September 2010|1 - KazEnergy
September 2010|1 - KazEnergy
September 2010|1 - KazEnergy
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>September</strong> 2010|8<br />
Kazakhstan North-South Transit Project was<br />
carried out in accordance with the approved<br />
Environmental Action Plans agreed with the<br />
project’s financial backers – European Bank<br />
for Reconstruction and Development and the<br />
International Bank for Reconstruction and<br />
Development.<br />
The accepted project decisions were in<br />
compliance with regulatory requirements for<br />
sanitary and environmental safety. During<br />
implementation of the Construction of 500<br />
kV Second Transmission Line of Kazakh-<br />
ENvirONmENTal priOriTiES iN KEgOC’S<br />
OpEraTiON arE DETErmiNED by KazaKhSTaN’S<br />
aCCESSiON TO WTO, aND ThE implEmENTaTiON<br />
Of a STraTEgy fOr KazaKhSTaN TO JoiN thE<br />
woRld’s top 0 most compEtitivE couNtRiEs<br />
ANd coRpoRAtE GovERNANcE codE.<br />
stan North-South Transit Project at 500 kV<br />
YuKGRES SS, Agadyr SS and Ekibastuz SS,<br />
17 sets of SF6 circuit-breakers were installed.<br />
This equipment and the equipment installed<br />
under the Kazakhstan Electricity Transmission<br />
Rehabilitation Project comply with environmental<br />
standards and reduce negative impact<br />
on the environment.<br />
During construction works on substation<br />
upgrading and line construction all actions<br />
are performed in line with air, land, surface<br />
and underground water protection.<br />
When planning NPG development<br />
projects – new investment projects for the<br />
upgrading and construction of electric grid<br />
facilities – the Terms of Reference include<br />
requirements for meeting environmental legislation<br />
during designing and implementation<br />
of projects. At present during implementation<br />
of the Kazakhstan Electricity Transmission<br />
Rehabilitation Project – Phase II, Moinak<br />
Electricity Transmission Project, Alma Electricity<br />
Transmission Project, and Reconstruction<br />
of 220 kV OHTL TsGPP–Ossakarovka Project,<br />
the preliminary environmental impact assessment<br />
(PEIA) is carried out under the FS of the<br />
projects mentioned. The opinions of the State<br />
Environmental Experts for PEIA was obtained<br />
for both the Kazakhstan Electricity Transmission<br />
Rehabilitation Project – Phase II and the<br />
Alma Electricity Transmission Project.<br />
During the environmental impact assessment<br />
of the new projects the Company<br />
considers the opinions of stakeholders and<br />
conducts public hearings. Thus, in 2009 the<br />
hearings were conducted for the Moinak<br />
Electricity Transmission Project and Alma<br />
Electricity Transmission Project.<br />
The World Bank conducted its own<br />
independent assessment of these projects,<br />
and based on its findings the projects are acknowledged<br />
to comply with the environmental<br />
policy of the Bank. It should be noted that<br />
the environmental actions of KEGOC were<br />
also acknowledged as satisfactory under the<br />
other projects implemented by the Company.<br />
AiR EmissioNs<br />
fRom thE<br />
bRANchEs’<br />
ActivitY wERE<br />
.3t/YEAR iN 200<br />
iNcludiNG 1.6t of<br />
NoÕ, .t of soÕ<br />
ANd 1.t of ÑoÕ.