02.11.2012 Views

THE ECHO - Ferrostaal

THE ECHO - Ferrostaal

THE ECHO - Ferrostaal

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The new 60 MW Block 1 of the Wuppertal-Barmen plant reduces emissions of airborne<br />

pollutants by more than 50 percent.<br />

The crowded location of the new power plant in the Barmen<br />

district of Wuppertal, between the Wupper river and the Cologne-<br />

Hanover high-speed rail line, presented a particular challenge<br />

during this project: the existing power plant is located in a highdensity<br />

residential area. The new plant was constructed in very<br />

cramped conditions in the partly gutted buildings of the existing<br />

plant, which continued to be operational during the construction<br />

phase, and was then connected to parts of the existing plant.<br />

The construction phase remained on a very tight schedule within<br />

17 months. This meant that a buffer could be built into the timeconsuming<br />

phase that began with the first run-up of the gas turbine<br />

and included commissioning of all components, functional<br />

testing, and, finally, optimization. The agreed completion deadline<br />

of the end of 2005, which was necessitated by the regulations<br />

on cogeneration, was therefore never in question.<br />

The agreed timescale for the plant from signing the contract up to<br />

being ready for commercial use was just 22 months. The acceptance<br />

test for Phase 1 of the project, i.e., the integration of the existing DT<br />

23 steam turbines into the new electrotechnology and control<br />

technology infrastructure, was conducted as early as December<br />

2004. In December 2004 and January 2005, gas turbines, generators,<br />

and boiler components were delivered for assembly. In June 2005,<br />

the first gas turbine was started up, and, in December 2005,<br />

Wuppertaler Stadtwerke signed off on the completed plant.<br />

Helmut Wolff<br />

SCOPE OF SUPPLY AND SERVICES<br />

<strong>THE</strong> <strong>ECHO</strong> 1/2006 21<br />

>> Two 30 MW gas turbines from Hitachi in Japan, complete<br />

with generators, and two waste heat boilers manufactured<br />

by Innovative Steam Technology (IST) in Canada<br />

>> All electrical and process control technology<br />

>> Piping for water/steam circulation, including pumps and<br />

heat exchangers<br />

>> Installation of all essential auxiliary systems including a<br />

cooling water supply system, air inlets, fire protection<br />

installations, heating/climate control/air conditioning<br />

>> All required underground and structural engineering<br />

services<br />

>> Architectural design<br />

>> Design of all unit operations<br />

>> Detailed engineering<br />

>> Selection of all plant components<br />

>> Configuration of electrical and process control technology<br />

and safety equipment<br />

>> Construction of the new boiler house, foundation rafts for<br />

boilers and gas turbines<br />

>> Coordination and construction management<br />

>> Assembly of all components<br />

>> Commissioning and testing<br />

>> Documentation and training

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!