Triton XR-70,Triton XL & Groundhog® Butterfly Valves (24” & Larger) MAINTENANCE Maintenance of valves by owner is generally limited to actuators and shaft seals. In some instances, valve design permits field adjustment seats when leakage occurs. Unless the owner has skilled personnel and proper equipment, any major rework will require removal of the valve from the line. Depending on condition, valve may require return to the manufacturer. ANNUAL MAINTENANCE 1. Cycle valve to verify operation and no interference in line. 2. Close valve and check for leakage. If leakage is detected, check actuator stops to verify that disc is fully closed. If leakage persists, remove valve to inspect seat. Contact Pratt’s Field Service Deparment for information regarding adjustment or replacement of seat. 3. 4. Check flange connections for leakage. Tighten bolts accordingly. Check top trunnion area for shaft leakage. If leakage is detected, replace valve packing. 5. If Access to the line is possible, then removal of scale that may interfere with disc travel is suggested. The seat should be inspected for wear and the taper pin nuts should be tight. NOTE: LUBRICATION IS NOT REQUIRED. WARNING Removal of actuator from valve shaft will cause disc to rotate, striking persons or objects in the disc path, causing injury to persons and damage to valve. Block or lock disc before removing actuator. Typical maintenance would be shaft packing replacement and actuator adjustment. Seal leakage, broken parts and difficult operation should be discussed with Pratt’s Service Department before valve repairs are attempted. Pratt Service Engineers are available to perform or supervise valve repairs in the field. Stop line flow and isolate from line pressure prior to performing any corrective maintenance. After completing repair, cycle valve through one complete operating cycle and after line pressure has been restored, inspect for leakage. 24TRIGD Revision Date: 7/13/10 10
Triton XR-70,Triton XL & Groundhog® Butterfly Valves (24” & Larger) TROUBLESHOOTING GUIDE Problem Causes Remedies •Packing Leak Leakage between valve and actuator •First, cycle the valve several times. This should adjust the packing. If this fails, clean packing bore and replace packing. Bottom trunnion leaks •Packing or gasket leak •Replace bottom shaft packing, o-ring or gasket. Valve leaks when closed •Disc not fully closed or past fully closed •Adjust actuator closed position stop. •Disc edge wear or damage •Rubber seat wear or damage •Clean and/or repair disc edge. •Adjust or replace valve seat* Chainwheel jams •Poorly fitting chain •Replace with correct chain. Valve hard to operate •Foreign material in valve •Remove obstructions Automatic valve does not actuate •Corroded actuator parts •Loose actuator •No power source •Improper Signal •Burned out or impaired component •Clean and grease actuator •Apply Loctite or Omnifit locking compound and tighten bolts. •Check incoming power source and replace fuses or reset pressure. •Check actuating signal sequence. •Check and repair or replace solenoids, motors and relay devices. * Seat replacement should not be performed by untrained/unqualified personnel. In the event that seat replacement is needed, please contact Henry Pratt Field Service. 24TRIGD Revision Date: 7/13/10 11
- Page 87 and 88: 401 S. Highland Avenue Aurora, Illi
- Page 89 and 90: A Tradition of Excellence With the
- Page 91 and 92: Scope of Line: Triton XR-70 Butterf
- Page 93 and 94: Design Details: Triton XR-70 Butter
- Page 95 and 96: E-Lok Seat Design Years of Reliable
- Page 97 and 98: Water Flow Characteristics Proven P
- Page 99 and 100: Valve End Types and Dimensions: Mec
- Page 101 and 102: Actuation Traveling Nut Type Manual
- Page 103: 401 S. Highland Avenue Aurora, Illi
- Page 106 and 107: SCOPE OF THE LINE: PRATT HP250II B
- Page 108 and 109: THE HENRY PRATT SEAT ON BODY DESIGN
- Page 110 and 111: HP250II 3"- 20", DUCTILE IRON BODY
- Page 112 and 113: 401 S. Highland Avenue Aurora, Illi
- Page 114 and 115: Suggested Specification: Butterfly
- Page 116 and 117: 6" - 24" HP350 Mechanical Joint End
- Page 118 and 119: 3”-20” 2FII & Groundhog® Bonde
- Page 120 and 121: 3”-20” 2FII & Groundhog® Bonde
- Page 122 and 123: 3”-20” 2FII & Groundhog® Bonde
- Page 124 and 125: 3”-20” 2FII & Groundhog® Bonde
- Page 126 and 127: 3”-20” 2FII & Groundhog® Bonde
- Page 128 and 129: 3”-20” 2FII & Groundhog® Bonde
- Page 130 and 131: Triton XR-70,Triton XL & Groundhog
- Page 132 and 133: Triton XR-70,Triton XL & Groundhog
- Page 134 and 135: Triton XR-70,Triton XL & Groundhog
- Page 136 and 137: Triton XR-70,Triton XL & Groundhog
- Page 140 and 141: Triton XR-70,Triton XL & Groundhog
- Page 142 and 143: Triton XR-70,Triton XL & Groundhog
- Page 144 and 145: 24”-48” HP250II Butterfly Valve
- Page 146 and 147: 24”-48” HP250II Butterfly Valve
- Page 148 and 149: 24”-48” HP250II Butterfly Valve
- Page 150 and 151: 24”-48” HP250II Butterfly Valve
- Page 152 and 153: 24”-48” HP250II Butterfly Valve
- Page 154 and 155: 24”-48” HP250II Butterfly Valve
- Page 156 and 157: HP350 Butterfly Valve 6”-24” (M
- Page 158 and 159: HP350 Butterfly Valve Table of Cont
- Page 160 and 161: HP350 Butterfly Valve INSTALLATION
- Page 162 and 163: HP350 Butterfly Valve TESTING When
- Page 164 and 165: HP350 Butterfly Valve WARNING Fluid
- Page 166 and 167: HP350 Butterfly Valve TROUBLESHOOTI
- Page 168 and 169: HP350 Butterfly Valve Cross Section
- Page 170 and 171: Diviner Position Indicator SAFETY M
- Page 172 and 173: Diviner Position Indicator FUNCTION
- Page 174 and 175: Diviner Position Indicator INSTALLA
- Page 176 and 177: Diviner Position Indicator HOW TO C
- Page 178 and 179: PAINT SYSTEM SUMMARY Page 1 of 5 SY
- Page 180 and 181: Page 3 of 5 UL/FM HENRY PRATT COMPA
- Page 182: Page 5 of 5 UL/FM HENRY PRATT COMPA
- Page 185 and 186: A Tradition of Excellence With the
- Page 187 and 188: MANUAL ACTUATORS Spur G
Triton XR-70,Triton XL & Groundhog®<br />
<strong>Butterfly</strong> <strong>Valves</strong> (24” & Larger)<br />
MAINTENANCE<br />
Maintenance of valves by owner is generally limited to actuators and shaft seals. In some instances, valve design<br />
permits field adjustment seats when leakage occurs. Unless the owner has skilled personnel and proper<br />
equipment, any major rework will require removal of the valve from the line. Depending on condition, valve may<br />
require return to the manufacturer.<br />
ANNUAL MAINTENANCE<br />
1.<br />
Cycle valve to verify operation and no interference in line.<br />
2. Close valve and check for leakage. If leakage is detected, check actuator stops to verify that disc is<br />
fully closed. If leakage persists, remove valve to inspect seat. Contact Pratt’s Field Service Deparment<br />
for information regarding adjustment or replacement of seat.<br />
3.<br />
4.<br />
Check flange connections for leakage. Tighten bolts accordingly.<br />
Check top trunnion area for shaft leakage. If leakage is detected, replace valve packing.<br />
5. If Access to the line is possible, then removal of scale that may interfere with disc travel is suggested.<br />
The seat should be inspected for wear and the taper pin nuts should be tight.<br />
NOTE: LUBRICATION IS NOT REQUIRED.<br />
WARNING<br />
Removal of actuator from valve shaft will cause disc to rotate, striking persons or objects in the disc<br />
path, causing injury to persons and damage to valve. Block or lock disc before removing actuator.<br />
Typical maintenance would be shaft packing replacement and actuator adjustment. Seal leakage, broken parts<br />
and difficult operation should be discussed with Pratt’s Service Department before valve repairs are attempted.<br />
Pratt Service Engineers are available to perform or supervise valve repairs in the field.<br />
Stop line flow and isolate from line pressure prior to performing any corrective maintenance.<br />
After completing repair, cycle valve through one complete operating cycle and after line pressure has been<br />
restored, inspect for leakage.<br />