01.11.2014 Views

Wambo Coal AEMR 2011-2012 - Peabody Energy

Wambo Coal AEMR 2011-2012 - Peabody Energy

Wambo Coal AEMR 2011-2012 - Peabody Energy

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>2011</strong>-<strong>2012</strong> <strong>AEMR</strong><br />

2.0 Operations During the<br />

Reporting Period<br />

2.1 Exploration<br />

Surface exploration throughout the reporting period<br />

consisted of a total of 147 boreholes at<br />

approximately 34,150 meters drilled. Exploration<br />

drilling occurred in the following<br />

areas;<br />

23 x boreholes within A444 with a total of<br />

3,350 m drilled;<br />

61 x boreholes within CCL743 with a total of<br />

19,500 m drilled;<br />

63 x boreholes within CL397 with a total of<br />

11,300 m drilled; and<br />

Drilling is required to further define coal reserves,<br />

coal quantity and gas content of the Whybrow,<br />

Redbank Creek, <strong>Wambo</strong>, Whynot, Arrowfield and<br />

Bowfield coal seams. All exploration boreholes were<br />

fully grouted upon completion.<br />

It is expected that exploration activities over the<br />

coming twelve months will continue within A444,<br />

CL397, CCL743 and EL7211. WCPL is anticipating<br />

drilling approximately 360 boreholes (approximately<br />

28,700 m) during the next reporting period. A444<br />

and EL7211 are both pending confirmation of<br />

renewal.<br />

2.2 Land Preparation<br />

In accordance with the Open Cut MOP and DA 305-<br />

2003, all land clearing at WCPL is carried out under<br />

approved management plans and procedures. One<br />

such approved management plan is the Flora and<br />

Fauna Management Plan (FFMP), which includes a<br />

Vegetation Clearance Protocol (Figure 2.1). In<br />

accordance with the FFMP, a Surface Disturbance<br />

Permit (SDP) procedure and checklist has been<br />

developed. The SDP requires the approval of<br />

WCPL’s environmental department prior to any<br />

clearing activities taking place. The SDP aims to<br />

identify any environmental issues such as Cultural<br />

Heritage sites, flora and fauna communities, surface<br />

drainage, threatened species, and the identification<br />

of any seed or timber resources that can be<br />

salvaged.<br />

In addition to the FFMP, WCPL have developed a<br />

Timber Management Plan (TMP). The TMP has<br />

identified a number of options regarding the<br />

management and salvage of timber resources,<br />

dependent on the characteristics of the vegetation<br />

to be cleared, and is determined on a case by case<br />

basis.<br />

Nominally, a minimum of 100 millimetres (mm) of<br />

topsoil is recovered from the surface prior to mining<br />

an area. The actual volume of topsoil recovered is<br />

dependent on the depth of insitu soil conditions (e.g.<br />

deeper in alluvial areas and shallower on ridge<br />

lines), and the quality of the material.<br />

Where possible, direct placement of stripped topsoil<br />

onto re-profiled areas is preferred to stockpiling, in<br />

order to avoid rehandling and reduce the potential<br />

for further topsoil degradation or loss. However, due<br />

to lack of available area, this was not possible<br />

during this reporting period. If a re-profiled surface is<br />

not available, the topsoil is stockpiled. The<br />

treatment of the topsoil stockpiles is dependent on<br />

the planned timeframe between construction and<br />

use. If these stockpiles are to be left for longer than<br />

three months, they are generally shaped into<br />

elongated mounds and seeded with pasture to keep<br />

the soil fertile, stop weeds from growing and to<br />

reduce soil loss.<br />

Due to a change in dump plan for the RL 160 dump,<br />

approximately 14.2ha of previously rehabilitated<br />

land was re-disturbed during the reporting period.<br />

The topsoil and established pasture vegetation was<br />

recovered from the re-disturbed area prior to<br />

dumping.<br />

2.3 Construction<br />

During the reporting period there were a number of<br />

major projects completed or commenced across<br />

WCPL operations, these included:<br />

Maingate 8 High Wall Stabilisation: The project<br />

included meshing and rock bolting of the high wall<br />

above the new portal entries in the former<br />

Homestead Pit. The project also completed<br />

stabilising the wall behind the main Homestead<br />

Ventilation Fan. The box culvert portal entries in the<br />

former Homestead Pit have now been placed into<br />

final position on the established hardstand pad.<br />

Ground shaping for internal drainage above the<br />

Homestead Pit at the entry to Maingate 8 has been<br />

completed, with drain overpass design to be<br />

completed during the next reporting period.<br />

Finalised plans of adjacent infrastructure areas<br />

including the electrical enclosures are due to be<br />

finalised in July <strong>2012</strong>.<br />

North <strong>Wambo</strong> Creek Diversion (Stage 3):<br />

Construction works were nearing completion on the<br />

final stage (i.e. Stage 3) of the North <strong>Wambo</strong> Creek<br />

Diversion program. At the end of the reporting<br />

period approximately 800,000 m 3 of excavation had<br />

been carried out to construct the permanent creek<br />

line around the old Wollemi Underground Portal<br />

area, in conjunction with revegetation works.<br />

Page 18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!