18<br />

projects & contracting<br />

01<br />

METHANOL PLANT IN OMAN<br />

OFF TO A GOOD START IN OMAN<br />

PROJECT DATA MO3000<br />

Project Company: Oman Methanol Company LLC (OMC)<br />

Owners:<br />

>> 50% MHIL (Methanol Holdings International Ltd.)<br />

>> 30% OMHC (Oman Methanol Holdings Company Ltd.)<br />

>> 20% FMIL (MAN <strong>Ferrostaal</strong> Methanol International Ltd.)<br />

Plant capacity: 3,000 ton per day (1,050,000 tons per year)<br />

Operation/License: Johnsson Matthey/PLC<br />

Low pressure methanol synthesis processes<br />

Main Plant Units:<br />

>> Process unit<br />

>> Operating material systems<br />

>> Methanol tanks<br />

>> Buildings<br />

>> Natural gas measuring station<br />

Work on the first methanol plant (M03000) in Oman is in full<br />

swing. MAN <strong>Ferrostaal</strong> is responsible for the engineering and procurement<br />

of the 523 million dollar project. After its completion,<br />

the MO3000 plant in Oman will produce more than 1 million tons<br />

of methanol per year. Engineering, procurement, construction<br />

and assembly are all running to schedule. After the financing<br />

contracts were signed and the project contracts came into effect<br />

in March 2005, the hot phase of the procurement of critical plant<br />

equipment began. The prerequisite for punctual ordering was for<br />

the engineering to be started early by the Japanese engineering<br />

company Toyo.<br />

Specifically, the following progress was made in the early summer<br />

of 2006: buildings 80 percent completed, roads 90 percent completed<br />

and foundations for the reformer, waste heat boiler, reactor<br />

and refinery column 100 percent completed. The installation<br />

of the main pipe bridge as well as the assembly of the methanol<br />

storage and water tanks is also completed. The mechanical completion<br />

of the plant is scheduled for the start of the third quarter<br />

of 2007.