<strong>NEDSS</strong> Phase II, Deliverables 1 and 2<br />

Appendix D - Project Plan<br />

ID WBS Task Name Duration Start Finish Resource Initials<br />

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May<br />

49 1.2.6.1 Prepare document 5 days Fri 3/15/02 Fri 3/22/02 CON_QA<br />

Contractor Quality Assurance<br />

50 1.2.6.2 Conduct structured walkthrough(s) 1 day Fri 3/22/02 Mon 3/25/02 CON_QA<br />

Contractor Quality Assurance<br />

51 1.2.7 Data Migration Plan 11 days Mon 3/25/02 Tue 4/9/02<br />

52 1.2.7.1 Prepare document 10 days Mon 3/25/02 Mon 4/8/02 CON_TR<br />

53 1.2.7.2 Conduct structured walkthrough(s) 1 day Mon 4/8/02 Tue 4/9/02 CON_TR<br />

54 1.2.8 Data Dictionary Outline 5 days Tue 4/9/02 Tue 4/16/02 CON_TR<br />

55 1.2.9 Revise Project Plan 2 days Tue 4/16/02 Thu 4/18/02 CON_PM<br />

56<br />

57 1.3 DESIGN PHASE 60 days Tue 4/16/02 Tue 7/9/02<br />

58 1.3.1 Create Data Exchange Interface/Mapping Template 10 days Tue 4/16/02 Tue 4/30/02 CON_TR<br />

59 1.3.2 Create Logical Model 5 days Tue 4/30/02 Tue 5/7/02 CON_TR<br />

60 1.3.3 Create Data Flow Diagram (DFD) 5 days Tue 5/7/02 Tue 5/14/02 CON_TR<br />

61 1.3.4 Produce Data Dictionary 5 days Tue 5/14/02 Tue 5/21/02 CON_TR<br />

62 1.3.5 Requirements Traceability Matrix 5 days Tue 5/21/02 Tue 5/28/02 CON_PM<br />

63 1.3.6 Functional Design 7 days Tue 5/28/02 Thu 6/6/02<br />

64 1.3.6.1 Develop document 5 days Tue 5/28/02 Tue 6/4/02 CON_PM<br />

65 1.3.6.2 Conduct structured walkthrough(s) 1 day Tue 6/4/02 Wed 6/5/02 CON_PM<br />

66 1.3.6.3 Conduct Functional Design Review 1 day Wed 6/5/02 Thu 6/6/02 CON_PM<br />

67 1.3.7 Laboratory Data Exchange 5 days Thu 6/6/02 Thu 6/13/02<br />

68 1.3.7.1 Prepare Lab Data Mapping Matrices 5 days Thu 6/6/02 Thu 6/13/02 CON_TR<br />

69 1.3.8 Integration Test Plan (draft) 6 days Thu 6/13/02 Fri 6/21/02<br />

70 1.3.8.1 Prepare document 5 days Thu 6/13/02 Thu 6/20/02 CON_TR,DOT_TA,CON_QA<br />

71 1.3.8.2 Conduct structured walkthrough(s) 1 day Thu 6/20/02 Fri 6/21/02 CON_QA<br />

72 1.3.9 <strong>System</strong> Test Plan (draft) 6 days Fri 6/21/02 Mon 7/1/02<br />

73 1.3.9.1 Prepare document 5 days Fri 6/21/02 Fri 6/28/02 CON_TR,DOT_TA,CON_QA<br />

74 1.3.9.2 Conduct structured walkthrough(s) 1 day Fri 6/28/02 Mon 7/1/02 CON_QA<br />

75 1.3.10 Migration Plan 6 days Mon 7/1/02 Tue 7/9/02<br />

76 1.3.10.1 Prepare document 5 days Mon 7/1/02 Mon 7/8/02 CON_TR,BOH_PM<br />

77 1.3.10.2 Conduct structured walkthrough(s) 1 day Mon 7/8/02 Tue 7/9/02 CON_TR<br />

78 1.3.11 <strong>System</strong> Design Document 12 days Thu 6/6/02 Mon 6/24/02<br />

79 1.3.11.1 Prepare document 10 days Thu 6/6/02 Thu 6/20/02 CON_TR<br />

80 1.3.11.2 Conduct structured walkthrough(s) 1 day Thu 6/20/02 Fri 6/21/02 CON_TR<br />

81 1.3.11.3 Conduct Critical Design Review 1 day Fri 6/21/02 Mon 6/24/02 CON_TR<br />

82 1.3.12 Review Design with stakeholders 1 day Mon 6/24/02 Tue 6/25/02 CON_TR<br />

83 1.3.13 Revise Project Plan 1 day Mon 6/24/02 Tue 6/25/02 CON_PM<br />

84<br />

85 1.4 BUILD PHASE 120.5 days Tue 2/26/02 Tue 8/13/02<br />

86 1.4.1 Create Development Environment 3 days Tue 2/26/02 Thu 2/28/02 CON_TR,DOT_TA<br />

87 1.4.2 Installation Plan (draft) 6 days Tue 2/26/02 Tue 3/5/02<br />

88 1.4.2.1 Develop document 5 days Tue 2/26/02 Mon 3/4/02 CON_PM<br />

89 1.4.2.2 Conduct structured walkthrough(s) 1 day Tue 3/5/02 Tue 3/5/02 CON_PM<br />

90 1.4.3 Integration Test Plan (final) 2 days Tue 6/25/02 Thu 6/27/02 CON_TR<br />

91 1.4.4 <strong>System</strong> Test Plan (final) 2 days Thu 6/27/02 Mon 7/1/02 CON_TR<br />

92 1.4.5 Migration Plan 3 days Mon 7/1/02 Thu 7/4/02<br />

93 1.4.5.1 Develop document 2 days Mon 7/1/02 Wed 7/3/02 CON_TR<br />

94 1.4.5.2 Conduct structured walkthrough(s) 1 day Wed 7/3/02 Thu 7/4/02 CON_TR<br />

95 1.4.6 Support Plan (draft) 6 days Thu 7/4/02 Fri 7/12/02<br />

96 1.4.6.1 Prepare document 5 days Thu 7/4/02 Thu 7/11/02 CON_PM<br />

r 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quart<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Project Mgr.<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Project Mgr.<br />

Contractor Project Mgr.<br />

Contractor Project Mgr.<br />

Contractor Project Mgr.<br />

Contractor Technical Resource<br />

Contractor Technical Resource,DOTS Techni<br />

Contractor Quality Assurance<br />

Contractor Technical Resource,DOTS Techn<br />

Contractor Quality Assurance<br />

Contractor Technical Resource,BOH Project Mgr.<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

6/24<br />

Contractor Project Mgr.<br />

Contractor Technical Resource,DOTS Technical Advisor<br />

Contractor Project Mgr.<br />

Contractor Project Mgr.<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Technical Resource<br />

Contractor Project Mgr.<br />

Project: <strong>NEDSS</strong>_Implementation_98_20<br />

Date: Sun 9/30/01<br />

Task<br />

Split<br />

Progress<br />

Milestone<br />

Summary<br />

Project Summary<br />

External Tasks<br />

External Milestone<br />

External Milestone<br />

Deadline<br />

PHRG September 28, 2001