Full Version - Essential Energy

Full Version - Essential Energy Full Version - Essential Energy

essentialenergy.com.au
from essentialenergy.com.au More from this publisher
27.09.2014 Views

18 When Country Energy formed in July 2001, we began a long-term program to upgrade our network, improve supply reliability and lift overall service levels. In the past four years, we have spent more than $560 million on our network and associated services, with plans to invest an additional $1.2 billion between 2005 and 2009. $187 million investment The past 12 months has seen substantial investment in our network – all aimed at cementing the reliability of our unique regional electricity network and catering for increased demands and the rising expectations of our diverse customer base. More than $187 million was spent on the network during 2004-2005, with a further $1.2 billion pledged for the next five years. The challenge of distributing a safe and reliable power supply to such a vast geographic area, which includes some of the fastest-growing areas of the State, requires innovative, state-of-the-art solutions and forward thinking. Major initiatives of the past 12 months included the conversion and re-construction of sub-transmission powerlines, construction of new zone substations and the upgrade of major powerlines. Network investment by region Northern – $14.8 million North Western – $18 million Far North Coast – $41 million Far North Coast Region Northern Region North Western Region Mid North Coast – $29 million Mid North Coast Region Central Western Region Central Western – $9.3 million South Western Region Riverina Region South Western – $8.3 million South Eastern Region South Eastern – $19 million Riverina – $20.5 million COUNTRY ENERGY ANNUAL REPORT 2004–2005

The table below highlights some examples of projects that will be partially or fully completed in the next five years. Area Project Amount Key dates Albury Ballina Install new transformer and construct 132kV powerline to Corowa to increase capacity and improve reliability Major upgrade and expansion of the existing Ballina zone substation to increase capacity and improve reliability $2.7 million Due for completion by December 2006 $2.5 million Due for completion by July 2006 Lennox Head Bathurst New zone substation at Lennox Head to supply Lennox Head area, currently supplied by Ballina zone substation $2.5 million Due for completion by July 2008 Construct a new powerline for the industrial area at Raglan as backup supply for major industrial customers as well as improving reliability to urban and rural customers $300,000 Due for completion by December 2005 19 Coffs Harbour Dunedoo Condobolin Lismore Murrumbidgee Tweed Heads Wentworth Tamworth Construct Moonee to Coffs Harbour North 66kV power line to improve reliability Construct new high voltage powerline from Dunedoo to Coolah Village to increase capacity and improve supply quality Upgrade Condobolin to Tallebung powerline to 33kV to increase capacity and improve supply quality Construct new zone substation to supply Lismore University and surrounding area Construct 132/11kV Griffith substation 132kV transformer bays, 3000amp SWBD building and 132/11kV transformer to meet increased demand Construct new zone substation at Cobaki to increase capacity Install 66kV powerline and feeder bay at Dareton to cater for increased demand Rebuild Oxley Vale zone substation to cater for load growth $3.2 million Due for completion by July 2006 $250,000 Due for completion by December 2007 $630,000 Due for completion by December 2005 $3 million Due for completion by July 2007 $3.2 million Due for completion by December 2006 $3 million Due for completion by July 2008 $3.2 million Due for completion by November 2005 $3.8 million Due for completion by December 2006 COUNTRY ENERGY ANNUAL REPORT 2004–2005

18<br />

When Country <strong>Energy</strong> formed in July 2001, we began<br />

a long-term program to upgrade our network, improve<br />

supply reliability and lift overall service levels. In the<br />

past four years, we have spent more than $560 million<br />

on our network and associated services, with plans to<br />

invest an additional $1.2 billion between 2005 and 2009.<br />

$187 million investment<br />

The past 12 months has seen substantial investment<br />

in our network – all aimed at cementing the reliability<br />

of our unique regional electricity network and catering<br />

for increased demands and the rising expectations of<br />

our diverse customer base. More than $187 million was<br />

spent on the network during 2004-2005, with a further<br />

$1.2 billion pledged for the next five years.<br />

The challenge of distributing a safe and reliable power<br />

supply to such a vast geographic area, which includes<br />

some of the fastest-growing areas of the State,<br />

requires innovative, state-of-the-art solutions and<br />

forward thinking.<br />

Major initiatives of the past 12 months included the<br />

conversion and re-construction of sub-transmission<br />

powerlines, construction of new zone substations and<br />

the upgrade of major powerlines.<br />

Network investment by region<br />

Northern – $14.8 million<br />

North Western – $18 million<br />

Far North Coast – $41 million<br />

Far North Coast Region<br />

Northern Region<br />

North Western Region<br />

Mid North Coast – $29 million<br />

Mid North Coast Region<br />

Central<br />

Western Region<br />

Central Western – $9.3 million<br />

South Western<br />

Region<br />

Riverina<br />

Region<br />

South Western – $8.3 million<br />

South<br />

Eastern<br />

Region<br />

South Eastern – $19 million<br />

Riverina – $20.5 million<br />

COUNTRY ENERGY ANNUAL REPORT 2004–2005

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!