27.09.2014 Views

CEOP8079 - Connection Guidelines - Essential Energy

CEOP8079 - Connection Guidelines - Essential Energy

CEOP8079 - Connection Guidelines - Essential Energy

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

UNCLASSIFIED<br />

OPERATIONAL PROCEDURE – <strong>Connection</strong> <strong>Guidelines</strong> for High<br />

Voltage <strong>Connection</strong>s and Embedded Generators<br />

<strong>CEOP8079</strong><br />

The results achieved from the test.<br />

Each test report must be:<br />

Signed and dated by the testing officer(s) and the witnessing officer<br />

Provided to <strong>Essential</strong> <strong>Energy</strong>.<br />

12.3.4 Commissioning Tests<br />

The <strong>Connection</strong> Applicant will produce a test plan to cover the commissioning requirements<br />

of all High Voltage assets and secondary equipment. This plan must identify testing<br />

responsibilities and actions for all parties and must be submitted for <strong>Essential</strong> <strong>Energy</strong>‟s<br />

agreement and approval. <strong>Essential</strong> energy must approve the commissioning program, final<br />

design and equipment requirements, prior to it being finalised by the <strong>Connection</strong> Applicant‟s<br />

ASP or its nominated representative.<br />

Commissioning tests will vary depending upon the type and make of equipment to be<br />

installed, the manufacturer‟s recommendations and <strong>Essential</strong> <strong>Energy</strong>‟s policies covering<br />

commissioning tests for zone substation equipment, secondary systems, HV transmission<br />

lines and cables.<br />

Final commissioning may also require phase identification, temporary protection schemes,<br />

service voltage testing, phasing out checks, protection directional checks and in-service<br />

balances and in-service metering checks.<br />

<strong>Essential</strong> <strong>Energy</strong> needs to ensure that all appropriate tests have been completed so that all<br />

HV equipment can be energised. This will require close cooperation between the ASP and<br />

<strong>Essential</strong> <strong>Energy</strong> employees. <strong>Essential</strong> <strong>Energy</strong> will also expect the <strong>Connection</strong> Applicant to<br />

rectify all defects found as a result of testing and checks by <strong>Essential</strong> <strong>Energy</strong> or others<br />

employed by the <strong>Connection</strong> Applicant. Any delay in defect rectification may impact on final<br />

commissioning which may, in turn, delay commissioning of other infrastructure owned by<br />

the <strong>Connection</strong> Applicant.<br />

Commissioning tests and checks to ensure compliance may include but not be limited to:<br />

Substations<br />

General compliance including civil and building works, secondary containment<br />

systems, fencing, public safety, security, fire protection systems, general layout of<br />

equipment<br />

Identification of equipment in accordance with <strong>Essential</strong> <strong>Energy</strong>‟s requirements<br />

Earth grid and earthing of equipment<br />

Conductivity and insulation testing<br />

HV disconnect and earthing switches<br />

HV circuit breakers<br />

HV current transformers<br />

HV voltage transformers<br />

Power transformers (including high voltage testing and On Load Tap Changer (OLTC)<br />

Protection schemes and associated secondary equipment<br />

Substation control systems<br />

Metering<br />

SCADA systems<br />

23 November 2012 - Issue 7<br />

Approved By: Group Manager Major Customer Engagement<br />

Page 24 of 36<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!