SC-1 Silt Fence (SF) Maintenance and Removal Inspection of silt fence includes observing the material for tears or holes and checking for slumping fence and undercut areas bypassing flows. Repair of silt fence typically involves replacing the damaged section with a new section. Sediment accumulated behind silt fence should be removed, as needed to maintain BMP effectiveness, typically before it reaches a depth of 6 inches. Silt fence may be removed when the upstream area has reached final stabilization. Photograph SF-2. When silt fence is not installed along the contour, a "J-hook" installation may be appropriate to ensure that the BMP does not create concentrated flow parallel to the silt fence. Photo courtesy of Tom Gore. SF-2 Urban Drainage and Flood Control District November 2010 Urban Storm Drainage Criteria Manual Volume 3
Silt Fence (SF) SC-1 November 2010 Urban Drainage and Flood Control District SF-3 Urban Storm Drainage Criteria Manual Volume 3
- Page 425 and 426: Rolled Erosion Control Products (RE
- Page 427: Rolled Erosion Control Products (RE
- Page 430 and 431: EC-7 Temporary Slope Drains (TSD) M
- Page 432 and 433: EC-7 Temporary Slope Drains (TSD) S
- Page 434 and 435: EC-8 Temporary Outlet Protection (T
- Page 437 and 438: Rough Cut Street Control (RCS) EC-9
- Page 439: Rough Cut Street Control (RCS) EC-9
- Page 442 and 443: EC-10 Earth Dikes and Drainage Swal
- Page 444 and 445: EC-10 Earth Dikes and Drainage Swal
- Page 447 and 448: Terracing (TER) EC-11 Description T
- Page 449 and 450: Check Dams (CD) EC-12 Description C
- Page 451 and 452: Check Dams (CD) EC-12 November 2010
- Page 453 and 454: Check Dams (CD) EC-12 November 2010
- Page 455 and 456: Streambank Stabilization (SS) EC-13
- Page 457: Wind Erosion/Dust Control (DC) EC-1
- Page 460 and 461: MM-1 Concrete Washout Area (CWA) se
- Page 462 and 463: MM-1 Concrete Washout Area (CWA) CW
- Page 464 and 465: MM-2 Stockpile Management (SM) When
- Page 466 and 467: MM-2 Stockpile Management (SM) SP-4
- Page 468 and 469: MM-2 Stockpile Management (SM) SP-6
- Page 470 and 471: MM-3 Good Housekeeping Practices (G
- Page 472 and 473: MM-3 Good Housekeeping Practices (G
- Page 474 and 475: MM-3 Good Housekeeping Practices (G
- Page 478 and 479: SC-1 Silt Fence (SF) SF-4 Urban Dra
- Page 480 and 481: SC-2 Sediment Control Log (SCL) Alt
- Page 482 and 483: SC-2 Sediment Control Log (SCL) SCL
- Page 485 and 486: Straw Bale Barrier (SBB) SC-3 Descr
- Page 487: Straw Bale Barrier (SBB) SC-3 Novem
- Page 490 and 491: SC-4 Brush Barrier (BB) Maintenance
- Page 492 and 493: SC-5 Rock Sock (RS) RS-2 Urban Drai
- Page 495 and 496: Inlet Protection (IP) SC-6 Descript
- Page 497 and 498: Inlet Protection (IP) SC-6 • Remo
- Page 499 and 500: Inlet Protection (IP) SC-6 August 2
- Page 501 and 502: Inlet Protection (IP) SC-6 August 2
- Page 503 and 504: Sediment Basin (SB) SC-7 Descriptio
- Page 505 and 506: Sediment Basin (SB) SC-7 Illustrati
- Page 507 and 508: Sediment Basin (SB) SC-7 August 201
- Page 509: Sediment Basin (SB) SC-7 August 201
- Page 512 and 513: SC-8 Sediment Trap (ST) ST-2 Urban
- Page 515: Vegetated Buffers (VB) SC-9 Descrip
- Page 518 and 519: SC-10 Chemical Treatment (CT) Maint
- Page 520 and 521: SM-1 Construction Phasing/Sequencin
- Page 522 and 523: SM-1 Construction Phasing/Sequencin
- Page 524 and 525: SM-2 Protection of Existing Vegetat
Silt Fence (SF)<br />
SC-1<br />
November 2010 <strong>Urban</strong> <strong>Drainage</strong> and Flood Control District SF-3<br />
<strong>Urban</strong> Storm <strong>Drainage</strong> <strong>Criteria</strong> <strong>Manual</strong> <strong>Volume</strong> 3