24.10.2014 Views

Commuter Rail AC Electrification Load-Flow Simulation Report - RTD

Commuter Rail AC Electrification Load-Flow Simulation Report - RTD

Commuter Rail AC Electrification Load-Flow Simulation Report - RTD

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Commuter</strong> <strong>Rail</strong> <strong>AC</strong> <strong>Electrification</strong> <strong>Load</strong>-<strong>Flow</strong> <strong>Simulation</strong> <strong>Report</strong> Revision 1<br />

• Two paralleling stations were located along the East Corridor,<br />

• One paralleling station was located along the Gold Line, and<br />

• Three paralleling stations were located along the North Metro Corridor<br />

The purpose of the paralleling stations is to parallel the catenary and feeder systems, provide<br />

feeder and catenary sectioning, and to supply power from the feeder/catenary system to the catenary/rail<br />

system.<br />

Two sets of traction power supply system studies were performed, with substations connected<br />

to Xcel Energy’s 115 kV transmission network and configured as follows:<br />

• In the first study set, both substations, Sandown and Argo, were equipped with two<br />

traction power transformers.<br />

• In the second study set, the Sandown substation was equipped with two traction power<br />

transformers and the Argo substation was equipped with only one traction power<br />

transformer.<br />

The modeled autotransformer system provided a significant operating margin for the electrical<br />

traction power system. Minimum voltages along the three corridors were well above industry<br />

standards ensuring satisfactory operation under normal operating conditions, with all systems in<br />

service, and under particularly severe contingency operation with one substation (both<br />

transformers) out-of-service. The total system power demand averaged over 2 hours is<br />

approximately 15 MVA. Taking into consideration the fluctuating power demand of the traction<br />

power loads, short-term overloads and the requirement for transformer and substation<br />

contingency operation, a preliminary continuous rating of 12.5 MVA should be considered for<br />

each substation transformer when two transformers per substation can be installed. In the<br />

event that only one transformer can be installed in Argo substation, it is recommended that 15<br />

MVA rating for each transformer be considered. Further, it is recommended that a standard<br />

continuous rating for each autotransformer be 2.5 MVA. These ratings would allow operation of<br />

EMUs on the East Corridor, Gold Line, and the North Metro Corridor.<br />

Since the autotransformer-fed system performed with a significant operational margin,<br />

consideration should be given to the utilization of 1x25 kV direct-fed system. Preliminary results<br />

indicate that the 1x25 kV system might be effective but more comprehensive simulations would<br />

be required to ensure its viability. It is believed that this alternative system would be much<br />

simpler, substantially less expensive to build and maintain, and provide more efficient utilization<br />

of equipment.<br />

Regardless of whether an autotransformer-fed system or direct-fed system is selected for<br />

implementation, it is recommended that a utility impact study be performed. A key element of<br />

the study should be investigation into the effects of the fluctuating traction power load on the<br />

transmission system including a voltage flicker study. The unbalanced nature of the load due to<br />

phase-to-phase substation transformer connections should be evaluated and the levels of<br />

negative sequence currents in nearby generators determined. Further, the study should<br />

evaluate the effects of harmonics generated by the rolling stock on total and individual harmonic<br />

distortion of voltages and currents at the point of common coupling and assess the likelihood of<br />

utility system resonance.<br />

02/27/2009 FRSC Page 2 of 250

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!