CA NO: CDR/760TF/ / 2012-13 Ser Page No: 54<br />
3. Spares<br />
3.1 Any spares/ consumables required for replacement of defective parts, shall be supplied/ provided<br />
by the contractor of standard ISI mark.<br />
3.2 The unserviceable spares shall be handed over to Department.<br />
4. Transportation facilities at site<br />
4.1 No government vehicle will be provided.<br />
5. Maintenance Facilities<br />
5.1 The equipment at control room and panels on either end of the tunnel can be maintained during<br />
any hour of the day. However the maintenance of equipment inside the tunnel shall be carried out during<br />
night only.<br />
5.2 The hydraulically operated truck mounted platform (Hydra) and trolley available at site with BRO<br />
will be made available at no cost alongwith the driver.<br />
5.3 SMTs (Special Maintenance Tool) for maintenance and repairing will be arranged by the<br />
contractor.<br />
6. Payments<br />
6.1 Monthly payment (1/12 th of the amount of schedule ‘A’) shall be made on completion of each<br />
month for maintenance of system which the contractor shall submit the bill in the prescribed format.<br />
6.2 The contractor shall submit the bills on monthly basis for payments.<br />
7. Rules and Regulations<br />
7.1 All safety precautions shall be observed while executing the maintenance works.<br />
7.2 All statutory rules and regulations in force shall be observed.<br />
ACCEPTANCE OF SPARES<br />
8 (a) The spares will be provided by the contractor as mentioned in Para 3 under scope of work. The<br />
guarantee of the spares as provided by the manufacturer will be passes on to OC contract / Engineer-In-<br />
Charge by the contractor.<br />
(b) The Engineer-in-Charge shall exercise control over the quality of the materials so as to ascertain<br />
their conformity with specification/ requirement at the cost of the contractor. The testing shall be done as<br />
required by the Engineer-in-Charge.<br />
(c) Spares not confirming to the specification/ requirement given in the particular specification shall<br />
not be brought to the work site.<br />
(d)<br />
(e)<br />
All stores to be used in work to be got approved by Engineer-In-Charge/OC Contract.<br />
The cost of testing will be borne by Contractor.<br />
8. Performance Guarantee: Immediately on acceptance of the tender, the Contractor shall lodge a<br />
performance guarantee with Commander 760 BRTF, in the form of Bank Guarantee to the extent of 10%<br />
value of the Contract Agreement.<br />
___________________________<br />
(Signature of contractor with seal)<br />
sd/- xxx<br />
SW<br />
For Accepting Officer