<strong>NEDSS</strong> Phase II, Deliverables 1 and 2<br />

Schedule Summary<br />

The following table outlines the project schedule by phase. See appendix for detailed project<br />

plan which includes all tasks.<br />

WBS Phase Duration Begin Date End Date<br />

1 <strong>NEDSS</strong> IMPLEMENTATION 207.5d Tue 1/1/02 Thu 10/17/02<br />

1.1 PLANNING PHASE 34d Tue 1/1/02 Fri 2/15/02<br />

1.2 REQUIREMENTS PHASE 69.5d Fri 1/11/02 Thu 4/18/02<br />

1.3 DESIGN PHASE 60d Tue 4/16/02 Tue 7/9/02<br />

1.4 BUILD PHASE 120.5d Tue 2/26/02 Tue 8/13/02<br />

1.5 TEST PHASE 84.5d Fri 3/29/02 Thu 7/25/02<br />

1.6 IMPLEMENTATION PHASE 128.5d Wed 3/6/02 Mon 9/2/02<br />

1.7 REVIEW PHASE 33d Mon 9/2/02 Thu 10/17/02<br />

Evolution of the Plan<br />

The structure of this project plan is in compliance with the recommendations of IEEE Std. 1058-<br />

1998. The project plan will be maintained in Microsoft Project 2000, and will be disseminated<br />

both electronically and in hardcopy (where needed) by the contracted project manager. The<br />

contractor for this project will manage the project plan in cooperation with the BOH and be<br />

responsible for its configuration management process.<br />

After initial release of the draft plan, the contracted project manager will be responsible for<br />

maintaining the “master” project plan, and all earlier versions will be retained through the<br />

configuration process (check in / check out). A review protocol will be developed in the<br />

communication plan that will outline the process by which the plan is to be modified.<br />

References<br />

This document makes references to the following standards:<br />

IEEE Std 730-1998, IEEE Standard for Software Quality Assurance Plans<br />

IEEE Std 828-1998, IEEE Standard for Software Configuration Management Plans<br />

IEEE Std 1012-1998, IEEE Standard for Software Verification and Validation<br />

IEEE Std 1012-1998, IEEE Standard for Software Project Management Plans<br />

IEEE Std 1074-1997, IEEE Standard for Developing Software Life Cycle Processes<br />

PHRG Page 7 of 35 September 28, 2001