UNCLASSIFIED<br />
OPERATIONAL PROCEDURE - <strong>Elster</strong> <strong>LCR</strong>-<strong>212</strong> <strong>Single</strong> <strong>Phase</strong><br />
<strong>Load</strong> <strong>Control</strong> Ripple Receiver Installation and<br />
Use<br />
CEOP8086<br />
It is also possible to execute test switching operations with the programmer however, the<br />
input of the receiver is not tested through the serial interface. To test the input of the<br />
receiver, a TT-2 test transmitter can be used or a remote signal from a frequency injection<br />
plant can be called upon.<br />
When programming receivers not mounted and powered up on a switchboard, a suitable<br />
“receiver power-up cradle” shall be used.<br />
22 March 2011 - Issue 3<br />
Approved By: General Manager Technical Services<br />
Page 14 of 17<br />
UNCLASSIFIED<br />
UNCONTROLLED COPY IF PRINTED