CA NO: CDR/760TF/ / 2012-13 Ser Page No: 48<br />
(d) The first return shall be submitted immediately after any plant or equipment is brought to<br />
the site. Thereafter every week changes in return shall be furnished in the following form-<br />
Ser No Particulars of Plant /<br />
Eqpt<br />
Total No at site<br />
of work<br />
Location<br />
Remarks<br />
Additional since ------------------------------<br />
Reduction -----------------------------<br />
(Signature of contractor)<br />
--------------------------------------------------------------------------------------------------------------------<br />
(e) A complete return showing the upto date position of plant / equipment at site shall be<br />
submitted on 15 th of every month till the works are completed and the site cleared.<br />
(f) The contractor’s attention is invited to condition 34 of DGBR General Conditions of<br />
contracts according to which no tool, plant /equipment shall be removed off the site without written<br />
approval of the OC contract.<br />
12. LOSS OR DAMAGE ON ACCOUNT OF ENEMY ACTION<br />
(a)<br />
If as a result of enemy action, the contractor suffers any loss or damage, the<br />
government shall reimburse to the contractor such loss or damages, to the extent and in<br />
the manner herein after provided: -<br />
(i) The loss suffered by him on account of any damage or destruction of his plant /<br />
equipment (as defined in condition 11 (b) above) or materials or any part or parts thereof.<br />
The amount of losses assessed by the Accepting Officer of the contract on this account<br />
shall be final and binding.<br />
(ii) Compensation paid by him under any law for the time being in force to any<br />
workmen employed by him for any injury caused to him or the workmen’s legal<br />
successor for loss of the workmen’s life.<br />
(b) No requirement shall be made nor shall any compensation be payable under the above<br />
provisions unless the contractor had taken Air Defence Precautions ordered in writing by OC<br />
concerned or in the absence of such orders, reasonable precautions. No re-imbursement shall be<br />
made nor shall any compensation be payable for any plant/Eqpts or materials not lying on the site<br />
of work at the time of enemy action.<br />
13. TIME AND PROGRESS CHART<br />
(a) The time and progress chart to be prepared as per general Condition of Contract shall<br />
consist of detailed net work analysis and a time schedule. The critical path net work will be drawn<br />
jointly by the OC Contract and the contractor soon after acceptance of the tender. The time<br />
scheduling of the activities including a net work for all preliminary arrangements for mobilization of<br />
resources e.g. Man power, Plant and Machinery will be done by the contractor, completion of the<br />
time schedule will be prepared and submitted by the contractor to OC Contract who will approve it<br />
after due scrutiny. The schedule will be submitted in quadruplicate within one week from the date<br />
of handing over the site.<br />
___________________________<br />
(Signature of contractor with seal)<br />
sd/- xxx<br />
SW<br />
For Accepting Officer