UDFCD <strong>BMP</strong> MONITORING SITES<br />
Permeable Interlocking Concrete Pavement<br />
system using perforated HDPE pipe. Locate each<br />
perforated pipe just upstream of the lateral-flow cut-off<br />
barrier. Do not exceed 20-foot spacing. Use a control<br />
orifice sized to drain the pore volume of empty each cell<br />
in 6 hours or more.<br />
Design Area Ratio The design area ratio shall not exceed 2.0 (ratio =<br />
And Effective contributing impervious area/pervious pavement area).<br />
Imperviousness The interim recommendations for the Effective<br />
Imperviousness are provided in the Manual.