Wambo Coal AEMR 2011-2012 - Peabody Energy
Wambo Coal AEMR 2011-2012 - Peabody Energy
Wambo Coal AEMR 2011-2012 - Peabody Energy
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>2011</strong>-<strong>2012</strong> <strong>AEMR</strong><br />
2.4.3 Underground Operations<br />
WCPL’s North <strong>Wambo</strong> Underground (NWU) mines<br />
the <strong>Wambo</strong> seam using continuous miners and<br />
longwall mining methods. The first of eight longwall<br />
blocks (LW1) was completed in February 2009 and<br />
production commenced in the second longwall block<br />
(LW2) in March 2009. In December 2010, extraction<br />
of Longwall Panel 3 (LW3) was completed, with<br />
production of Longwall Panel 4 (LW4) commencing<br />
in January <strong>2011</strong>. During November <strong>2011</strong> LW4 was<br />
completed. Extraction of Longwall Panel 5 (LW5)<br />
commenced during December <strong>2011</strong>. At the end of<br />
the reporting period LW5 had retreated<br />
approximately 2,858m. The completion of LW5 is<br />
expected during August <strong>2012</strong>. The NWU continues<br />
to operate seven days a week.<br />
In total 8 x 250m wide Longwall panels,<br />
approximately 3.8 km to 4 km in length will be<br />
developed with the Longwall panels orientated<br />
south-west to north-east. Longwall panels one to<br />
five will be developed off main headings driven from<br />
the existing Bates North Open Cut highwall. The<br />
remaining three panels will be developed by punch<br />
mining directly off the Homestead Pit Open Cut<br />
highwall.<br />
WCPL primarily use Joy Mining Longwall<br />
equipment, including the Longwall operating<br />
system. The Longwall panels are formed by driving<br />
two sets of gateroads (the tailgate and maingate<br />
roads). Each gateroad requires two roadways<br />
(headings) to be driven parallel to each other (31 m<br />
apart). One of the roadways is used for personnel<br />
and materials access and fresh air intake ventilation<br />
while the other is used for coal clearance and return<br />
air ventilation. The roadways are developed using<br />
two Joy 12CM30 continuous miners. Approximately<br />
77,382m of development has occurred since the<br />
commencement of North <strong>Wambo</strong> Underground, with<br />
a total of 17,695m of Longwall retreat.<br />
The headings are connected every 100m by driving<br />
a cut through from one heading to another. This<br />
forms pillars of coal along the length of the<br />
gateroad. The tailgate and maingate roads are<br />
separated by the 250 m wide Longwall panel. The<br />
maingate roads and tailgate roads are then linked<br />
together by driving an installation road and bleeder<br />
road at the inbye end of the longwall panels.<br />
As the continuous miners develop the roadways,<br />
Run of Mine (ROM) coal is conveyed to a stockpile<br />
with an approximate 70,000 tonne capacity. When<br />
a sufficient stockpile is present, coal is loaded onto<br />
trucks for transport to the CHPP. During the <strong>2011</strong>-<br />
<strong>2012</strong> reporting period, approximately 4.79 Mt of<br />
ROM coal was produced by NWU.<br />
At the end of the reporting period the following<br />
equipment was available for mining activities at the<br />
Underground, including:<br />
<br />
<br />
<br />
<br />
2 x Joy 12CM29 Continuous miners;<br />
1 x Joy 12CM30 Continuous miner<br />
3 x electric shuttle cars with a 15 t payload;<br />
8 x Load Haul Dump (LHD) machines;<br />
9 x personnel transporters Specialised<br />
Mining Vehicles (SMV’s);<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
Associated longwall equipment;<br />
146 Joy Roof Supports;<br />
2 x Joy 7LS2a Shearers;<br />
2 x BSL and AFC systems;<br />
2 x Monorail system;<br />
2 x Pump sled; and<br />
2 x 5MVA Transformer<br />
The old Wollemi Underground Mine was on care<br />
and maintenance throughout the reporting period<br />
with no coal being produced from this mine. The old<br />
Wollemi workshop, bathhouse and store facilities<br />
previously used by the WCPL’s Underground<br />
operations were decommissioned during October<br />
2008 due to the completion of the new<br />
administration and bathhouse facilities. The sealing<br />
of the old Wollemi Mine was completed during the<br />
reporting period on 25 May <strong>2012</strong>.<br />
2.4.4 Open Cut Operations<br />
Downer EDI Mining are contracted to undertake<br />
Open Cut mining operations at WCPL. Open cut<br />
mining is divided into pits known as the Bates Pit,<br />
Bates South Pit, Montrose Pit and the Homestead<br />
Pit. The Bates Pit, Bates South Pit and the<br />
Montrose Pit are adjoining and linked via a mining<br />
corridor. The Homestead Pit is a separate mining<br />
area. Operations during the reporting period<br />
occurred in the Bates Pit, Bates South Pit, Montrose<br />
Pit and the Homestead Pit. The current Open Cut<br />
workings are presented in Figure 2.2.<br />
Mining of the Open Cut commences with the<br />
removal of vegetation and topsoil as described in<br />
Section 2.2. Following land preparation,<br />
excavators and trucks remove any weathered<br />
material as a “free dig” operation. The weathered<br />
material that can be free dug ranges from one metre<br />
to ten metres in thickness. The remaining<br />
overburden is drilled, blasted and removed utilising<br />
the excavators and rear dump haul trucks to<br />
uncover the coal.<br />
Page 22