIES 200 Page 3 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

area repaired in conformance with its original condition or as indicated or<br />

specified.<br />

205.3.2 Oily Substances: At all times, special measures shall be taken to prevent oily<br />

or other hazardous substances from entering the ground, drainage areas, or<br />

local bodies or water in such quantities as to affect normal use, aesthetics,<br />

produce a measurable ecological impact on the area.<br />

205.4 Fish and Wildlife Resources: The Contractor shall at all times perform all<br />

work and take such steps required to prevent any interferences of disturbance<br />

to fish and wildlife. The Contractor will not be permitted to alter water flows or<br />

otherwise significantly disturb native habitat adjacent to the project area which<br />

are critical to fish and wildlife except as may be indicated or specified.<br />

206. EROSION AND SEDIMENT CONTROL MEASURES<br />

206.1 Burnoff: Burnoff of ground cover will not be permitted.<br />

206.2 Borrow Areas: Borrow areas shall be managed and controlled to prevent<br />

sediment from entering nearby streams or lakes. Restoration of the areas,<br />

including areas outside the borrow area disturbed by the borrow and haul<br />

operations shall include grading, replacement of topsoil, and establishment or<br />

permanent vegetative cover.<br />

206.3 Reduction of Exposure of Unprotected Erodible Soils: Earthwork brought<br />

to final grade shall be finished as soon as practically possible, as indicated and<br />

specified. Side slopes and back slopes shall be protected as soon as<br />

practically possible upon completion of rough grading. All earthworks shall be<br />

planned and conducted in such a manner as to minimize the duration of<br />

exposure of unprotected soils.<br />

206.4 Temporary Protection of Erodible Soils: Such methods as may be<br />

necessary shall be utilized to effectively prevent erosion and control<br />

sedimentation, including but not limited to the following:<br />

206.4.1 Mechanical Retardation and Control of Runoff: The rate of runoff from the<br />

construction site shall be mechanically retarded and controlled. This included<br />

construction of diversion ditches, benches, and berms to retard and divert<br />

runoff to protected drainage courses.<br />

206.4.2 Borrow: Borrow will not be permitted in areas where suitable environmental<br />

controls are not possible.<br />

206.4.3 Vegetation and Mulch: Temporary protection shall be provided all exposed<br />

earth surfaces as soon as rough grading or trench backfill is completed or<br />

sufficient soil is exposed to required protection to prevent erosion. Such<br />

protection shall be by accelerated growth of permanent vegetation, temporary<br />

vegetation, mulching or netting. Slopes too steep for stabilization by other<br />

means shall be stabilized by hydro-seeding, mulching anchored in place,<br />

covering by anchored netting, sodding, or such combination of these and other<br />

methods as may be necessary for effective erosion control.<br />

SERIES 200 Page 4 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

206.5 Sediment Basins: Sediment shall be trapped in temporary or permanent<br />

sediment basins. The basins shall be designed (sized) according to recognized<br />

engineering practice.<br />

206.6 Sediment Retention at Dragline Site<br />

206.6.1 General: The Contractor shall provide sedimentation retention booms,<br />

confining embankments, and/or other devices in order to confine siltation<br />

generated by dragline activities within Water Quality Boundaries. Dragline<br />

operations shall be limited to authorized areas and shall not degrade<br />

waters outside of the Water Quality Boundary below the Standards of<br />

Water Quality for the waters. The Contractor shall limit all effluent from<br />

dragline operations to areas within confining embankments. The<br />

Contractor shall obtain an earthmoving permit for fill placed in tidal waters<br />

at the dredging site prior to start of fill operations.<br />

206.6.2 Sedimentation Retention Booms: Sedimentation retention booms made<br />

of synthetic rubber of pliable plastic shall be deployed around all dragline<br />

areas and all areas of work within waters near shore to limit the effects of<br />

siltation to these immediate areas. The sedimentation retention booms<br />

shall have a continuous float not less than 24 inches in diameter along top<br />

edge. The boom shall be sufficiently weighted along the bottom edge and<br />

shall be anchored to the bottom to prevent floating or kiting. When properly<br />

deployed the sedimentation retention boom shall hang vertically in the<br />

water. The sedimentation retention boom shall have “skirt” lengths<br />

sufficient to meet Environmental Protection regulations and shall be<br />

sufficiently long to confine siltation within the water quality boundary. The<br />

Contractor shall deploy the sedimentation retention booms in a manner that<br />

essentially creates a totally confined area around dredge and/or dredge<br />

disposal areas or other work areas. Prior to construction, the Contractor<br />

shall submit to the Contracting Officer for approval, samples, catalogues, or<br />

shop drawings of the Sedimentation Retention Booms he proposes to use.<br />

Work within near shore areas shall not commence prior to receiving<br />

approval of the proposed booms and methods of use.<br />

206.6.3 Spillages: Care shall be taken to ensure that petroleum products,<br />

bituminous materials “without the approval from the Environmental<br />

Protection Agency” or other deleterious substances including debris are not<br />

allowed to fall, flow, leach or otherwise enter the water.<br />

207. CONTROL AND DISPOSAL OF SOLID WASTE AND CHEMICAL AND<br />

SANITARY WASTES<br />

207.1 General: Waste shall be picked up and placed in containers, which are<br />

emptied on a regular schedule. All handling and disposal shall be so conducted<br />

as to prevent contamination of the site and any other areas. On completion, the<br />

areas shall be left clean and natural looking. All signs of temporary construction<br />

and activities incidental to construction of the required permanent work in place<br />

shall be obliterated.<br />

SERIES 200 Page 5 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

207.2 Disposal of Rubbish and Debris: The Contractor transport all waste off the<br />

project site and dispose of it at the Dalipebinaw sanitary landfill site or other<br />

approved site in manner that complies with <strong>Government</strong> and local<br />

requirements, or as directed by the Contracting Officer. The Contractor shall<br />

provide the Contracting Officer a copy of the <strong>Government</strong> and/or local permit or<br />

license, which reflects such agency’s approval and compliance with their solid<br />

waste disposal regulations. The permit or license and the location of the<br />

disposal area shall be provided prior to transporting any material off the project<br />

site.<br />

207.3 Sewage, Odor and Pest Control: Sewage shall be disposed of through<br />

connection of municipal or district sanitary sewage systems. Where such<br />

systems are not available, chemical toilets or comparably effective units shall<br />

be used with wastes periodically emptied into municipal or district sanitary<br />

sewage system. Provisions shall be included for pest control and for masking<br />

or elimination of odors.<br />

207.4 Chemical Waste: Chemical waste shall be stored in corrosion resistant<br />

containers, removed from the project site and disposed of, a minimum of once a<br />

month unless directed otherwise. Disposal of chemical waste shall be in<br />

accordance with standard established practices. Fueling and lubricating of<br />

equipment and motor vehicles shall be conducted in a manner that affords the<br />

maximum protection against spills and evaporation. Lubricants to be discarded<br />

and burned soil shall be disposed of in accordance with procedures meeting<br />

<strong>Government</strong> and local regulations. For oil and hazardous material spills, which<br />

may be large enough to violate <strong>Government</strong> and local regulations, the<br />

Contracting Officer shall be notified immediately.<br />

207.5 Garbage Disposal: The Contractor shall transport garbage to the dumpsite<br />

subject to approval of the Contracting Officer.<br />

207.6 Sanitary waste shall be disposed of through chemical toilets or comparably<br />

effective units with wastes periodically emptied into the Colonia wastewater<br />

treatment plant. In no case will sanitary waste discharge to the ground be<br />

allowed. Provisions shall be included for masking or elimination of odors.<br />

208. DUST CONTROL:<br />

Dust shall be kept down at all times, including non-working hours, weekends<br />

and holidays. Soil at the site, haul roads and other areas disturbed by the<br />

Contractor’s operations shall be sprinkled or treated with dust suppressors as<br />

necessary to control dust. No dry power brooming will be permitted.<br />

Vacuuming wet mopping; wet sweeping or wet power brooming shall be used<br />

instead. Air blowing will be permitted only cleaning off non-particulate debris,<br />

such as reinforcing bars. No sandblasting will be permitted unless the dust<br />

thereform is confined. Only wet cutting of concrete blocks, concrete and<br />

asphalt will be permitted. No unnecessary shaking of bags will be permitted<br />

where concrete mortar and plaster mixing is done.<br />

209. NOISE:<br />

The maximum use of “low-noise-emission products” as certified by the<br />

Environmental Protection Agency shall be made when available. No blasting or<br />

SERIES 200 Page 6 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

use of explosives will be permitted without written permission of the Contracting<br />

Officer and then only during the designated times. Unless directed otherwise,<br />

the time for such operations shall be confined to the period between 8:00 a.m.<br />

and 6:00 p.m. Monday thru Friday unless otherwise specified in the<br />

Earthmoving Permit.<br />

210. RECORDING AND PRESERVING HISTORICAL AND ARCHEOLOGICAL<br />

FINDS:<br />

All items having any apparent historical or archaeological interest, which are<br />

discovered in the course of any construction activities, shall be carefully<br />

preserved. The Contractor shall leave the archeological find undisturbed and<br />

shall immediately report the find to the Contracting Officer who will notify the<br />

proper authorities. Such items shall not become the property of the Contractor<br />

unless specifically approved by the Contracting Officer.<br />

211. CLEAN AIR AND WATER POLLUTION CONTROL REQUIREMENTS FOR<br />

ALL CONSTRUCTION CONTRACTS AND SUBCONTRACTS EXCEEDING<br />

$100,000:<br />

211.1 Contractors and Subcontractors agree:<br />

211.1.1 That any facility to be used in the performance of the contract or to benefit<br />

from the contract is not listed on the Environmental Protection Agency<br />

(EPA) List of Violating Facilities.<br />

211.1.2 To comply with all the requirements of Section 114 of Clean Air Act and<br />

Section 608 of the Federal Water Pollution Control Act and all regulations<br />

issued thereunder.<br />

211.1.3 That, as a condition for award of a contract they will notify the awarding<br />

official of the receipt of any communication from the EPA indicating that a<br />

facility to be utilized for performance of or benefit from the contract is under<br />

consideration to be listed on the EPA List of Violating Facilities.<br />

211.1.4 To include or cause to be included in any contract or subcontract, which<br />

exceeds $100,000 the aforementioned criteria and requirements.<br />

****** END OF SECTION ******<br />

SERIES 200 Page 7 of 7


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

SERIES 300<br />

ARCHAEOLOGICAL DEPOSITS AND RECOVERY<br />

301. INTENT<br />

301.1 The intent of this Section is to alert the Contractor about the archaeological<br />

deposits that exist, in fact and in theory, on or about the site. In general,<br />

archaeological deposits include:<br />

301.1.1 <strong>Yap</strong>ese stone money.<br />

301.1.2 <strong>Yap</strong>ese stone money platforms.<br />

301.1.3 Japanese graves (circa 1941-1946.)<br />

301.1.4 World War II relics.<br />

301.1.5 <strong>Yap</strong>ese graves and items of cultural interest (these may have been<br />

hidden or buried by the <strong>Yap</strong>ese during the Japanese occupation of the<br />

islands).<br />

301.1.6 American items of cultural interest (these may been appropriated by<br />

Japanese troops during World War II).<br />

301.2 All artifacts, graves or otherwise, potentially have historical interest and value<br />

and shall be preserved in accordance with the requirements of this Section and<br />

as shown on the drawings.<br />

302. GENERAL LOCATION<br />

302.1 Graves may be located within and near the construction areas. In addition,<br />

artifacts of potential historical significance, whether foreign or indigenous to<br />

Micronesia, and <strong>Yap</strong> particularly, may be found in the project area. It is possible<br />

(unlikely) that the Contractor may discover graves during the progress of<br />

construction.<br />

303. PROCEDURES<br />

303.1 All graves and artifacts discovered within the limits of work during the course of<br />

construction shall be marked by stakes establishing the locations in the<br />

discovery areas and shall not be disturbed in any manner.<br />

303.2 The Contracting Officer shall be notified as to the discovery and location as<br />

soon as possible.<br />

303.3 All graves, artifacts, and other items of historical significance and so recognized<br />

by the Contracting Officer and discovered outside or beyond the limits of work,<br />

shall remain undisturbed and protected.<br />

SERIES 300 Page 1 of 2


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

303.4 All graves, stone money, artifacts, and other items of historical significance and<br />

so recognized by the Contracting Officer, and which are immediately adjacent<br />

to the construction area shall remain undisturbed and marked and protected as<br />

specified earlier in Clause 303.1.<br />

303.5 Hazard of Unexploded Ordinance:<br />

Unexploded ordinance may be encountered during the construction of the<br />

project. The Contractor shall employ extreme diligence when performing any<br />

clearing, grubbing, grading, excavation, trenching or dredging. Any explosive<br />

device found should be reported to the Contracting Officer who will effect<br />

removal.<br />

304. RELOCATION OF STONE MONEY<br />

304.1 For stone money to be relocated, the <strong>Yap</strong>ese Owners of the stone money shall<br />

move and place all stone money to its final location. The Contractor shall<br />

provide assistance of equipment use including operator as requested by the<br />

Contracting Officer. Such assistance shall be at no additional cost to the<br />

Owner. The Contractor will not be liable for any damage to artifacts that are<br />

being salvaged by Owners with the Contractor assistance under property<br />

Owner’s direction.<br />

304.2 Prior to movement of any stone money, the Contractor shall notify the<br />

Contracting Officer at least 14 days in advance in writing.<br />

304.3 All other stone money to remain shall be protected in accordance with this<br />

section.<br />

305. RECORD REPORTS<br />

305.1 It is assumed that there may be archaeological deposits buried within the<br />

project area; thus, all precautions shall be taken to minimize subsurface and<br />

surface disturbance. The procedure governing archaeological deposits shall be<br />

in accordance with the requirements of Clause 303.<br />

305.2 All excavation equipment operation shall be given instruction on reporting any<br />

archaeological datum to their supervisors, who in turn shall report to the<br />

Contracting Officer.<br />

305.3 The Contractor in quadruplicate shall prepare a record of all findings, three<br />

copies of it shall be turned over the Contracting Officer, and the Contractor for<br />

his record shall retain the other copy.<br />

****** END OF SECTION ******<br />

SERIES 300 Page 2 of 2


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

SERIES 500<br />

MAINTAINING OF TRAFFIC<br />

501. GENERAL REQUIREMENTS<br />

501.1 Traffic control and safety devices shall be in accordance with Part VI of the<br />

Manual of Uniform Control Devices for Streets and Highways: U.S. Federal<br />

Highway Administration, hereafter referred to as the Traffic Devices Manual.<br />

501.2 Prior to beginning work, the Contractor shall submit to the Contracting Officer<br />

for approval the methods and schedule for traffic control indicating the number<br />

of lanes and detours within and along the public used thoroughfares. The<br />

Contractor shall also include a schedule listing the types and numbers of traffic<br />

control and safety devices proposed for use.<br />

501.3 Each road subject to construction activity shall be open to a minimum of onelane<br />

traffic during working hours except as approved or authorized by the<br />

Contracting Officer. Two-way, two-lane traffic shall be maintained during all<br />

non-working hours except at select construction points where self-regulating<br />

on-lane traffic shall be permitted as approved or directed by the Contracting<br />

Officer.<br />

501.4 Unless otherwise approved or directed by the Contracting Officer, the minimum<br />

widths for one-lane and two-lane traffic shall be 10 feet and 14 feet,<br />

respectively.<br />

502. TRAFFIC CONTROL DEVICES<br />

502.1 Traffic control devices shall conform to the applicable specifications, standards<br />

and principles of the Traffic Devices Manual except as amended herein. The<br />

traffic control devices shall be used at the site for construction, engineering<br />

surveys, and related work that might endanger passing motorists, pedestrians<br />

and workers.<br />

502.2 Traffic control devices shall be in the place prior to the start of any construction,<br />

maintenance, engineering survey, and related work and shall not be removed<br />

until the obstruction or danger of obstruction no longer exists. Where work is<br />

performed in stages, there shall be in place those devices that apply to the<br />

conditions and activities present during the stage in progress.<br />

502.3 Prior to the installation of any traffic control device, the Contractor shall notify the<br />

Contracting Officer who shall in turn notify the Fire Departments, the Police<br />

Department, the Ambulance Service, and Department of Public Works and<br />

Transportation and apprise those agencies of the locations of the traffic devices.<br />

502.4 All signs, markers, barricades, cones, lights, and other devices indicating the<br />

existence of special conditions and activities shall remain in place until their<br />

need is no longer required, unless otherwise directed by the Contracting Officer.<br />

Signs that do not apply to existing conditions and activities shall be removed or<br />

covered. All devices employed shall be neatly constructed and shall be<br />

SERIES 500 Page 1 of 2


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

repaired, cleaned, repainted, and properly maintained in good condition. Special<br />

care shall be taken to see that shrubbery, construction materials, equipment,<br />

spoil and other obstructions do not obscure any sign, light or barricade,<br />

particularly at intersections or curves.<br />

502.5 When it becomes necessary to excavate along or across a highway or any lane<br />

thereof, the work shall be performed to avoid existing local peak traffic hours.<br />

Trenches shall be excavated to maintain at least one lane at all times. A selfregulated<br />

one-lane road will be permitted if approved by the Contracting Officer.<br />

See paragraph “BARRIERS AND CHANNELIZING DEVICES” below.<br />

503. SIGNS<br />

503.1 Regulatory signs, warning signs, and guide signs use at construction, surveying<br />

or other work sites shall be reflectorized and shall conform to the basic<br />

standards prescribed in the Traffic Devices Manual and as specified in the<br />

applicable Sections of the Specifications. Generally, signs shall be placed in the<br />

most effective locations so as to assure the fastest and most adequate driver<br />

response time. All advance-warning signs shall indicate the general character of<br />

the work being done and the distance from the sign to the actual work area.<br />

Where the speed limit is 25 miles per hour or less, an advance warning sign<br />

shall be placed on each approach affected by the work, approximately 150 to<br />

200 feet in advance of the actual work area.<br />

503.2 The Contracting Officer may waive any requirements specified herein if advance<br />

application is made by the Contractor when, in his judgment, the placement of<br />

signs may not be feasible for such placement may interfere with the progress of<br />

the work.<br />

504. BARRIERS AND CHANNEL DEVICES<br />

504.1 Barriers and channelizing devices used at work sites shall follow the basic<br />

standards prescribed in the Traffic Devices Manual and following provisions.<br />

504.2 When it is necessary to confine the traffic to singular lanes, additional transverse<br />

barricades and drums shall be placed at close intervals (approximately 120-foot<br />

spacing on tangents and curves of more than 500-foor radius and approximately<br />

60-foot spacing on curves of 500-foot radius and less) in the closed lane.<br />

****** END OF SECTION ******<br />

SERIES 500 Page 2 of 2


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

SERIES 900<br />

SUBBASE COURSE<br />

Additional Requirements for Subbase Course Section 32 11 35.<br />

901. APPLICABLE PUBLICATIONS<br />

The following publications of the issues listed, but referred to thereafter by basic<br />

designation only, form a part of this specification to the extent indicated by the reference<br />

thereto:<br />

901.1 American Society for Testing and Materials (ASTM) Publications:<br />

D423-66 Liquid Limit of Soils (1972)<br />

D424-59 Plastic Limit and Plasticity<br />

(1971) Index of Soils<br />

D1556-82 Density of Soil In-Place by the Sand-Cone (1974) Method<br />

D1557-78 Moisture-Density Relations of Soils Using 10-lb. (4.5 Kg.)<br />

Hammer and 18-inch (457mm) Drop<br />

D1883-73 Bearing Ratio of Laboratory-Compacted Soils<br />

D2922-81 Density of Soil and Soil-Aggregate in Place by Nuclear<br />

Methods (Shallow Depth)<br />

902. QUALITY CONTROL: Approvals, except those required for field installations,<br />

field applications, and field tests, shall be obtained before delivery of material or<br />

equipment to the project site.<br />

903. SUBMITTALS: Certified Laboratory Test Reports: Before delivery of materials,<br />

certified copies of the reports of all tests required in referenced publications<br />

shall be submitted to the Contracting Officer. The testing shall have been<br />

performed in an independent laboratory approved by the Contracting Officer.<br />

Certified test reports are required for the coral material.<br />

904. DELIVERY AND STORAGE: Materials delivered to the site shall be unloaded<br />

and stored with a minimum of handling. Aggregates shall be stored in such a<br />

manner as to prevent segregation.<br />

905. MATERIALS: In addition to the Technical Specifications Section 32 11 35,<br />

The subbase material can be dredged ledge coral and containing sand, soil or<br />

other similar binding or filler material. The Contractor shall not use materials<br />

from existing roadbed excavations as subbase material.<br />

The dredged coral shall have the following properties: -<br />

Gradation: Sieve Size % Passing by Weight<br />

4 inch 100<br />

2-1/2 inch 90 -100<br />

SERIES 900 Page 1 of 4


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

No 4 40 -90<br />

No 200 3 – 25<br />

CBR – 40% min. Liquid Limit – 40% max. Plasticity Index – 15 max<br />

906. CONSTRUCTION EQUIPMENT: The Contractor shall submit a list of<br />

construction equipment to the Contracting Officer for approval.<br />

907. GENERAL REQUIREMENTS: The subbase shall be composed of granular<br />

materials constructed on a prepared subgrade. The subbase course shall be<br />

provided where indicated and shall be shaped and compacted thoroughly within<br />

the tolerances specified. Subbase courses shall not be constructed when<br />

weather conditions detrimentally affect the quality of the finished course. Areas<br />

of the subbase course that are damaged by the affects of weather conditions<br />

during any phase of the construction, shall be aerated, if required, reshaped,<br />

and re-compacted at no additional cost to the Owner. Line and grade stakes<br />

shall be provided as necessary for control. Grade stakes shall be placed in<br />

lanes parallel to the centerline of the areas to be paved, and suitably spaced for<br />

string lining.<br />

908. CONSTRUCTION<br />

908.1 Placing: The subgrade shall be cleaned of all foreign substances for proper<br />

compaction and smoothness before placement of subbase course. Material<br />

shall be placed and compacted in maximum 6” compacted lifts.<br />

908.1.1 Spreading of fine material over the surface of the compacted material is<br />

prohibited. Additional material if required shall be incorporated uniformly<br />

without segregation, throughout the thickness of the compacted material by<br />

scarifying and blading. The combined material shall meet all quality<br />

requirements specified herein.<br />

908.2 Compacting and Finishing: Layers of subbase course materials shall be<br />

compacted by rolling with tamping rollers three-wheel general purpose rollers,<br />

pneumatic-tired rollers, vibratory rollers, grid rollers or tractors, or by<br />

combinations thereof or by other approved equipment. Compaction shall be<br />

continued until the layer or layers are compacted through the full depth to at<br />

least 100 percent of the maximum density as determined by ASTM D1557.<br />

During rolling operations the material shall be maintained within 2 percent of the<br />

specified optimum moisture content to aid compaction to the density required.<br />

The surface of the layer shall be finished by blading or rolling with three-wheel<br />

general purpose rollers or light pneumatic-tired roller, or combinations thereof.<br />

In all places not accessible to the rolling equipment, the subbase material shall<br />

be compacted by mechanical tamping. Blading, rolling, and tamping shall<br />

continue until the surface is smooth and free from waves and irregularities. If at<br />

any time the subbase material is excessively moistened by rain during<br />

construction, it shall be aerated by means of blades, graders harrows, or other<br />

suitable equipment, until the moisture is controlled, and the required density is<br />

obtained. The subbase shall be maintained until the construction of the next<br />

course.<br />

SERIES 900 Page 2 of 4


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

909. MAINTENANCE: After construction is completed, the subbase shall be<br />

maintained throughout except where portions of the succeeding course are<br />

under construction thereon. Maintenance shall include drainage, rolling,<br />

shaping, and watering as necessary to maintain the course in proper condition.<br />

Deficiencies in thickness, composition, construction, smoothness, or density,<br />

which develop during the maintenance, shall be corrected by the Contractor to<br />

conform to the requirements specified hereinbefore. Sufficient moisture shall<br />

be maintained at the surface to prevent a dusty condition, by sprinkling with<br />

water.<br />

910. TESTING<br />

910.1 The Contractor at no additional cost to the Owner shall perform testing.<br />

910.1.1 Aggregate Testing: all aggregate tests shall be made on the initial source<br />

samples, and shall be repeated when there is a change of source. The<br />

tests shall include an analysis of the combined material representing the<br />

aggregate part of the mix. The Contracting Officer may request or make<br />

additional tests at random at expense of the Contractor. Four samples<br />

each shall be taken for gradation, liquid limit, plasticity index and CBR tests<br />

from each source approved.<br />

910.1.2 GRADATION: Gradation Test shall be performed at least once a day.<br />

910.1.3 CBR Tests: CBR tests shall be performed for each source in conformance<br />

with ASTM D1883.<br />

910.1.4 Liquid Limit and Plasticity Index: Liquid Limit and Plastic Limit shall be<br />

performed for each source in conformance with ASTM D423, and D424,<br />

respectively.<br />

910.1.5 Soundness Test: The material shall be hard, durable particles or<br />

fragments of coral or schist and shall be free of vegetable matter, lumps or<br />

balls of clay.<br />

910.1.6 Smoothness Test: Surface deviations in excess of 3/8 inch, when tested<br />

with a 10-foot straightedge applied parallel with and at right angles to the<br />

center line of the area to be paved, shall be corrected by loosening, adding<br />

and/or removing material, reshaping and re-compacting.<br />

910.1.7 Field Determination of Density: Field determination of density shall be in<br />

accordance with ASTM D1556 or ASTM D2922. One test shall be<br />

conducted for each 250 linear feet or at least once a day.<br />

910.1.8 Laboratory Density Tests: Laboratory density tests shall be performed in<br />

accordance with Method D, ASTM D1557, with the following modification:<br />

(1) all materials passing 2-inch sieve and retained on a ¾ inch sieve shall<br />

be removed and replaced with an equal portion of material between the No.<br />

4 and ¾ inch sieves, and (2) a separate batch of material shall be used for<br />

each compaction test specimen. No material shall be reused for<br />

SERIES 900 Page 3 of 4


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

compaction tests. One test shall be conducted for each 2,500 cubic yards<br />

of material.<br />

910.1.9 Thickness: The thickness of the completed subbase course shall be<br />

measured at intervals in such a manner that there will be a depth<br />

measurement for at least each 500 square yards of completed subbase<br />

course. The depth measurements shall be made by test holes, at least 3<br />

inches in diameter, through the subbase course. Deficiencies in thickness<br />

greater than ½ inch in diameter shall be corrected by scarifying such areas,<br />

adding mixture of proper gradation, re-blading, and re-compacting.<br />

****** END OF SECTION ******<br />

SERIES 900 Page 4 of 4


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

SERIES 1000<br />

PORTLAND CEMENT STABILIZED BASE COURSE<br />

Additional Requirements for Cement Treated Base Course Section 32 11 34.<br />

1001 APPLICABLE PUBLICATIONS: The following publications of the issues listed<br />

below, but referred to thereafter by basic designation only, form a part of this<br />

specification to the extent indicated by the references thereto.<br />

1001.1 Federal Specification:<br />

1001.2 SS-C-1960-3A Cement, Portland<br />

1001.3 American Society for Testing and Materials (ASTM) Publications:<br />

C117-87 Materials Finer then No. 200 (75-m) Sieve in Mineral<br />

Aggregates by Washing<br />

C-136-82<br />

Sieve or screen Analysis of Fine and Coarse<br />

Aggregates<br />

D75-82 Sampling Aggregates<br />

D420-69 Investigating and Sampling Soils and Rocks for<br />

(1969) Engineering Purposes<br />

D423-66 Liquid Limit of Soils<br />

(1972)<br />

D424-59 Plastic Limit and Plasticity Index Soils<br />

(1971)<br />

D558-82 Moisture-Density Relations of Soil-Cement<br />

(1970) Mixtures<br />

D1556-82 Density of Soil in Place by the Sand-Cone Method<br />

(1974)<br />

1002 GENERAL REQUIREMENTS:<br />

The base course shall be composed of graded coral aggregate or graded<br />

aggregate manufactured from quarry-run rock of an approved source, and<br />

cement uniformly blended together, mixed with water, spread, shaped and<br />

compacted in accordance with these specifications and in conformity to the<br />

lines, grades, dimensions, and typical sections shown. Base shall not be<br />

constructed when whether conditions detrimentally affect the quality of the<br />

finished course. Areas of the base that are damaged by the effects of weather<br />

conditions during any phase of the construction shall be aerated, if required,<br />

reshaped, and re-compacted at no additional cost to the Owner. Adequate<br />

drainage shall be provided during the entire construction period to prevent<br />

water from collecting or standing on the area to be stabilized or on the<br />

pulverized, mixed, or partially mixed material. Line and grade stakes shall be<br />

SERIES 1000 Page 1 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

provided as necessary for control. Grade stakes shall be placed in lanes<br />

parallel to the centerline of the areas under construction, and suitably spaced<br />

for string lining.<br />

1002.1 Definition of ‘Soil Cement’ in this series shall mean a mixture of graded<br />

corals, cement and water.<br />

1003 MATERIALS<br />

1003.1 Cement: ASTM C150, Type II.<br />

1003.2 Dredged Coral: Dredged ledge coral shall be obtained from designated<br />

dredge sites and may contain sand or other similar binding material. But<br />

should not contain any material deleterious to construction or finishing of<br />

the Base Course. The dredged coral shall have the following properties: -<br />

GRADATION: Sieve Size Percent Passing by Weight<br />

1-inch 100<br />

No. 4 35-75<br />

No. 40 15-35<br />

No. 200 2-15<br />

A minimum CBR of 100% at 7-days after cement stabilization. The portion<br />

of the dredged coral, including any blended materials, passing the No. 40<br />

mesh sieve shall have a liquid limit of not more than 25 and a plasticity<br />

index of not more than 6 when tested in accordance with ASTM D423 and<br />

D424.<br />

1003.3 Water: Water shall be clean, fresh, and free from injurious amounts of oil,<br />

acid, salt, alkali, organic matter, and other substances deleterious to the<br />

hardening of soil-cement, and shall be subject to approval<br />

1004. CONSTRUCTION EQUIPMENT<br />

1004.1 The Contractor shall submit a list of all construction equipment to the<br />

Contracting Officer for review 30 days prior to shipping the equipment to <strong>Yap</strong>.<br />

All equipment shall be dependable and adequate for the purpose intended and<br />

shall be properly maintained in satisfactory and safe operating condition at all<br />

times. Calibrated equipment such as scales, batching equipment, spreaders<br />

and similar equipment, shall have been recalibrated by a calibration laboratory<br />

recommended by the Contractor and approved by the Contracting Officer<br />

before shipping to <strong>Yap</strong>. Additional recalibration shall be done by the<br />

Contractor. The list of equipment shall include the make, model, serial number<br />

and the date on which the calibrated equipment was last recalibrated.<br />

1004.2 Rollers:<br />

1004.2.1 Steel-wheel roller shall be the self-propelled, three-wheel or tandem<br />

type, weighing not less than 10-tons, and shall be suitable for rolling<br />

soil-cement mixtures. The wheels shall be equipped with adjustable<br />

scrapers.<br />

SERIES 1000 Page 2 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

1004.2.2 Rubber-tired rollers shall be self-propelled and equipped with not less<br />

than nine rubber-tired wheels mounted on two axles in such manner<br />

than the rear group of tires will not follow in the tracks of the forward<br />

group. The rubber-tired roller shall also be equipped with suitable<br />

boxes or platforms for ballast loading and shall be loaded as directed.<br />

The tires shall be uniformly inflated.<br />

1004.2.3 Pneumatic-Tired Rollers: Pneumatic-tired rollers shall be single or<br />

double axle, vibrating or non-vibrating type equipment with tires of<br />

equal size and diameter, uniformly inflated so that the air pressure of<br />

the several tires shall not vary more than 5-pounds per square inch<br />

(psi). Rollers may be self-propelled or towed by a suitable power unit.<br />

The self propelled roller or the power unit and towed roller shall be<br />

considered a pneumatic-tired roller unit.<br />

1004.2.4 Light-Pneumatic-tired rollers shall have low axles on which are<br />

mounted not less than nine pneumatic-tired wheels in such a manner<br />

that the rear group of tires will not follow in the tracks of the forward<br />

group. The axles shall be mounted in a rigid frame provided with a<br />

loading platform or body suitable for ballast loading. The roller shall<br />

develop a load of not less than 22 pounds per inch width or tire tread<br />

and shall be capable of being loaded to provide loads up to 30 pounds<br />

per inch or normal tire width.<br />

1004.2.5 Heavy Pneumatic-Tired Rollers: Heavy pneumatic-tired rollers shall be<br />

of the vibratory or non-vibratory type with a minimum loading of 25,000<br />

pounds per tire. The loading shall be distributed equally to all wheels.<br />

1004.2.6 Vibrating Rollers: Vibrating rollers shall be the self-propelled type of a<br />

minimum static weight of 10-tons.<br />

1004.3 Blade Graders: Blade graders shall have a wheelbase of not less than 15-<br />

feet, a blade of not less than 12-feet, and shall be self-propelled.<br />

1004.4 Scarifier: Scarifiers shall have two rows of teeth with the teeth in each row not<br />

more than 8-inches apart. The rows shall be staggered so that the paths of the<br />

teeth will not be more than 4-inches apart.<br />

1004.5 Hauling Equipment: Hauling equipment shall consist of pneumatic tired<br />

vehicles having dump bodies suitable for dumping materials in windrows (for<br />

traveling plant method) or into spreading machines. Dump trucks shall be<br />

equipped with tailgates, which can be chained to proper opening to prevent<br />

segregation during dumping.<br />

1004.6 Power Brooms and Power Blowers: Power brooms and power blowers shall<br />

be suitable types for effectively cleaning prepared sub-grades, sub-bases, and<br />

base courses.<br />

1004.7 Sprinkling Equipment: Sprinkling equipment shall consist of tank trucks,<br />

pressure distributors, or other equipment designated to apply water uniformly<br />

and at controlled quantities to variable widths of surface.<br />

SERIES 1000 Page 3 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

1004.8 Mixing Plants: Mixing plants shall be so designed and constructed as to<br />

thoroughly mix the aggregates, cement, and water. The plants shall be<br />

equipped to accurately measure the required amounts of cement and water<br />

while the plants are in operation.<br />

1004.9 Mechanical Spreader: Mechanical Spreader shall be self-propelled or<br />

attached to a propelling unit capable of moving the spreader and material truck.<br />

The device shall be steer-able and shall have variable speed forward and<br />

reverse. The spreader and propelling unit shall be carried on tracks, rubber<br />

tires, or drum-type wheel rollers that will not disturb the sub-grade, sub-base, or<br />

underlying base-course layer. The spreader shall contain a hopper, an<br />

adjustable screed, and outboard bumper rolls and shall be so designed that<br />

there will be a uniform, steady flow of material from the hopper. The spreader<br />

shall be capable of laying material across the full width of the lane to a uniform<br />

thickness and to uniform loose density so that when compacted the layer or<br />

layers will conform to the thickness and grade requirements indicated.<br />

1004.10 Tampers: Tampers shall be an approved mechanical type, operated either by<br />

pneumatic pressure or by internal combustion. Tampers shall have sufficient<br />

weight and striking power to produce the compaction required.<br />

1004.11 Miscellaneous Equipment: Miscellaneous equipment such as tractors,<br />

windrow equalizers, plows, adjustable spike-tooth harrows, and discs shall be<br />

suitable for construction of soil cement stabilized courses.<br />

1005. CONSTRUCTION<br />

1005.1 General: When application of water and mixing are completed, the moisture<br />

content in the mixture, on the basis of dry weight, shall be within 10% of the<br />

specified optimum moisture content of the mixture. When the stabilized course<br />

is constructed in more than one layer, the previously constructed layers shall be<br />

cleaned of loose and foreign matter by sweeping with power sweepers or power<br />

brooms, except that hand brooms may be used where permitted by the<br />

Contracting Officer.<br />

1005.2 Stockpiling of Material: Material shall be stockpiled in the manner and at the<br />

locations approved by the Contracting Officer. Prior to stockpiling of material,<br />

the storage sites shall be cleared, drained, and leveled.<br />

1005.3 Preparation of Sub-base: Soft-yielding spots and ruts or other irregularities in<br />

the surface shall be corrected. The material in the affected areas shall be<br />

loosened and unsatisfactory material removed. Approved select material shall<br />

be added where required. The area shall then be shaped to line, grade, and<br />

cross section, and shall be compacted to the specified density requirements as<br />

directed.<br />

1005.4 Fixed Grades: The finished and completed stabilized area shall conform to the<br />

lines, grades, cross section, and dimensions indicated. The lines and grades<br />

indicated shall be maintained by means of line and grade stakes placed at the<br />

site of the work.<br />

SERIES 1000 Page 4 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

1005.5 Mixing and Placing Materials:<br />

1005.5.1 Central-Plant Method: A pugmill may be used to mix aggregate,<br />

cement, and water on jobs where select material is required for the<br />

cement treated course. Aggregate and cement shall be dry-mixed<br />

sufficiently to prevent cement balls from forming when water is added.<br />

The plant shall be capable of producing a uniform cement-treated<br />

mixture at the specified cement and moisture contents. The mixture<br />

shall be hauled to the job in trucks equipped with protective covers.<br />

The sub-base shall be thoroughly moistened and the mixture then<br />

placed on the sub-base in a uniform lay with mechanical spreaders.<br />

Not more than 60-minutes shall elapse between the start of the moist<br />

mixing and the start of compaction of the treated layer. The layer shall<br />

be uniform in thickness and surface contour and in such quantity that<br />

the completed layer, after compaction, shall conform to the required<br />

grade and cross section. Dumping the mixture in piles or windrows<br />

shall not be permitted. The mixture shall contain not less than five (5)<br />

percent cement calculated by dry weight of aggregate.<br />

1005.5.2 Traveling-Plant Method: Traveling plant, when used for mixing the<br />

materials, shall move at a uniform rate of speed and accomplish<br />

thorough mixing of the materials. Water and cement shall be delivered<br />

from supply trucks or bins at a predetermined rate. Windrows of<br />

prepared soil-cement mixture shall be of sufficient size to cover a<br />

predetermined width or roadway to the indicated compacted thickness.<br />

When this method is used, cement content shall be not less than 5-1/2<br />

percent. The mixing and placing of materials shall be as mentioned in<br />

the above Central-Plant method.<br />

1005.6 Construction Control:<br />

1005.6.1 Lay Thickness: The compacted thickness of the stabilized course<br />

shall be as called for in the drawings.<br />

1005.6.2 Compaction: Before the compaction operations begin and as a<br />

continuation of the mixing operation, the mixture shall be thoroughly<br />

loosened to the full depth. The compaction shall be started<br />

immediately after mixing is completed. The loose mixture shall be<br />

uniformly and continuously compacted until the entire depth and width<br />

of the area is compacted to at least 100 percent for maximum density.<br />

The moisture content at the surface shall be maintained near optimum<br />

at all times through the rolling but shall be less than that which shall<br />

cause the mixture to become unstable during compaction. Rolling shall<br />

begin at the outside edge of the surface and proceed to the center,<br />

overlapping on successive trips at least one-half the width of the roller.<br />

Alternate trips of the roller shall be slightly different lengths. The speed<br />

of the roller at all times shall be such that displacement of the mixture<br />

does not occur. Areas that are inaccessible to rollers shall be<br />

compacted with mechanical tampers.<br />

SERIES 1000 Page 5 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

1005.6.3 Finishing: After compaction, the surface shall be moistened, if<br />

necessary, and shaped to the required lines, grades, and cross section.<br />

If necessary, the surface shall be lightly scarified to eliminate any<br />

imprints made by the compacting or shaping equipment. The surface<br />

shall then be thoroughly compacted to specified density with rubbertired<br />

rollers and smooth wheel tandem rollers to the extent necessary to<br />

provide a smooth, dense, uniform surface that is free of surface<br />

checking, ridges or loose material, and that conforms to the crown,<br />

grade and line indicated. The surface shall then be broomed to remove<br />

any surface fines without dislodging any embedded coarser aggregates<br />

prior to application of the prime coat, which is to be applied immediately<br />

after completion of the cement treated base course. The Contractor is<br />

required to perform field trials on this operation to ascertain no<br />

dislodging of the embedded aggregates and loosening of the cement<br />

treated base course. These finishing operations shall be completed<br />

within 2-hours after completion of missing operations. In places not<br />

accessible to finishing and shaping equipment, the mixture shall be<br />

compacted with mechanical tampers to the density specified and shall<br />

be shaped and finished by hand methods. Any portion of the<br />

compacted mix that has density less than that specified shall be rerolled<br />

until the required density is obtained or shall be removed to the<br />

full depth and replaced with new base course material and again<br />

compacted. Areas removed shall have a true vertical face free of loose<br />

or shattered material.<br />

1005.6.4 Construction Joints: At the end of each day’s construction and when<br />

cement treated base operations are delayed or stopped for more than<br />

2-hours, a straight transverse construction joint shall be formed by<br />

cutting back into the completed work to form a true vertical face free of<br />

loose or shattered material. Material along construction joints not<br />

properly compacted shall be removed and replaced with soil-cement<br />

that is mixed, moistened, and compacted in accordance with this<br />

specification. Where cement treated base has been finally compacted<br />

more than one hour, longitudinal joints shall be by cutting vertically into<br />

the existing edge or approximately 3-inches and disposed properly.<br />

The face of the cut joints shall be moistened in advance of placing the<br />

adjacent base.<br />

1005.6.5 Edge of Stabilized Course: Approved material shall be placed along<br />

the edges of the stabilized course in such quantity for compaction to<br />

the thickness of the course being constructed, allowing at least a onefoot<br />

width of the shoulder to be rolled and compacted simultaneously<br />

with the rolling and compacting of the stabilized course as directed.<br />

1006.6.6 Thickness Control: The completed thickness of the stabilized course<br />

shall be within ¼ inch of the thickness indicated. The thickness of the<br />

stabilized course shall be measured at intervals in such manner that<br />

there shall be one depth measurement at least for each 500 square<br />

yards of stabilized course. The depth measurement shall be made by<br />

test holes at least stabilized course. The depth measurement shall be<br />

made by test holes at least 3-inches in diameter through the stabilized<br />

SERIES 1000 Page 6 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

course. Where the measured thickness of the stabilized course is<br />

more than ¼ inch deficient in thickness, the Contractor shall correct<br />

such areas by removal and replacement with cement-treated base<br />

course for full depth. Where the measured thickness of the stabilized<br />

course is more than ¼ inch thicker than that indicated of the stabilized<br />

course is more than ¼ inch thicker than that indicted and satisfies the<br />

required lines, grades and cross section, it shall be considered as<br />

conforming with the specified thickness requirements plus ¼ inch. The<br />

average job thickness shall be the average of the job measurements<br />

determined as specified above but shall be within ¼ inch of the<br />

thickness indicated. Material removed by making test holes will be<br />

replaced with new soil-cement mixture at no additional cost to the<br />

Owner.<br />

1005.7 Curing: Immediately after the finishing operations are completed bituminous<br />

prime coat shall be applied at a rate of 0.22 gallons per sq. yd. Or as directed<br />

by the C.O., in accordance with SERIES 1100: BITUMINOUS PRIME COAT.<br />

In the event there is a delay in applying the prime coat, the surface shall be<br />

kept wet with water. This curing membrane may serve the function of a primer<br />

if remain satisfactory prior to paving. Immediately prior to paving, if any surface<br />

appear unsatisfactory, the surface may have to be re-primed in accordance with<br />

SERIES 1100: BITUMINOUS PRIME COAT as determined by the Contracting<br />

Officer.<br />

1005.8 Traffic: Completed portions of the cement-treated soil area may be opened to<br />

light, local traffic after 4-days curing provided the curing is not impaired and to<br />

all other traffic after the curing period of 7-days, provided that the cementstabilized<br />

course has hardened sufficiently to prevent marring or distorting of<br />

the surface by equipment or traffic. If in the opinion of the C.O. a longer curing<br />

period is required for the cement treated base, he may direct the Contractor to<br />

do so at no extra cost to the Owner. Heavy equipment shall not be permitted<br />

on the area during the protection and curing period. However, the necessary<br />

cement and water may be hauled over the area with pneumatic-tired equipment<br />

with the approval of the Contracting Officer. Finished portions of cementstabilized<br />

soil that are traveled on by equipment used in constructing an<br />

adjoining section shall be protected in a manner so as to prevent equipment<br />

from marring or damaging the completed work.<br />

1005.9 Maintenance: The stabilized area shall be maintained in a satisfactory<br />

condition until the completed work is accepted. Maintenance shall include<br />

immediate repairs of any defects that may occur either before or after the<br />

cement is applied and shall be repeated as often as may as necessary to keep<br />

the area continuously intact. Defects in freshly mixed base course shall be<br />

remedied by re-rolling until required densities are obtained and imperfections<br />

corrected and leveled. Base course defects where materials have replaced<br />

with new base course material and again compacted.<br />

1006. SAMPLING, TESTING AND APPROVALS<br />

1006.1 Samples: Samples shall be of the size required for testing as specified and<br />

shall be furnished at no additional cost to the Owner. Samples of the<br />

SERIES 1000 Page 7 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No.1 (11-29-2010)<br />

material shall be submitted for approval prior to starting the work and<br />

thereafter at regular intervals during construction. Material samples shall<br />

be obtained at the source, from stockpiles, or from other locations<br />

designated by the Contracting Officer in conformance with ASTM D420.<br />

The source of the material shall be selected in advance of the time the<br />

materials shall be required in the work. Samples for gradation tests shall<br />

be taken in conformance with ASTM D75. Samples for density test shall<br />

be taken during construction. Samples for determining the optimum<br />

moisture content and the specified degree of compaction shall be<br />

representative of soil-cement mixtures obtained from the area being<br />

processed. Samples for determining the density of the compacted soilcement<br />

mixture shall be taken in conformance with ASTM D1556.<br />

Samples of bituminous material shall be taken in conformance with ASTM<br />

D140. Sampling shall be supervised by the Contracting Officer at his<br />

option.<br />

1006.2 Approval of Materials: Approval of materials shall be based on tests of<br />

samples for specific job but test certificates should accompany samples<br />

submitted by the Contractor.<br />

1006.3 Cement and bituminous materials shall be tested as prescribed in the<br />

referenced specification under which furnished. Cement may be accepted<br />

on the basis of mill tests and the manufacturer’s certification of compliance<br />

with the specification, provided the cement is the product of a mill with a<br />

record for the production of high-quality cement for the past 3-years.<br />

1006.4 CBR: Sampling and testing for CBR shall be taken for each 2,000 cubic<br />

yards of material.<br />

1006.5 Smoothness Test: The surface course shall not show any deviations in<br />

excess of 3/8 inch when tested with a 10-foot straightedge applied parallel<br />

with the centerline of the stabilized area. Any deviation in excess of this<br />

amount shall be corrected as hereinbefore specified in subparagraph<br />

1005.6.5.<br />

1006.6 Test shall be performed by the Contractor at no additional cost to the<br />

Owner. One test of each type listed below shall be conducted for each 250<br />

linear feet along the road or one day’s production whichever is less.<br />

1006.6.1 Sieve analysis shall be made in accordance with ASTM C136.<br />

1006.6.2 Density Tests: The density of the compacted soil-cement mixture<br />

shall be at least 100 percent of the maximum density determined in<br />

the laboratory. The density shall be determined in the field in<br />

accordance with ASTM D1556. The maximum density at optimum<br />

moisture content will be determined in the laboratory in accordance<br />

with ASTM D558.<br />

****** END OF SECTION ******<br />

SERIES 1000 Page 8 of 8


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

SERIES 1100<br />

BITUMINOUS PRIME COAT<br />

Additional Requirement for Bituminous Prime Coat Section 32 12 10.<br />

1101. APPLICABLE PUBLICATIONS: The following publications of the issues listed<br />

below, but referred to thereafter by basic designation only, form a part o this<br />

specification to the extent indicated by references thereto.<br />

1101.1 American Association of <strong>State</strong> Highway Transportation Officials (AASHTO)<br />

Publication:<br />

1101.2 American Society for Testing and Materials (ASTM), Publications:<br />

1102. QUALITY CONTROL: Approvals, except those required for field installations,<br />

field applications and field tests, shall be obtained before delivery of materials or<br />

equipment to the project site.<br />

1103. CERTIFIED TEST REPORTS: Before delivery of materials and equipment, four<br />

certified copies of the reports of all tests required in referenced publications or<br />

specified herein shall be submitted and approved. The testing shall have been<br />

performed by approved independent laboratory. Test reports shall be<br />

accompanied by notarized certificates from the manufacturer certifying that the<br />

tested material and equipment is of the same type, quality, manufacture, and<br />

make as that proposed to be supplied. Certified test reports are required for the<br />

following:<br />

1103.1 Spot test of Asphaltic Materials.<br />

1103.1.1 Emulsion Asphalt.<br />

1104. DELIVERY AND STORAGE: Materials delivered to the site shall be inspected<br />

for damage, unloaded, and stored with a minimum of handling.<br />

1105. GENERAL: The bituminous prime coat shall be applied on a previously<br />

prepared base course immediately after the completion of the cement treating<br />

base course. The bituminous prime coat may be applied to function as a curing<br />

membrane as well as a primer.<br />

1106. MATERIALS: Bituminous material for the prime coat shall be emulsified asphalt<br />

Type SS-1 where applied to cement treated base.<br />

1106.1 Emulsified Asphalt: Emulsified asphalt shall conform to ASTM D977 Type<br />

SS-1. The base asphalt used to manufacture the emulsion shall show a<br />

negative spot when tested in accordance with AASHTO T102 using<br />

standard naptha.<br />

SERIES 1100 Page 1 of 3


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

1107. APPLICATION: Application rate shall be 0.22 US gallons per square yard OR<br />

AS DIRECTED BY THE Contracting Officer. Apply prime coat to all prepared<br />

surfaces of base course prior to placement of pavement.<br />

1108. CONSTRUCTION EQUIPMENT: All equipment shall be dependable and<br />

adequate for the purpose intended and shall be properly maintained in<br />

satisfactory and safe operating condition at all times.<br />

1108.1 Bituminous Distributor: Bituminous Distributor shall have pneumatic tires<br />

of such width and number that the load produced on the base surface shall<br />

not exceed 650 pounds per inch of tire width. The distributor shall be<br />

designed and equipped to distribute the bituminous material uniformly at<br />

even heat on variable widths of surface at readily determined and controlled<br />

rates from 0.05 to 2.0 gallons per square yard, with a pressure range of 25<br />

to 75 pounds per square inch and with an allowable variation not to exceed<br />

5 percent from any specified rate. Distributor equipment shall include<br />

separate power unit for the bitumen pump, full-circulation spray bars,<br />

tachometer, pressure gauges, volume-measuring devices, adequate<br />

heaters for heating the materials to the proper application temperature, a<br />

thermometer to show the temperature of tank contents, and a hose<br />

attachment suitable for applying bituminous materials to spots unavoidable<br />

missed by the distributor. The distributor shall be equipped to circulate and<br />

agitate the bituminous material during the heating process.<br />

1108.2 Brooms and Blowers: Brooms and blowers shall be of the power type and<br />

shall be suitable for cleaning prepared sub-grades or bases.<br />

1109. WEATHER LIMITATIONS: Do not apply the prime coat during drain or when<br />

rain is imminent.<br />

1110. PREPARATION OF SURFACE: Immediately before applying the prime coat to<br />

the surface that is to be primed, all loose materials, dirt, clay, or other<br />

objectionable substances shall be removed from the surface by means of a<br />

power broom or blower supplemented with hand brooms. After the cleaning<br />

operation and prior to the application of the prime coat, an inspection of the area<br />

to be primed will be made by the Contracting Officer to determine the fitness of<br />

the area to receive the bituminous priming material. To assure a uniform spread<br />

of the bituminous material, the portion of the base course prepared for<br />

treatment, if excessively dry, shall be lightly sprinkled with water immediately<br />

before the application.<br />

1111. APPLICATION OF BITUMINOUS MATERIAL<br />

1111.1 Immediately following the preparation of the base course, the bituminous<br />

material shall be applied by means of a bituminous distributor. The<br />

bituminous material shall be applied at a pressure within the range of 25 to<br />

75 pounds per square inch and in the amounts directed. The priming<br />

material shall be applied with uniform distribution at all points of the surface<br />

to be treated. Unless the distributor is equipped to obtain satisfactory<br />

results at the junction of previous and subsequent applications, building<br />

paper shall be spread on the surface of the applied material for a sufficient<br />

SERIES 1100 Page 2 of 3


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

distance back from the ends of each application so that flow from the sprays<br />

may be started and stopped on the paper, and so that all sprayers will<br />

operate at full force on the surface to be treated. Immediately after the<br />

application, the building paper shall be removed and destroyed. All spots<br />

unavoidably missed by the distributor shall be properly treated with<br />

bituminous material.<br />

1111.2 Following the application of prime material, the surface shall be allowed to<br />

dry without being disturbed for as long a period as may be necessary to<br />

attain penetration into the foundation course and evaporation of the volatiles<br />

from prime material, which period shall be a minimum of four (4) days or as<br />

determined by the Contracting Officer. The Contractor shall maintain the<br />

primed surface until pavement is placed by protecting the surface against<br />

damage and by repairing and re-priming deficient areas at no additional cost<br />

to the Owner. No smoking, fires, or flames other than the heaters that are<br />

part of the equipment shall be permitted in the vicinity of heating,<br />

distribution, or transferring operations for bituminous materials. The surface<br />

may have to be re-primed prior for paving if it appears unsatisfactory to the<br />

C.O.<br />

1111.3 Application Temperature of Emulsified Asphalt: Application temperature of<br />

emulsified asphalt shall be as directed by the C.O. and shall provide an<br />

application viscosity between 20 and 100 seconds, Saybolt-Furol.<br />

Application temperature shall be within the range of 85 to 190 degree<br />

Fahrenheit.<br />

1112. FIELD SAMPLING AND TESTING<br />

1112.1 Samples of Bituminous Materials: Samples of bituminous materials shall<br />

be furnished by and at the expense of the Contractor. Sampling shall be in<br />

accordance with ASTM D140.<br />

1112.2 Tests: An independent testing laboratory at the expense of the Contractor<br />

shall conduct all tests of bituminous materials.<br />

1112.2.1 Spot test for bitumen shall be conducted in accordance with<br />

AASHO T102, and shall be performed on each shipment.<br />

1112.2.2 Calibration Tests: The Contractor shall furnish such equipment<br />

and materials and perform the work to calibrate the tank and<br />

measuring devices of the distributor. This shall be done on the site<br />

at the beginning of the work.<br />

****** END OF SECTION ******<br />

SERIES 1100 Page 3 of 3


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

SERIES 1800A<br />

BITUMINOUS TACK COAT<br />

Additional Requirements for Bituminous Tack Coat Section 32 12 11.<br />

PART 1 – GENERAL<br />

1.1 APPLICABLE PUBLICATIONS: The publications listed below form a part of<br />

this specification to the extent referenced. The publications are referred to in<br />

the text the basic designation only.<br />

1.1.1 American Association of <strong>State</strong> Highways and Transportation Officials<br />

(AASHTO) Publications:<br />

1.1.2 American Society for Testing and Materials (ASTM) Specifications:<br />

1.2 CERTIFIED TEST REPORTS: Before delivery of materials and equipment, six<br />

certified copies of the reports of all tests required in referenced publications or<br />

specified herein shall be approved by the Contracting Officer. The testing shall<br />

have been performed in an independent laboratory approved by the Contracting<br />

Officer. Test reports shall be accompanied by notarized certificates from the<br />

manufacturer certifying that the tested material and equipment is of the same<br />

type, quality, manufacture, and make as that proposed to be supplied. Certified<br />

test reports are required for the following:<br />

a. Spot Test of Asphaltic Materials<br />

b. Emulsified Asphalt<br />

1.3 DELIVERY AND STORAGE: Materials delivered to the site shall be inspected<br />

for damage, unloaded, and stored with a minimum of handling.<br />

1.4 WEATHER LIMITATIONS: Apply the tack coat only when the surface is dry or<br />

contains moisture not in excess of the amount that will permit uniform<br />

distribution and the desired adhesion. Apply the tack coat only when the<br />

ambient 50 degrees F or above and when the temperature has not been below<br />

50 degrees F for 12 hours immediately prior to applications, unless otherwise<br />

directed.<br />

1.5 TRAFFIC CONTROLS: Keep all traffic off surfaces freshly treated with<br />

bituminous materials. Provide sufficient warning signs and barricades so that<br />

traffic will not travel freshly treated surfaces.<br />

1.6 Tack Coat is to be applied on primed base course prior to laying of bituminous<br />

Hot Mix Pavement.<br />

PART 2 PRODUCTS<br />

2.1 MATERIALS: Bituminous Material for the tack coat shall be asphalt emulsion.<br />

SERIES 1800A Page 1 of 3


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

2.1.1 Emulsified Asphalt: Emulsified asphalt shall conform to ASTM D 977<br />

Type SS-1. The base asphalt used to manufacture the emulsion shall<br />

show a negative spot when tested in accordance with AASHTO T 102<br />

using standard naphtha.<br />

2.2 QUANTITIES TO BE APPLIED: The rate of application of actual bitumen shall<br />

be sufficient to adequately bond the succeeding course of pavement but in no<br />

case shall the rate be less than 0.05 gallon nor more than 0.15 gallon per<br />

square yard. The exact amount of tack coat to be applied shall be as indicated<br />

by the Contracting Officer after test application by the Contractor. The<br />

application rate used as a basic for bidding quantity shall be 0.10 gallons per<br />

square yard.<br />

2.3 CONSTRUCTION EQUIPMENT: All equipment shall be dependable and<br />

adequate for the purpose intended and shall be properly maintained in<br />

satisfactory and safe operating condition at all times. Calibrated equipment<br />

such as asphalt distributors, scales, batching equipment, spreaders and similar<br />

equipment shall have been recalibrated within 12 months of commencing work.<br />

The Contractor in the presence of the Contracting Officer when required by the<br />

Contracting Officer shall do additional recalibration.<br />

2.3.1 BITUMINOUS DISTRIBUTOR: The equipment used by the Contractor<br />

shall include a self-powered pressure bituminous material distributor<br />

and equipment for heating bituminous material. Bituminous distributor<br />

shall have pneumatic tires of such width and number that the load<br />

produced on the base surface shall not exceed 650 psi of tire width.<br />

The distributor shall be designed and equipped to distribute the<br />

bituminous materials uniroformly at even heat on variable widths of<br />

surface at readily determined and controlled rates from 0.05 to 2.0<br />

gallons per square yard, with a pressure range of 25 to 75 psi and an<br />

allowable variation not to exceed 5 percent from any specified rate.<br />

Distributor equipment shall include a separate power unit for the<br />

bitumen pump, full-circulation spray bars, tachometer, pressure gages,<br />

volume-measuring devices, adequate heaters for heating the materials<br />

to the proper application temperature, a thermometer to show the<br />

temperature of tank contents, and a hose attachment suitable for<br />

applying bituminous material to spots unavoidably missed by the<br />

distributor. The distributor shall be equipped to circulate and agitate<br />

the bituminous material during the heating process.<br />

2.3.2 Brooms and Blowers: Brooms and blowers shall be of the power<br />

type and shall be suitable for cleaning the prepared surfaces for<br />

application of the tack coat. They shall not create environmental<br />

pollution and shall meet the requirements of SERIES 200:<br />

ENVIRONMENTAL PROTECTION.<br />

PART 3 – EXECUTION<br />

3.1 GENERAL: The bituminous tack coat shall be applied on a previously<br />

prepared primed Portland cement stabilized base course (CTB) and concrete<br />

structures where asphaltic paving abuts new or existing items.<br />

SERIES 1800A Page 2 of 3


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

3.2 PREPARATION OF SURFACE: Immediately before applying the tack coat to<br />

the surface that is to be paved, all loose material, dirt, clay, or other objectional<br />

substance shall be removed from the surface by means of a power broom or<br />

blower supplemented with hand brooms. After the cleaning operation and prior<br />

to the application of the tack coat, an inspection of the area to be paved will be<br />

made by the Contracting Officer to determine the fitness of the area to receive<br />

the bituminous material. To assure a uniform spread of the bituminous material,<br />

the portion of the surface prepared for treatment, if excessively dry, shall be<br />

lightly sprinkled with water immediately before the application.<br />

3.3 APPLICATION OF BITUMINOUS MATERIAL: Emulsified asphalt shall be<br />

diluted with one part water to one part asphalt after the asphalt is placed in the<br />

distributor tank. The tack coat shall be applied when the surface to be treated<br />

is dry or contains moisture not in excess of that which will permit uniform<br />

distribution and the desired adhesion. Immediately following the preparation of<br />

the surface for treatment, the bituminous material shall be applied by means of<br />

the distributor, within the limits of temperature and at the rate not less 0.05<br />

gallons nor more than 0.15 gallons of bituminous material per square yard as<br />

directed by the Contracting Officer. Bituminous material shall be applied so that<br />

uniform distribution is obtained over the entire surface to be treated. All areas<br />

missed by the distributor shall be treated properly with the bituminous material.<br />

Following the application of bituminous material, the surface shall be allowed to<br />

cure without being disturbed for such period of time as may be necessary to<br />

permit setting of the tack coat. The bituminous tack coat shall be applied only<br />

as far in advance of the placing of overlaying layer as required for that day’s<br />

operation. The treated surface shall be maintained and protected from damage<br />

until the succeeding course of pavement is placed.<br />

3.3.1 Application Temperature of Emulsified Asphalt: Application<br />

temperature of emulsified asphalt shall be within the range of 85 to 190<br />

degrees F.<br />

3.4 FIELD SAMPLING AND TESTING:<br />

3.4.1 Calibration Tests: The Contractor shall furnish such equipment and<br />

materials and perform the work to calibrate the tank and measuring<br />

devices of the distributor. This shall be done on the job at the<br />

beginning of the work.<br />

3.4.2 Samples of Bituminous materials: Samples of bituminous materials<br />

shall be furnished by and at the expense of the Contractor. Sampling<br />

shall be in accordance with ASTM D140.<br />

3.4.3 Tests: An independent testing laboratory at the expense of the<br />

Contractor shall conduct all tests on bituminous materials.<br />

3.4.4 Spot Test: Spot test for bitumen shall be conducted in accordance<br />

with AASHTO T102, and shall be performed on each shipment.<br />

****** END OF SECTION ******<br />

SERIES 1800A Page 3 of 3


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

SERIES 1800B<br />

HOT MIX BITUMINOUS PAVEMENT<br />

Additional Requirements for Hot Mix Bituminous Pavement Section 32 12 17.<br />

PART 1 – GENERAL<br />

1.1 APPLICABLE PUBLICATIONS: The publications listed below form a part of<br />

this specification to the extent referenced. The publications are referred to in<br />

the text by the basic designation only.<br />

1.1.1 Military Standard:<br />

MIL-STD-620A Test Methods for Bituminous Paving Materials.<br />

1.1.2 American Association of <strong>State</strong> Highway and Transportation Officials<br />

(AASHTO) Publications:<br />

1.1.3 American Society of Testing and Materials (ASTM) Publications:<br />

1.1.4 Asphalt Institute Publications:<br />

1.2 SUBMITTALS:<br />

1.2.1 Samples: Samples of the following materials shall be submitted and<br />

approved in accordance with the specifications:<br />

a. Coarse Aggregate<br />

b. Fine Aggregate<br />

c. Mineral Filler<br />

d. Asphalt Cement<br />

1.2.2 Test Reports: Seven copies of the certified test reports required in<br />

referenced publications or specified herein for each lot of bitumen used<br />

for the project shall be approved by the Contracting Officer. The<br />

furnishing of the certified test reports for the bituminous materials shall<br />

not be interpreted as a basis for final acceptance. All such test reports<br />

shall be subject to verification by testing samples of materials received<br />

for use on the project.<br />

1.2.3 Job Mix Formula: A job mix formula shall be furnished by the<br />

Contractor, approved by the Contracting Officer prior to preparing and<br />

placing the bituminous mixture. The formula shall indicate the definite<br />

percentage of each sieve fraction, percentage of bitumen, the<br />

temperature of the mixture leaving the mixer, number of blows of<br />

compaction hammer per side of molded specimen, stability, flow,<br />

percent of voids total mix, percent of voids filled bitumen, the<br />

temperature viscosity relationship of the asphalt cement, and percent<br />

of aggregate by size from each source.<br />

SERIES 1800B Page 1 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

1.3 DELIVERY AND STORAGE: Materials delivered to the site shall be inspected<br />

for damage and stored with a minimum of handling. Aggregates shall be stored<br />

in such a manner as to prevent segregation.<br />

1.4 GENERAL REQUIREMENTS: The hot-mix pavement shall be constructed on<br />

a prepared base course. The new pavement shall consist of mineral aggregate<br />

uniformly mixed with hot bituminous material. The wearing course shall be<br />

constructed only during dry weather and on dry surfaces. Lines and grade<br />

stakes shall be provided as necessary for control. Grade stakes shall be<br />

placed in lanes parallel to the center of the areas to be paved and suitably<br />

spaced for string lining.<br />

PART 2 – PRODUCTS<br />

2.1 Aggregates: The grading and proportioning of aggregate and filler shall be<br />

such that the combined mineral aggregate conforms to the grading specified<br />

hereinafter.<br />

2.1.1 Coarse aggregates shall conform to ASTM D692/D692M, except for<br />

the soundness test requirements, as modified herein. Crushed gravel<br />

shall have at least 75 percent by weight of pieces having two or more<br />

fractured faces. Aggregates, which show stripping when tested in<br />

accordance with ASTM D1664, shall be rejected. Percentage wear<br />

shall be a maximum of 40 after 500 revolutions by ASTM C131.<br />

2.1.2 Fine aggregate shall conform to ASTM D1073, except for the<br />

soundness test requirements.<br />

2.1.3 Mineral Filler: Not less than two-thirds of material passing 200 mesh<br />

sieve shall be non-plastic material meeting the requirements of ASTM<br />

D242/D242M. The material passing a 200 mesh sieve may be<br />

limestone or other suitable non-plastic material and shall be<br />

supplemented as required by the addition of limestone, Portland<br />

cement, or non-plastic materials as required to obtain the composition<br />

specified.<br />

2.2 ASPHALT CEMENT: Asphalt cement shall conform to ASTM D946,<br />

penetration grade 60-70. The asphalt shall show a negative spot when tested<br />

in accordance with AASHTO method T102. The temperature-viscosity<br />

relationship of the asphalt cement shall be given to the Contracting Officer. The<br />

asphalt cement shall be heated and delivered to the mixer at the temperature<br />

required and shall provide a mixing viscosity of 20 & 120 centistokes, kinematic<br />

or 10 & 60 seconds, Saybolt-Furol.<br />

2.3 Composition of Mixtures: The gradation shall be in accordance with the<br />

typical gradations listed herein for the selected maximum aggregate size when<br />

tested in accordance with ASTM C 136 and ASTM C 117. The gradation shall<br />

be within the job mix formula tolerance limitations specified hereinafter. The<br />

combined aggregate and filler shall be graded smoothly from coarse to fine and<br />

shall not vary the low limit on one sieve to the high limit on the adjacent sieve.<br />

The grading is based on aggregates of uniform specific gravity, and the<br />

SERIES 1800B Page 2 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

percentages passing the various sieves are subject to appropriate correction<br />

when aggregates of varying specific gravities are used. For material passing<br />

the one-inch sieve, the stability and flow will be determined by ASTM D 1559<br />

and shall meet the following requirements.<br />

Tests/Criteria<br />

75 Blow Mix 50 Blow Mix<br />

Stability (Minimum), pounds 2150 1350<br />

Flow, 0.01 inch 8-16 8-18<br />

TSR, minimum percent 75 75<br />

The voids requirements shown herein shall be determined in accordance with<br />

the procedures described in MIL-STD-620, Test Methods 101, based on<br />

maximum specific gravity determined in accordance with ASTM D 2041.<br />

Test/Criteria<br />

Percent voids total mix 3 to 5<br />

Percent voids filled with bitumen 75 to 85<br />

2.4 JOB MIX:<br />

2.4.1 Composition of Mixture: The bituminous plant mix shall be<br />

composed of a mixture of aggregate filler and bituminous material<br />

within the ranges indicated in the following mix composition table,<br />

except that the percentages of asphalt shall be increased as<br />

necessary if the mineral aggregate is porous. The maximum size of<br />

the aggregates shall be 1/2-inch. The aggregate fractions shall be<br />

seized, uniformly graded, and combined in such proportions that the<br />

resulting mixture meets the grading requirements of the job mix<br />

formula.<br />

MIX COMPOSITIONS<br />

Sieve 1-Inch Max ¾-Inch Max ½ Inch Max<br />

3A 4A 5A<br />

1-inch 900 – 100 100 - -<br />

¾-inch - - 90-100 100<br />

½-inch 60 – 80 - - 90 – 100<br />

3/8-inch - - 60 – 80 - -<br />

No. 4 25 – 60 35 – 65 45 – 70<br />

No. 8 15 – 45 20 – 50 25 – 55<br />

No. 50 3 – 18 3 – 20 5 – 20<br />

No. 200 1 – 7 2 – 8 2 – 9<br />

Asphalt Cement 5 – 7 5 – 7 6 – 8<br />

Weight (Percent of total mixture)<br />

SERIES 1800B Page 3 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

2.4.2 Variations: Variations from the approved job mix formula shall not<br />

exceed the following:<br />

Aggregates<br />

½ inch<br />

3/8-inch to No. 4<br />

No. 8 to No. 16<br />

No. 30 and 50<br />

No. 100<br />

No. 200<br />

Asphalt<br />

Temperature of mixture as<br />

discharged<br />

Tolerance (Plus or Minus)<br />

3 percent<br />

3 percent<br />

3 percent<br />

2 percent<br />

1 percent<br />

1 percent<br />

0.4 percent<br />

25 degrees<br />

Adjustments of the bitumen content and aggregate gradation, within the limits<br />

specified herein, to improve the paving mixture shall be made as necessary by<br />

the Contractor and approved by the Contracting Officer without change in the<br />

contract price.<br />

2.5 CONSTRUCTION EQUIPMENT: All equipment shall be dependable and<br />

adequate for the purpose intended and shall be properly maintained in<br />

satisfactory and safe operating condition at all times. Calibrated equipment<br />

such as asphalt distributors, scales, batching equipment, spreaders, and similar<br />

equipment, shall have been recalibrated by a calibration laboratory<br />

recommended by the Contractor and approved by the Contracting Officer within<br />

12 months of commencing work. The Contractor in the presence of the<br />

Contracting Officer when required by the Contracting Officer shall do additional<br />

recalibration.<br />

2.5.1 Mixing Plant: The mixing plant shall be designed, coordinated, and<br />

operated to produce a mixture within the job mix formula tolerance and<br />

shall meet the requirements of ASTM D995 except as specified herein.<br />

The mixing plant shall be either weight-batch type or continuous mixing<br />

type. The mixing plant shall have a capacity capable of producing AC<br />

mixtures at rates meeting job specification requirements. Rotary-drum<br />

type may be substituted for the above types, provided the equipment is<br />

suitable for producing finished mixtures complying with the job mix<br />

formula specified herein. The paving plant and equipment shall remain<br />

accessible at all times for checking its adequacy, inspecting its<br />

operation, verifying weights, proportions, and character of materials,<br />

and checking mixture temperatures.<br />

2.5.1.1 Equipment for Preparation of Bituminous Material: Tank for<br />

storage of bituminous material shall be equipped with a heating<br />

system capable of heating the material under the effective and<br />

positive control, at all times, to the temperature requirements<br />

specified. Heating shall be accomplished by steam coils,<br />

electricity, or other means shall accomplish heating so that no<br />

flame will come in contact with the heating tanks. The circulating<br />

SERIES 1800B Page 4 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

system for the bituminous material shall be adequate size to<br />

insure proper and continuous circulation between storage tank<br />

and mixer during the entire operating period. All pipe lines and<br />

fittings shall be steam-jacketed or otherwise properly insulated to<br />

prevent heat loss. The storage tank capacity shall be sufficient for<br />

at least a one-day run. The storage tank capacity shall be free<br />

from accretions of foreign or caked bituminous materials or other<br />

substances, which could contaminate the bituminous mix<br />

materials or preclude an accurate inventory of quantities. Tanks<br />

shall be calibrated and charts indicating the depth to liquid-volume<br />

relationship shall be proved. The temperature of the asphaltic<br />

cement shall not exceed 325 degrees F at any time.<br />

2.5.1.2 Feeder for Dryer: The plant shall be provided with a accurate<br />

mechanical means for uniformly feeding the mineral aggregate<br />

into the dryer so that uniform production and uniform temperature<br />

will be secured. The feeder or feeders shall be capable for<br />

delivering the maximum number of aggregate sized required in<br />

their proper proportion. The feeder shall provide for adjustment of<br />

total and proportional feed and shall be capable of being locked in<br />

any position. When more than one cold elevator is used, each<br />

shall be fed as separated unit and individual controls shall be<br />

integrated with a master control.<br />

2.5.1.3 Dryer: A rotary dryer of satisfactory design for drying and heating<br />

the aggregates shall be provided. Dryer shall be capable of<br />

continuously supplying the mixing unit at its operating capacity<br />

with dried aggregates of the specified temperature. The<br />

aggregates delivered to the hot bins shall contain moisture to an<br />

extent that will cause foaming, segregation, or stripping during<br />

hauling and placing operations. The dyer shall be equipped with a<br />

heat-indicating device to measure the temperature of the<br />

aggregate as it leaves the dryer. The device shall be accurate<br />

within 10 degrees F and shall be installed in such manner that a<br />

10 degrees F change in aggregate temperature will be indicated<br />

within one minute.<br />

2.5.1.4 Plants screens capable of screening all dried aggregates to the<br />

specified sizes and proportions and having normal capacities<br />

slightly in the excess of the full capacity of the mixer or the dryer<br />

shall be provided. The screens shall be accurate and efficient and<br />

no bin shall be allowed to contain more than 10 percent oversize<br />

or undersize.<br />

2.5.1.5 Bins: The plant shall include storage bins of sufficient capacity to<br />

supply a mixer operating at full capacity. Bins shall be arranged to<br />

assure separate and adequate storage of appropriate fractions of<br />

the mineral aggregates. When used, separate dry storage shall<br />

be provided for filler or hydrated lime, and plant shall be equipped<br />

to feed such material into the mixer. Each pin shall be provided<br />

with overflow pipes of such size and at such location to prevent<br />

SERIES 1800B Page 5 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

back of material into the adjacent compartments or bins. Each<br />

compartment shall be provided with its individual outlet gate to<br />

prevent leakage. The gate shall cut off quickly and completely.<br />

Bins shall be equipped with adequate tell-tale devices, which<br />

indicate the position of the aggregates in the bins at the lower<br />

quarter points.<br />

2.5.1.6 Bituminous Control Units: Satisfactory means shall be provided<br />

to obtain the proper of bituminous material in the mix within the<br />

tolerances specified by the job mix formula, either by weighing,<br />

metering, or volumetric measurements. Suitable means shall be<br />

provided, either by steam-jacketing or other methods of insulation,<br />

for maintaining the specified temperature of the bituminous<br />

material in the pipelines, meters, weight buckets, spray bars, and<br />

other containers or flow lines.<br />

2.5.1.7 Thermometric Equipment: An armored thermometer with a<br />

range from 200 degrees to 400 degrees F shall be fixed in the<br />

bituminous feed line at a suitable location near the discharge<br />

valve at the mixer unit. The plant shall be further equipped with<br />

an approved dial-scale, mercury-actuated thermometer, an<br />

electric pyrometer, or other approved thermometric instrument so<br />

placed at the discharge chute of the dryer as to register<br />

automatically or indicate the temperature of the heated aggregate.<br />

The dial shall be in full view of the dryer fireman of feeder.<br />

2.5.2 Safety Requirements: Adequate and safety stairways to the mixer<br />

platform and sampling points shall be provided, and guarded ladders to<br />

other plant units shall be placed at all points where accessibility to plant<br />

operations is required. Accessibility to the top of the truck bodies shall be<br />

provided by a suitable device to enable the Contractor to obtain sampling<br />

and mixture temperature data. Means shall be provided to raise and lower<br />

scale calibration equipment, and other similar equipment between the<br />

ground and the mixer platform. All gears, pulleys, chains, sprockets, and<br />

other dangerous moving parts shall be thoroughly guarded. Ample and<br />

unobstructed passage shall be maintained at all times in and around the<br />

truck loading area. These areas shall be kept free of drippings from the<br />

mixing platform.<br />

2.5.3 Dust Control: The plant shall be equipped with a dust collector designed to<br />

waste or return in a constant flow to the hot elevator, by mechanical means,<br />

all or part of the material collected. The quantity recovered shall be as<br />

necessary to provide and maintain composition specified. The plant shall<br />

have a mixer cover such additional housing to insure the proper control of<br />

dust.<br />

2.5.4 Truck Scales: Unless an automatic batching plant with automatic printers<br />

is used, the bituminous mixture shall be weighted on approved scales<br />

furnished by the Contractor or on public scales at the Contractor’s expense.<br />

Scales shall be inspected for accuracy and sealed as often as the<br />

Contracting Officer deems necessary.<br />

SERIES 1800B Page 6 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

2.5.5 Testing Laboratory: The Contractor shall provide a testing laboratory for<br />

control and acceptance testing functions during periods of mix production,<br />

sampling, and testing and whenever materials subject to the provisions of<br />

these specifications are being supplied or tested. The laboratory shall<br />

provide adequate equipment, space, and utilities as required for the<br />

performance of the specified tests.<br />

2.5.6 Special Requirements for Batch Mixing Plants:<br />

2.5.6.1 Weigh Box or Hopper: The equipment shall include means for<br />

accurately weighing each bin size of aggregate in a weigh box or<br />

hopper suspended on scales, ample in size to hold a full batch without<br />

hand-raking or running over. The weigh box or hopper shall be<br />

supported on knife-edge fulcrums so constructed that they will not be<br />

thrown out of alignment easily. The gates on the bins and hopper shall<br />

prevent leakage of aggregate when closed.<br />

2.5.6.2 Scales for weigh box or hopper shall be of standard make and<br />

design and shall be of the beam or springless dial type sensitive to ½ of<br />

one percent of the maximum load that may be required. Beam type<br />

scales shall have a separate beam for each size aggregate, with a<br />

single tell tale actuated for each separate and a tare beam for<br />

balancing the hopper. Dial scales shall be designed, constructed and<br />

installed so that they will be free from vibration. All dials shall be<br />

located so as to be plainly visible to the operator at all times and of<br />

such size that the numerals can be read at a distance of 25 feet.<br />

At least ten standard 50-pound test weights shall be provided for<br />

checking the accuracy of the scales. Test weights will be kept clean<br />

and shall be stored near the scales.<br />

2.5.6.3 Asphalt bucket for weighing the bituminous material shall have<br />

sufficient capacity to hold not less than 15 percent of the rated capacity<br />

of the mixer. It shall be steam-jacketed or equipped with properly<br />

insulated electric heating units and shall be suspended on dial or beam<br />

scales which shall show the weight of the bucket, for each weighing,<br />

and the net weight of bituminous material to an accuracy within one<br />

percent of the weight of material required. The discharge system shall<br />

deliver the heated bituminous material in a thin, uniform sheet or in<br />

multiple streams the full width of the mixer, except that in the case of a<br />

rotary mixer, the bituminous material shall be sprayed into the mixer.<br />

2.5.6.4 Volumetric meter for automatically metering the bituminous<br />

material into each batch shall be provided with a dial to indicate the<br />

amount of asphalt and shall have a capacity of at least 10 percent in<br />

excess of the number of gallons of asphalt required in each batch.<br />

The meter shall be constructed so that it may be locked at any dial<br />

setting and will automatically reset to this reading after the addition of<br />

asphalt to each batch. The dial shall be in full view of the mixer<br />

operator. The flow of asphalt shall be automatically controlled, shall<br />

SERIES 1800B Page 7 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

begin when the dry mixing period ends, and all of the asphalt shall be<br />

discharged in not more than 15 seconds after the flow has started.<br />

Spray bar openings of sufficient size and spacing shall provide for the<br />

uniform application of asphalt for the full length of the mixer. A valve<br />

and outlet shall be provided between the charging valve and spray bar<br />

as a means for checking and testing the accuracy of the meter.<br />

2.5.6.5 Mixer: The batch mixer shall be an approved type capable of<br />

producing a uniform mixture within the job mix tolerances. If not<br />

enclosed, the mixer box shall be equipped with a dust hood to prevent<br />

loss of dust. The clearance of blades from all fixed and moving parts<br />

shall not exceed ¾ inch.<br />

2.5.6.6 Control of Mixing Time: The mixer shall be equipped with an<br />

accurate time lock to control the operations of complete mixing cycle.<br />

It shall lock the weigh-box gate after the charging of the mixer and<br />

keep cycle. It shall lock the bituminous material bucket throughout the<br />

dry mixing periods. The dry mixing period is defined as the interval of<br />

time between the opening of the weigh-box gate and the introduction<br />

of bituminous material. The wet mixing period is the interval of time<br />

between the introduction of bituminous material and the opening of the<br />

mixer gate. The timing control shall be flexible and shall be capable of<br />

settings of 5-seconds intervals or less throughout a 3-minute cycle. A<br />

mechanical batch counter shall be installed as part of the timing device<br />

and shall be designed to register only completely mixed batches. The<br />

setting of time intervals shall be at the direction of the Contracting<br />

Officer, who shall then lock the case covering the timing device until a<br />

change is made in the timing periods.<br />

2.5.7 Special Requirements for Continuous Mixing Plants:<br />

2.5.7.1 Aggregate Proportioning: The plant shall include means for<br />

accurately proportioning each size of aggregate. The plant shall have<br />

a feeder mounted under each compartment bin. Each compartment<br />

bin shall haven an accurately controlled individual gate to form an<br />

orifice for volumetrically measuring the material drawn form each<br />

compartment. The feeding orifice shall be rectangular with one<br />

dimension adjusted by positive mechanical means provided with a<br />

lock. Indicators shall be provided for each gate to show the respective<br />

gate opening in inches. The fine bin shall be equipped with a vibrating<br />

unit or other equipment, which shall effectively prevent any “hang-up”<br />

of material while the plant is operating. A positive system shall be<br />

provided to indicate the level of material in each bin, and as the level of<br />

material in one bin approaches the strike-off capacity of the feed gate,<br />

the device shall automatically close down the plant instantly. The plant<br />

will not be permitted to operate unless this automatic system is in good<br />

working condition.<br />

2.5.7.2 Weight Calibration of Aggregate Feed: The plant shall include a<br />

means for calibration of gate openings by weighing test samples.<br />

Provisions shall be made so that materials fed out of individual orifices<br />

SERIES 1800B Page 8 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

may be passed to individual test boxes. The plant shall be equipped to<br />

conveniently handle individual test samples weighing not less than 200<br />

pounds. Accurate scale of adequate capacities shall be provided by<br />

the Contractor to weigh such test samples.<br />

2.5.7.3 Synchronization of aggregate and Bituminous Feed: Satisfactory<br />

means shall be provided to afford positive interlocking control between<br />

the flow of aggregate from the bins and the flow of bituminous material<br />

form the meter or other proportioning device. This control shall be<br />

accomplished by interlocking mechanical means or any positive<br />

satisfactory to the Contracting Officer. Aggregate feeders that are<br />

mechanically driven shall be directly connected with the drive on the<br />

asphalt binder pump. The drive shaft on the feed shall be equipped<br />

with a revolution and with counter reading to 1/100 of a revolution and<br />

with sufficient capacity to register the total number of revolutions in a<br />

day’s run.<br />

2.5.7.4 Mixer: The plant shall include a continuous mixer of an approved<br />

type, adequately heated and capable of producing a uniform mixture<br />

within the job-mix tolerances. It will be equipped with a discharge<br />

hoper with dump gates, which will permit rapid and complete discharge<br />

of the mixture. The paddles shall be adjustable for angular position on<br />

the shafts and reversible to retard the flow of the mix. The mixer shall<br />

have a manufacturers plate giving the net volumetric contents of the<br />

mixer at the several heights inscribed on a permanent gage. Charts<br />

shall be provided showing the rate of feed of aggregate per minute for<br />

the aggregate being used.<br />

2.5.8 Paving Equipment:<br />

2.5.8.1 Spreading equipment: Spreading equipment shall be the selfpropelled<br />

type, equipped with hoppers, distributing screws, adjustable<br />

screeds, and equalizing devices capable of spreading hot bituminous<br />

mixtures without treating, shoving, or gouging, and of producing a<br />

finished surface of specified evenness. Spreaders shall operate, when<br />

laying mixtures, at a speed between 5 and 45 feet per minute, as<br />

directed by the Contracting Officer. They shall be equipped with a<br />

quick and efficient steering device and shall have a forward and<br />

reverse traveling speed of not less than 100 feet per minute.<br />

Spreaders shall be equipped with mechanical devices to adjust to<br />

grade and confine the edges of the pavement curbs, manholes, and<br />

similar structures shall be given a bituminous tack coat.<br />

2.5.8.2 Rolling equipment shall consist of self-propelled roller of the<br />

pneumatic-tired and/or the three-wheel tandem type and vibratory<br />

type. Three wheel and tandem rollers shall weigh not less than 9<br />

tons. Three wheel rollers shall have a minimum weight of 300 pounds<br />

per inch of rear wheel width. Pneumatic-tired rollers shall be of the<br />

double axle type equipped with pneumatic tires of equal size and<br />

diameter. Tires shall be uniformly inflated so that the air pressure in<br />

the several tires will not vary more than 5-pounds per square inch and<br />

SERIES 1800B Page 9 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

be so arranged that the tires on the axle will cover the gap between the<br />

tires on the other axle. Pneumatic-tired rollers shall be so constructed<br />

that the total weight of the rollers can be varied to produce an<br />

operating weight per tire from 1,000 pounds minimum to a maximum of<br />

4,500 pounds or as required to obtain the specified density. All rollers<br />

shall be suitable for rolling hot-mix bituminous pavements and shall be<br />

capable of reversing without backlash. Pneumatic-tired rollers shall be<br />

capable of being operated both forward and backward without turning<br />

on the mat, and without loosening the surface being rolled. Rollers<br />

shall be equipped with suitable devices and apparatus to keep the<br />

rolling surfaces wet and prevent adherence of bituminous mixtures.<br />

2.5.8.3 Hand Tampers: Hand tampers shall weigh not less than 25 pounds<br />

and shall have a tamping face of not more than 50-square inches.<br />

2.5.8.4 Mechanical Hand Tampers: Mechanical hand tampers shall be<br />

commercial type operated by pneumatic pressure or by internal<br />

combustion.<br />

2.5.8.5 Power Blowers and Power Brooms: Blowers and brooms shall be of<br />

the power type and shall be suitable for cleaning the surface to be<br />

paved.<br />

2.5.8.6 Scales: Scales shall be standard truck scales of the beam type. The<br />

scales shall be of sufficient size and capacity to accommodate all<br />

trucks to be used for handling bituminous mixtures with all wheels on<br />

the scale at the time. All scales shall be tested, as directed by the<br />

Contracting Officer, and the necessary number of standard weights for<br />

testing the scales shall be on hand at all times.<br />

2.5.8.7 Miscellaneous Equipment: Shall tools, including rakes, lutes,<br />

shovels, smoothing irons, pavement cutters, wheel-mounted wagons<br />

for heating small tools, wood sandals and stilts sandals type, and other<br />

small tools, shall be provided as necessary.<br />

PART 3 – EXECUTION<br />

3.1 Mixing: The bituminous mixture shall be produced in a suitable plant as<br />

specified hereinbefore. The fine and coarse aggregate shall be piled separately<br />

and fed to the dryer by separate mechanical feeders in a manner to produce a<br />

bituminous mixture within the tolerances specified for the job mix formula. The<br />

aggregates shall be heated and dried thoroughly before being placed in the<br />

plant hot bins. The temperature of the aggregate, mineral filler, and asphalt in<br />

the mixer shall be such that the viscosity of the asphalt in the mixture will be in<br />

the range of 20 & 120 centistokes kinematic or 10 & 60 seconds, Saybolt Furol<br />

The heated and dried aggregates shall be screened, separated into specified<br />

size conveyed to separate bins, and held ready for mixing with the bituminous<br />

material. Adequate dry storage shall be provided for mineral filler at the mixing<br />

plant. After the aggregates have been prepared properly, they shall be<br />

accurately weighted or measured and conveyed into the mixer in the<br />

proportionate amounts of each aggregate size required. Mineral filler shall be<br />

SERIES 1800B Page 10 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

weighted or fed by some accurate and uniform measurement, and added<br />

separately, and in a dry condition, as near as possible to the center of the<br />

mixer. The required amount of asphalt for each batch, or calibrated amount for<br />

continuous mixing, shall be introduced into batch, or calibrated amount for<br />

continuous mixing, shall be introduced into the mixer. In batch mixing, the<br />

aggregates shall be charged into the mixer, the asphalt added, and mixing<br />

continued for at least 25 seconds or longer as necessary to obtain<br />

homogeneous mixture. When a continuous mixer is used, the mixing time shall<br />

be not less than 30 seconds, as may be necessary to obtain homogeneous<br />

mixture. The additional mixing time, when required, shall be as directed by the<br />

Contracting Officer. The temperature of the asphalt at the time of mixing shall<br />

not exceed 325 degreed F. When prepared in a twin pugmill mixer, the depth<br />

of the mixture shall be not greater than the tips of the mixer blades when the<br />

blades are in a vertical position. All overheated and carbonized mixtures, and<br />

mixtures that foam, segregate, or strip shall be rejected. When excessive<br />

moisture causes foaming, segregation, or stripping, all aggregates in bins shall<br />

be removed and placed in their respective stockpiles.<br />

3.2 Transportation of Bituminous Mixtures: The bituminous mixture shall be<br />

transported from the paving plant to the site in trucks having tight, clean,<br />

smooth beds which have been painted or sprayed with a limewater, soap, or<br />

detergent solution at least once a day to prevent adhesion of the mixture to the<br />

truck bodies. Each load shall be covered with canvas or other suitable material<br />

of ample size to protect it from the weather and to control the loss of heat.<br />

Deliveries shall be made so that spreading and rolling of all the mixture<br />

prepared for a day’s run can be completed during daylight, unless satisfactory<br />

artificial light is provided. The mixture shall be delivered to the area to be<br />

paved in such a manner that the temperature at the time of the dumping the<br />

spreader will be not less than 250 degrees F. Any load that has been<br />

uncovered and contaminated by rainwater prior to placing shall be rejected.<br />

Hauling over freshly laid material will not be permitted.<br />

3.3 Placing: Prior to laying the wearing course, the underlying course shall be<br />

cleaned of all foreign or objectionable matter by power blowers, power brooms,<br />

or hand brooms in places inaccessible to power equipment, and will be<br />

inspected by the Contracting Officer for compaction and smoothness<br />

requirements. Asphalt mixture having a temperature less than 250 degrees F,<br />

when dumped into the hopper of the spreader, will be rejected. The mechanical<br />

spreader shall be adjusted and the speed regulated so that the surface of<br />

wearing course shall be smooth and when compacted shall conform to depth,<br />

cross section, grades, and contours indicated. The finished surface shall vary<br />

not more than 1/8-inch for wearing course when the test for smoothness is<br />

performed with a 10-foot straightedge. The thickness shall vary from the<br />

specified thickness by not more than ¼-inch for wearing course. When the<br />

irregularities of the surface or the deficiency in depth is more than the specified<br />

tolerances, the defective work shall be removed and replace with new material<br />

without additional cost to the Owner. Whenever possible, the mixture for the<br />

wearing course shall be placed in strips not less than 10 feet wide. After the<br />

first strip has been placed and rolled the second strip and succeeding strips<br />

shall be placed and rolled. Rolling shall overlap to the previously placed strip<br />

and shall be extended to overlap the first strip. The length of any strip laid<br />

SERIES 1800B Page 11 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

before placing the succeeding strip shall be as directed by the Contracting<br />

Officer. Placing of the mixture shall be as continuous as possible. A sufficient<br />

number of experienced shovelers and rakers shall follow the spreading<br />

equipment, adding hot mixture and raking as required to produce a course that,<br />

when completed, shall conform to all requirements specified. In areas wherein<br />

the use of machine spreading is impractical, the mixture may be spread by<br />

hand. The mixture shall be distributed into place from dump boards by means<br />

of hot shovels and spread with hot rakes in a uniformly loose layer of such<br />

thickness that, when compacted, it shall conform to the required grade and<br />

thickness. The loads shall not be dumped any faster than they can be handled<br />

properly by the shovelers and rakers. Contact surfaces of previously<br />

constructed curbs, manholes, and similar structures shall be painted with a thin<br />

coat of bituminous material prior to placing the bituminous mixture.<br />

3.4 Joints: All joints shall present the same textures, density, and smoothness as<br />

other sections of the course. The joints between old and new pavements or<br />

between successive day’s work shall be made carefully in a manner to ensure a<br />

thorough and continuous bond between old and new sections of the course. All<br />

contact surfaces of previously constructed pavements shall be coated with a<br />

uniform coat of hot bituminous material immediately before the fresh mixture is<br />

placed. Where required, fresh mixtures shall be raked against joints, thoroughly<br />

tamped, smoothed with hot smoothers, and rolled.<br />

3.4.1 Transverse: The roller shall pass over the unprotected end of the<br />

freshly laid mixture only when the laying of the course is to be<br />

discontinued. Except when a canvas-rope cloth is used, the edge of<br />

the previously, laid course shall be cut back to expose an even,<br />

vertical surface for the full thickness of the course. The fresh mixtures<br />

shall be raked against the joints, thoroughly tamped with hot tampers,<br />

and smooth with hot smoothers, followed by rolling.<br />

3.4.2 Longitudinal: When the edges of the longitudinal joints are irregular,<br />

honeycombed, or poorly compacted, all unsatisfactory section of the<br />

joint shall be cut back to expose an even, vertical surface for the full<br />

thickness of the course, and joint shall be repaired with new material.<br />

When required, fresh mixture shall be raked against the joints,<br />

thoroughly, tamped with hot tampers, and smoothed with hot<br />

smoothers, followed by rolling.<br />

3.5 Compaction of Mixture: Compaction shall be effected by rolling. Rolling shall<br />

begin as soon as after placing as the mixture will bear the roller without undue<br />

displacement. Delays in rolling freshly spread mixture will not be tolerated.<br />

Rolling shall start longitudinally at the extreme sides of the lanes and shall<br />

proceed toward the center of the pavement, overlapping on successive strips<br />

by at least one-half the width of the rear wheel of the roller. Alternate trips of<br />

the roller shall be slightly different lengths. The initial longitudinal rolling shall be<br />

effected by the use of a steel roller. Tests for conformity with the specified<br />

crown, grade, and smoothness shall be made immediately after initial<br />

compaction. Before continuing the rolling any variation shall be corrected by<br />

removing or adding materials as necessary. The course shall then be rolled,<br />

using pneumatic-tired rollers or tandem rollers, while the mixture is hot and in<br />

SERIES 1800B Page 12 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

condition suitable for proper compaction. The speed of the roller shall not<br />

exceed 3-miles per hour and shall at all times be slow enough to avoid<br />

displacement of the hot mixture. Any displacement of the mixture shall be<br />

corrected at once by the use of rakes and fresh mixture applied or mixture<br />

removed as required. Rolling shall be continued until all roller marks are<br />

eliminated and the course has a density of at least 96 percent of the density<br />

obtained in a laboratory specimen of the same mixture when subjected to 50<br />

blows per side in the Marshall mold. During rolling, rollers shall be moistened<br />

to prevent adhesion of the mixture to the rolling surfaces, but an excess of<br />

water shall not be permitted. Competent and experienced roller men shall<br />

operate the rollers. At least two rollers shall be provided for each spreading<br />

machine operation on the job. Additional 10-ton rollers shall be provided if the<br />

specific pavement density is not obtained by the operation of the minimum<br />

number of rollers. In all places not accessible to the rollers, the mixture shall<br />

be compacted thoroughly with hot mechanical or manual hand tampers. Skin<br />

patching of an area that has rolled will not be permitted. Any mixture that<br />

becomes mixed with foreign material or defective shall be removed, replaced<br />

with fresh mixture, and compacted to the density of the surrounding area. The<br />

roller shall pass over the unprotected edge of the course only when the laying<br />

of the course is to be discontinued for a length of time to permit the mixture to<br />

become cold. The Contractor shall provide competent workmen who are<br />

capable of performing all work incidental to the correction of all pavement<br />

irregularities. After final rolling, no vehicular traffic of any kind shall be<br />

permitted on the pavement until it has cooled and hardened, and in no case<br />

less than 6 hours.<br />

3.6 FIELD SAMPLING AND TESTING: Samples shall be supplied as specified<br />

herein by the Contractor at his expense. The Contractor at his expense will<br />

conduct testing. All materials and material sources shall be approved not less<br />

than 30 days prior to the use of such material in the work. Duplicate samples<br />

shall be approved to the Contracting Officer on an average of one sample a<br />

week. The duplicates samples shall be taken at the same time and in the same<br />

manner as the original ones.<br />

3.6.1.1 Sampling:<br />

3.6.1.1 Aggregates at Source: Prior to production and delivery of<br />

aggregates, at least one initial sample will be taken in accordance with<br />

ASTM D75/D75M at the source. Each sample shall be collected by<br />

taking three incremental samples at random from the source material<br />

to make a composite sample of not less than 50 pounds. Three<br />

random samples shall be taken from each 3,000 tons of material, or a<br />

day’s run, thereafter during the course of the project. Three increments<br />

shall be taken at random to make a composite sample of not less than<br />

50 pounds. A repetition of the above sampling shall be made when<br />

the source of material is changed or when unacceptable deficiencies<br />

or variation form the specified grading of materials are found in testing.<br />

3.6.1.2 Cold Feed Aggregate Sampling: Two samples shall be taken daily<br />

from the belt conveying materials from the cold feed. Materials shall<br />

be collected in three increments at random to make representative<br />

SERIES 1800B Page 13 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

composite sample of not les than 50 pounds. Samples shall be taken<br />

by a method approved by the Contracting Officer.<br />

3.6.1.3 Fine Aggregates: A 50-pound sample shall be taken form the cold<br />

feed at least two times daily for sieve analyses of fine aggregate and<br />

specific gravity tests. Additional samples may be required to perform<br />

more frequent tests on mineral fillers, or will be required when<br />

analyses show deficiencies, or unacceptable variances or deviations.<br />

Sampling can be reduced to once a day when test results show that<br />

the fines consistently meet specified requirements. The method of<br />

sampling shall be as described herein for aggregates.<br />

3.6.1.4 Bituminous Mix: One sample for each 400 tons, or fraction thereof, of<br />

the un-compacted shall be taken each day for the extraction test. The<br />

sample shall be taken form a truck behind the paver. The minimum<br />

sample shall be 20 pounds. One sample for each 400 tons, or fraction<br />

thereof, shall also be taken of the un-compacted mix each day for<br />

stability testing. The minimum sample shall be 15 pounds. The<br />

samples shall be taken in a clean scoop or shovel by the Contracting<br />

Officer. The size of the sample shall be governed by the maximum<br />

size of particle of mineral aggregate in the mixture in accordance with<br />

ASTM D979. Samples cores at least three inches in diameter shall be<br />

obtained at locations determined by random sampling method, Asphalt<br />

Institute Manual MS-1 (Appendix P) from the completed pavement, for<br />

density tests. Cores shall be carefully removed and shall be delivered<br />

undisturbed and undamaged to a laboratory selected by the Contractor<br />

and approved by the Contracting Officer, without delay<br />

3.6.1.5 Sample Identification: The sample shall be contained in a clean<br />

container, which shall be securely fastened to prevent loss of material.<br />

Each sample shall be tagged for identification. The tag shall contain<br />

the following information.<br />

Contract No. ______________________<br />

Sample No. ______________________<br />

Quality ______________________<br />

Date of Sample ______________________<br />

Sample ______________________<br />

Source ______________________<br />

Intended Use ______________________<br />

For Testing ______________________<br />

3.7 Testing:<br />

3.7.1 Aggregate Testing: Testing of aggregates shall be made on each<br />

sample without delay. Gradation tests shall be made on each sample<br />

in accordance with ASTM C136. Mineral filler shall be tested in<br />

accordance with ASTM D546.<br />

SERIES 1800B Page 14 of 16


NORTHERN YAP ROAD IMPROVEMENTS PROJECT<br />

TECHNICAL SPECIFICATIONS Addendum No. 1 (11-29-2010)<br />

3.7.1.1 Abrasion: The aggregate shall be tested for wear (Los Angeles<br />

test) in accordance with ASTM C131.<br />

3.7.1.2 Stripping Test: A stripping test in accordance with ASTM D1664<br />

shall be performed initially on all aggregate prior to incorporation<br />

into the work.<br />

3.7.2 BITUMINOUS MIX TESTING: One sample for entire project<br />

requirements of the un-compacted mix shall be tested for extraction in<br />

accordance with ASTM D2172 and sieve analysis in accordance with<br />

AASTO T30. One sample for entire project requirements shall be<br />

tested for stability and flow in accordance with ASTM D1559.<br />

3.7.3 TESTING OF PAVEMENT COURSE:<br />

3.7.3.1 The compacted surfaces of the wearing course shall be<br />

straightedge tested as the work progresses. The straightedge test<br />

shall be applied parallel with and at right angles to the centerline<br />

after final rolling. Variations in the wearing course shall not vary<br />

more than plus or minus 1/8-inch in ten feet. Any portion of the<br />

pavement showing irregularities greater than that specified shall<br />

be corrected as directed by the Contracting Officer.<br />

****** END OF SECTION ******<br />

SERIES 1800B Page 15 of 16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!