URBAN INFRASTRUCTURE <strong>CHAPTER</strong> <strong>14</strong> | PART 4<br />

F. Retention and Detention Pond<br />

The application of MASMA standards in SJER will result in a greater<br />

emphasis on providing retention and detention ponds or lakes to<br />

improve water quality, minimize flooding and improve the quality of the<br />

environment. The water in the ponds or lakes can be used to dilute rivers<br />

especially during dry season.<br />

G. Installation of Silt Traps<br />

UI 7 :<br />

UI 8 :<br />

UI 9 :<br />

KEY DIRECTION<br />

The need for sustainable sewerage system in SJER.<br />

All new housing development to be connected to the ecofriendly<br />

centralized sewerage system (CSS).<br />

All land made available for Sewerage Treatment Plants must<br />

be primarily reserved and designated for public purposes.<br />

Silt traps should also be constructed in many tributaries especially at the<br />

new development areas.<br />

H. Guidelines for Sustainable Storm Water Drainage & Flood Mitigation<br />

• Install trash racks or screens to trap debris/litter;<br />

• Allow for buffer strips and grass swales to protect water source<br />

from contamination by nearby development precinct.;<br />

A. Existing Sewerage System<br />

Sewerage waste in the District of Johor Bahru comes from both public<br />

and private sewerage plants, individual septic tanks (IST), primitive<br />

systems (villages and illegal squatters) and untreated discharge<br />

from households. As Indah Water Konsortium is only responsible for<br />

maintaining public treatment plants, many other forms of treatment<br />

plants are currently not properly maintained.<br />

• Install GPT and oil/grease traps in major drains at strategic<br />

locations;<br />

• Install series of bio-retention /infiltration porous systems for storm<br />

water to get back into the ground;<br />

• Install buried drainage pipes to cater for major storm; and<br />

• Install water collection equipment, storage and pump for recycle<br />

storm water as non-potable water.<br />

Sewerage Treatment Plant at Taman Suria Johor Bahru<br />

For land under development which has a gradient of less than 30º<br />

but greater than 25º, geo-technical analysis, analysis on contour and<br />

drainage pattern and an EIA study should be included. All hill slopes<br />

have to be closely turfed after cutting.<br />

<strong>14</strong>.9 Sewerage<br />

The Department of Sewerage Southern Region (JPP) is the government<br />

agency responsible for the management of sewerage in the District<br />

of Johor Bahru. Meanwhile operation and maintenance services is<br />

carried out by a concession company, Indah Water Konsortium (IWK).<br />

The process of taking over maintenance work has been carried out<br />

progressively by JPP since 1995. Untill now only the areas under the City<br />

Council of Johor Bahru and areas outside of Municipality Councils have<br />

not been taken over.<br />

<strong>14</strong> - 13