UDFCD <strong>BMP</strong> MONITORING SITES<br />
Porous Asphalt Pavement<br />
Geotextile Fabric<br />
The geotextile fabric shall be installed below the s<strong>and</strong><br />
layer. The woven fabric shall conform to the following<br />
requirements:<br />
o ASTM D 4751 – AOS U.S. STD sieve #50 to #70<br />
o ASTM D 4633 – Minimum trapezoidal tear strength<br />
100 x 60 lbs<br />
o Minimum COE specified open area of 4%<br />
Possible geotextile fabric may be US 670, Mirafi<br />
Filterweave 500, or approved equivalent.<br />
Impermeable Liner<br />
Fabric <strong>and</strong> Liner<br />
Contained Cells<br />
When expansive or NRCS Type D soils are present, or<br />
potential for groundwater contamination exists, install a<br />
16 mil impermeable<br />
liner on the bottom <strong>and</strong><br />
sides of all areas to be<br />
paved including the<br />
bottom of the underdrain<br />
trench. The impermeable<br />
liner shall be wrapped to the top of the perimeter walls<br />
<strong>and</strong> attached to the sides securely.<br />
If soils are not expansive (NRCS Types A, B or C) use<br />
woven geotextile fabric (as described above) as a liner.<br />
Place fabric <strong>and</strong> liner by rolling parallel to the contours<br />
starting at the most downstream part of the pavement.<br />
Provide a minimum of 18” overlap between adjacent<br />
sheets. Bring up geotextile fabric <strong>and</strong> impermeable liner<br />
to the top of the perimeter walls <strong>and</strong> attach with roofing<br />
tar or other adhesive or concrete anchors. Provide<br />
sufficient slack in the geotextile fabric <strong>and</strong> impermeable<br />
liner to prevent stretching during the installation of the<br />
infiltration bed, choker course <strong>and</strong> wearing course<br />
aggregate. Seal all joints of the impermeable liner to be<br />
totally leak free.<br />
Install lateral flow cut-off barriers using 16 mil or<br />
thicker PE or PVC membrane liner or concrete walls<br />
installed parallel to the contours (i.e. normal to the flow)<br />
to prevent flow of water downstream <strong>and</strong> then surfacing<br />
at the toe of the porous asphalt pavement installation.<br />
Distance (L max ) between these cut-off barriers shall not<br />
exceed: