OPERATIONAL PROCEDURE – <strong>Connection</strong> <strong>Guidelines</strong> for High<br />
Voltage <strong>Connection</strong>s and Embedded Generators<br />
<strong>CEOP8079</strong><br />
9 CONNECTION AGREEMENT<br />
<strong>Essential</strong> <strong>Energy</strong>‟s connection agreement will deal with:<br />
Location of connection project<br />
The agreed point of connection (shown on a Single Line Diagram - SLD)<br />
The <strong>Connection</strong> Agreement term, commencement and termination dates<br />
The maximum Voltage fluctuation<br />
<strong>Connection</strong> assets to be transferred to <strong>Essential</strong> <strong>Energy</strong><br />
Easements and other Registrable Instruments<br />
Land title deeds<br />
Route or land plans – initial survey and final form of survey<br />
The agreed technical standards of equipment to be connected<br />
The agreed access standards (automatic or negotiated)<br />
The agreed performance standards (for generators)<br />
Any augmentation work to the network<br />
Any ancillary services provided by the <strong>Connection</strong> Applicant<br />
Any network service charges<br />
The agreed network transfer capacity<br />
The remote control and monitoring equipment required by AEMO if applicable<br />
Proposed metering installation<br />
Arrangements for meter provision<br />
The commercial terms and conditions<br />
Maximum voltage fluctuation<br />
Authorised staff<br />
Land tenure, if required and not addressed in any LAIA.<br />
Note that the connection of the connecting assets may be conditional on gaining<br />
environmental and planning approvals for any necessary augmentation or extension works<br />
to <strong>Essential</strong> <strong>Energy</strong>‟s network and finalisation of other schedules to the connection<br />
agreement post execution.<br />
The agreement may also address the delivery of assets required to give physical effect to<br />
the connection service.<br />
If a deemed connection is required to be documented under the NER, the connected person<br />
will be taken to be a <strong>Connection</strong> Applicant for the purposes of the connection agreement.<br />
Template connection agreements are available by contacting the Manager Network<br />
<strong>Connection</strong>s by email: networkconnections@essentialenergy.com.au<br />
23 November 2012 - Issue 7<br />
Approved By: Group Manager Major Customer Engagement<br />