exceeded 100 million US dollars. For the<br />
construction of the delayed coker, the partners<br />
developed a financing concept for an<br />
investment volume of 430 million US dollars.<br />
Financing packages for the mild hydro<br />
cracker and the delayed coker, amounting<br />
to over 540 million dollars in total, were<br />
arranged and internationally syndicated in<br />
New York. Both financing concepts were<br />
well oversubscribed, which proves the<br />
attractiveness of the business model and<br />
Chile as a location of industry and commerce.<br />
In 2005, the financing of the<br />
delayed coker was given the title “Latin<br />
America Deal of the Year 2005” by the internationally<br />
renowned financing magazine<br />
“Project Finance International”. The project<br />
was seen as “the most important projectrelated<br />
financial operation of the year<br />
2005 in Latin America”.<br />
49%<br />
ENAP Group<br />
TASK FORCE IN MADRID<br />
Process licensor for the delayed coker<br />
is Foster Wheeler, a well-known plant<br />
constructor from the USA. Foster Wheeler<br />
Iberia, Madrid, and Técnicas Reunidas,<br />
Madrid, are responsible for the full<br />
engineering. The equipment is delivered<br />
by Foster Wheeler, Técnicas Reunidas<br />
and MAN <strong>Ferrostaal</strong>. For this reason,<br />
a temporary project company (Union<br />
Temporal de Empresas) was established<br />
in Spain, with MAN <strong>Ferrostaal</strong> owning<br />
a stake of one third. This company<br />
executes the non-Chilean part of the<br />
contract from its Madrid location. A task<br />
force was established at Foster Wheeler<br />
Madrid into which the MAN <strong>Ferrostaal</strong><br />
project team was also delegated. The<br />
project management as well as all purchasing<br />
of equipment will be executed from<br />
there.<br />
CAPITAL OWNED – INVESTORS<br />
51%<br />
MAN <strong>Ferrostaal</strong> 17%<br />
Foster Wheeler Iberia 17%<br />
Técnicas Reunidas 17%<br />
PROCESSING SERVICES CONTRACT<br />
ENAP Refineria Aconcagua<br />
OPERATION AND MAINTENANCE CONTRACT<br />
ENAP Refineria Aconcagua<br />
LEASING CONTRACT<br />
ENAP Refineria Aconcagua<br />
FINANCING<br />
ENERCON S.A.<br />
PROJECT COMPANY<br />
<strong>THE</strong> <strong>ECHO</strong> 1/2006 51<br />
For the local tasks in Chile, the consortium<br />
partners established a joint venture in<br />
Santiago de Chile. The Chilean subsidiary<br />
of MAN <strong>Ferrostaal</strong>, DSD Chile, is responsible<br />
for the construction and assembly of the<br />
complete plant.<br />
Helmut Mühlemeier<br />
PLANT DELIVERY CONTRACT (TURNKEY)<br />
Consortium Foster Wheeler, Técnicas<br />
Reunidas, MAN <strong>Ferrostaal</strong><br />
CAPITAL BORROWED<br />
Credit international<br />
Banking syndicate