<strong>Wambo</strong> <strong>Coal</strong> Pty Limited <strong>AEMR</strong> <strong>2011</strong>-<strong>2012</strong><br />

Summary of Environmental Incidents<br />

1 July <strong>2011</strong> - 30 June <strong>2012</strong><br />

NO<br />

DATE<br />

RECEIVED<br />

AREA<br />

RESPONSIBLE<br />

CAT.<br />

1 20/9/<strong>2011</strong> Projects - Daracon 1<br />

ISSUE<br />

Excessive dust generation from Project works<br />

NWCD<br />

ACTION TAKEN<br />

Vegetation had been cleared over the previous week,<br />

exposing bulldust on high wind day.<br />

Very windy day – wind speed between 8am and 4pm<br />

on 20/9/<strong>2011</strong> was 9.5m/s @ 280 degrees (WNW).<br />

More formalised assessment of dust potential, and<br />

modification of operations in response to climatic<br />

conditions (as put into practice on the high wind day).<br />

Introduction of a second water cart. Currently a<br />

smaller subcontractor’s cart is being used, while a<br />

second (or, if required, third) large water cart is being<br />

sourced and prepared for use.<br />

Establishment of a second water refill standpipe, to<br />

provide greater flexibility in water cart refilling, and<br />

ensure greater watering coverage.<br />

Modification of refill standpipes to prevent the<br />

recurrence of the refilling difficulties caused by the<br />

strong wind gusts on the day of the incident.<br />

Identification of topsoil material with high dust<br />

potential (i.e. bulldust), and the prioritised<br />

management (stripping, stockpiling and stockpile<br />

revegetation) of that material, as permitted by<br />

prevailing weather conditions. Once the topsoil<br />

material has been stripped, stockpiled and<br />

revegetated, it is expected that the underlying clay<br />

material will represent a much lesser dust risk.<br />

• Implementation of processes for the regular<br />

inspection of the project site, closer assessment of<br />

dust monitoring results, and provision of timely<br />

feedback to the project contractors.<br />

2 6/10/<strong>2011</strong> Projects - Daracon 1 Creek line Disturbance<br />

<br />

<br />

<br />

Authorisation (DA approval) had been obtained to<br />

clear ground for construction of NWC Diversion.<br />

Vegetation clearance and ground disturbance had<br />

occurred prematurely for entire area of flood bund<br />

section of creek, causing unnecessary disturbance,<br />

and increasing erosion/ sedimentation risk.<br />

Section of impacted creek line to be revegetated. Turf<br />