Risk Combination for Fishing areas and pisciculture installations in Crete. Numbers are in risk units 10 th NOS-DCP Meeting 22 Prof. Manju Mohan CAS, IIT Delhi
Risk Combination for Tourist zones, and Tourist installations in Crete. Numbers are in risk units 10 th NOS-DCP Meeting 23 Prof. Manju Mohan CAS, IIT Delhi
- Page 1 and 2: THE TENTH NATIONAL OIL SPILL DISAST
- Page 3 and 4: MAJOR OIL SPILL INCIDENTS Year Plac
- Page 5 and 6: Stages of Risk Analysis Hazard Iden
- Page 7 and 8: 2. Frequency Analysis i.e. Assessme
- Page 9 and 10: 4. Risk Calculation: Broadly risk c
- Page 11 and 12: CASE STUDIES 10 th NOS-DCP Meeting
- Page 13 and 14: Background of the Analysis • Cret
- Page 15 and 16: Map of Crete 10 th NOS-DCP Meeting
- Page 17 and 18: • As per priorities of significan
- Page 19 and 20: • The combined Risk Units for eac
- Page 21: Results from Crete Oil Spill Risk A
- Page 25 and 26: METHODOLOGY OVERVIEW • Hazard ide
- Page 27 and 28: Location of Gulf of Mexico Counties
- Page 29 and 30: • At about 11 km intervals in the
- Page 31 and 32: • The model counts the occurrence
- Page 33 and 34: Results from GoM Oil Spill Risk Ana
- Page 35 and 36: 10 th NOS-DCP Meeting 35 Prof. Manj
- Page 37 and 38: • The remotely sensed data as spa
- Page 39 and 40: • The GIS based system can be use
- Page 41 and 42: CONCLUSIONS • A schematic risk as
<strong>Risk</strong> Combination for Tourist zones, and Tourist installations in Crete.<br />
Numbers are in risk units<br />
10 th NOS-DCP Meeting<br />
23<br />
Prof. Manju Mohan<br />
CAS, IIT Delhi