5.3.6<br />
The handling, pitching and the order of placing of the piles shall be enumerated<br />
according to their size and length, and whether they are to be placed singly or in<br />
clusters.<br />
5.3.7<br />
Test piles shall be scheduled separately and the position of each shall be stated.<br />
5.3.8<br />
Where the piles are to be placed from any level other than existing ground level this<br />
shall be stated in the description.<br />
5.3.9<br />
The placing of raking piles shall be scheduled separately.<br />
5.3.10<br />
Rock anchors where specified shall be scheduled generally in accordance with the<br />
principles of this section.<br />
5.4 MEASUREMENT PROCEDURE<br />
5.4.1<br />
Piles shall be classified according to type, size, and the length and shall be measured<br />
in metres.<br />
5.4.2<br />
Driving shall be measured in metres and classified according to the length of the piles<br />
to be driven.<br />
5.4.3<br />
Boring for piles shall be described and measured in metres and classified according<br />
to depth and size. Bulbs, bellings and the like shall be enumerated as extra value<br />
giving the volume outside the pile shafi.<br />
5.4.4<br />
Disposal of spoil shall be measured.<br />
5.4.5<br />
Liners or casings shall be measured in metres. If lefi in, this shall be stated.<br />
5.4.6<br />
Cutting piles to required levels, stripping to length, disposal of debris and bending of<br />
reinforcement shall be enumerated; if below water or ground level details shall be<br />
given.<br />
--`,,``,,,,,,``,``,`,,,`,,,`,-`-`,,`,,`,`,,`---<br />
5.4.7<br />
A provisional item or items shall be scheduled where required to cover the<br />
lengthening or shortening of piles where appropriate.<br />
5.4.8<br />
Tests on placed piles shall be described and enumerated.<br />
5.4.9<br />
Piles required to be cast away from the site and subsequently transported shall be<br />
so described.<br />
5-2<br />
Copyright Standards New Zealand<br />
Provided by IHS under license with SNZ<br />
Document provided by IHS Licensee=<strong>Unitec</strong> Inst of Technology/5911177001,<br />
03/02/2005 18:31:52 MST Questions or comments about this message: please call<br />
the Document Policy Group at 303-397-2295.