Wambo Coal AEMR 2011-2012 - Peabody Energy
Wambo Coal AEMR 2011-2012 - Peabody Energy
Wambo Coal AEMR 2011-2012 - Peabody Energy
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>2011</strong>-<strong>2012</strong> <strong>AEMR</strong><br />
2.0 Operations During the<br />
Reporting Period<br />
2.1 Exploration<br />
Surface exploration throughout the reporting period<br />
consisted of a total of 147 boreholes at<br />
approximately 34,150 meters drilled. Exploration<br />
drilling occurred in the following<br />
areas;<br />
23 x boreholes within A444 with a total of<br />
3,350 m drilled;<br />
61 x boreholes within CCL743 with a total of<br />
19,500 m drilled;<br />
63 x boreholes within CL397 with a total of<br />
11,300 m drilled; and<br />
Drilling is required to further define coal reserves,<br />
coal quantity and gas content of the Whybrow,<br />
Redbank Creek, <strong>Wambo</strong>, Whynot, Arrowfield and<br />
Bowfield coal seams. All exploration boreholes were<br />
fully grouted upon completion.<br />
It is expected that exploration activities over the<br />
coming twelve months will continue within A444,<br />
CL397, CCL743 and EL7211. WCPL is anticipating<br />
drilling approximately 360 boreholes (approximately<br />
28,700 m) during the next reporting period. A444<br />
and EL7211 are both pending confirmation of<br />
renewal.<br />
2.2 Land Preparation<br />
In accordance with the Open Cut MOP and DA 305-<br />
2003, all land clearing at WCPL is carried out under<br />
approved management plans and procedures. One<br />
such approved management plan is the Flora and<br />
Fauna Management Plan (FFMP), which includes a<br />
Vegetation Clearance Protocol (Figure 2.1). In<br />
accordance with the FFMP, a Surface Disturbance<br />
Permit (SDP) procedure and checklist has been<br />
developed. The SDP requires the approval of<br />
WCPL’s environmental department prior to any<br />
clearing activities taking place. The SDP aims to<br />
identify any environmental issues such as Cultural<br />
Heritage sites, flora and fauna communities, surface<br />
drainage, threatened species, and the identification<br />
of any seed or timber resources that can be<br />
salvaged.<br />
In addition to the FFMP, WCPL have developed a<br />
Timber Management Plan (TMP). The TMP has<br />
identified a number of options regarding the<br />
management and salvage of timber resources,<br />
dependent on the characteristics of the vegetation<br />
to be cleared, and is determined on a case by case<br />
basis.<br />
Nominally, a minimum of 100 millimetres (mm) of<br />
topsoil is recovered from the surface prior to mining<br />
an area. The actual volume of topsoil recovered is<br />
dependent on the depth of insitu soil conditions (e.g.<br />
deeper in alluvial areas and shallower on ridge<br />
lines), and the quality of the material.<br />
Where possible, direct placement of stripped topsoil<br />
onto re-profiled areas is preferred to stockpiling, in<br />
order to avoid rehandling and reduce the potential<br />
for further topsoil degradation or loss. However, due<br />
to lack of available area, this was not possible<br />
during this reporting period. If a re-profiled surface is<br />
not available, the topsoil is stockpiled. The<br />
treatment of the topsoil stockpiles is dependent on<br />
the planned timeframe between construction and<br />
use. If these stockpiles are to be left for longer than<br />
three months, they are generally shaped into<br />
elongated mounds and seeded with pasture to keep<br />
the soil fertile, stop weeds from growing and to<br />
reduce soil loss.<br />
Due to a change in dump plan for the RL 160 dump,<br />
approximately 14.2ha of previously rehabilitated<br />
land was re-disturbed during the reporting period.<br />
The topsoil and established pasture vegetation was<br />
recovered from the re-disturbed area prior to<br />
dumping.<br />
2.3 Construction<br />
During the reporting period there were a number of<br />
major projects completed or commenced across<br />
WCPL operations, these included:<br />
Maingate 8 High Wall Stabilisation: The project<br />
included meshing and rock bolting of the high wall<br />
above the new portal entries in the former<br />
Homestead Pit. The project also completed<br />
stabilising the wall behind the main Homestead<br />
Ventilation Fan. The box culvert portal entries in the<br />
former Homestead Pit have now been placed into<br />
final position on the established hardstand pad.<br />
Ground shaping for internal drainage above the<br />
Homestead Pit at the entry to Maingate 8 has been<br />
completed, with drain overpass design to be<br />
completed during the next reporting period.<br />
Finalised plans of adjacent infrastructure areas<br />
including the electrical enclosures are due to be<br />
finalised in July <strong>2012</strong>.<br />
North <strong>Wambo</strong> Creek Diversion (Stage 3):<br />
Construction works were nearing completion on the<br />
final stage (i.e. Stage 3) of the North <strong>Wambo</strong> Creek<br />
Diversion program. At the end of the reporting<br />
period approximately 800,000 m 3 of excavation had<br />
been carried out to construct the permanent creek<br />
line around the old Wollemi Underground Portal<br />
area, in conjunction with revegetation works.<br />
Page 18