SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT<br />

FY2014 COOPERATIVE FUNDING INITIATIVE APPLICATION FORM<br />

Project Name<br />

Reclaimed <strong>Water</strong> - Pasco County - Reclaimed <strong>Water</strong> for Natural System Treatment & Restoration Phase<br />

4<br />

Project Number H092<br />

Cooperator<br />

Pasco County<br />

Department<br />

Utilities<br />

Contact Person Pamela Wright<br />

Address<br />

7536 State Street<br />

City Sate Zip New Port Richey, FL 34654<br />

Phone #<br />

727-847-8145 ext7825<br />

Email<br />

pwright@pascocountyfl.net<br />

Project Type:<br />

X <strong>Water</strong> Supply <strong>Water</strong> Quality Flood Protection X Natural Systems<br />

Strategic Initiatives:<br />

<strong>Water</strong> Quality Maintenance and Improvement <strong>Water</strong> Quality Monitoring<br />

Alternative <strong>Water</strong> Supply Conservation<br />

X Reclaimed <strong>Water</strong> <strong>Region</strong>al <strong>Water</strong> Supply Planning<br />

Emergency Flood Response Floodplain <strong>Management</strong><br />

Minimum Flows and Level Establishment and Monitoring Minimum Flows and Levels Recovery<br />

X Natural Systems Conservation and Restoration Natural Systems Identification and Monitoring<br />

Indicate All Counties to Benefit From Project:<br />

Charlotte Citrus Desoto Hardee Hernando Highlands Hillsborough Lake<br />

Levy Manatee Marion X Pasco Pinellas Sarasota Sumter Polk<br />

Project Description:<br />

This project is for the design, permitting and construction of facilities that will help to restore natural systems that have been<br />

impacted by groundwater withdrawals in central Pasco County. These facilities may include; created wetlands, infiltration basins<br />

and/or spray irrigation systems. The final scope of the project will be more clearly defined as the preliminary design phase is<br />

completed for the project. This preliminary design work will include: evaluation of the technical aspects of the project, meetings to<br />

coordinate activities with all the key stakeholders associated with the project, discussions with the regulatory agencies which will be<br />

involved with the permitting and other project approvals including any nitrogen management concerns associated with the project,<br />

and meetings to invite public involvement and address public comments and concerns. The final project design, permitting and<br />

construction will follow the preliminary design work.<br />

This request is for phase four of the project. During this phase the following tasks are anticipated to be completed during FY '14.<br />

Task 5 - design, Task 5.1 - preliminary engineering report, Task 5.2 - final design, Task 6 - permitting, and Task 7 - bid services.<br />

Describe your organizations efforts in developing, implementing and enforcing water conservation and flood protection<br />

ordinances.<br />

Pasco County adopted Ordinance 01-08 requiring the following: one day/week irrigation restrictions for potable water; curtailed use<br />

of potable water for irrigation when rain has occurred within 24 hours; scheduled availability and restricted use of reclaimed water<br />

irrigation to distribute limited supply to as many customers as possible; washing of non-business, personal vehicles only using low<br />

volume methods and over non-impervious surfaces; prohibiting aesthetic uses of water unless such use also provides a necessary<br />

aeration or water quality benefit; and the use of reclaimed water for road construction activities when available. Enforcement of this<br />

ordinance is by designated County personnel and law enforcement officers. During <strong>Water</strong> Year 2012, 100% of Pasco County<br />

Utilities' wastewater was reused. The bulk rate charged for the use of reclaimed water is $0.47 per 1,000 gallons (normal rate),<br />

$0.21 per 1,000 gallons (surplus rate), and a flat rate of $10.26 per month residential irrigation. Pasco County's potable water rates<br />

are applied in a water conservation inclining block rate. County Ordinance 93-16 requires each new development to construct a<br />

reclaimed water distribution system as a condition of wastewater service when the development is within designated areas in the<br />

Reclaimed <strong>Water</strong> Master Plan and when providing the development with reclaimed water supply is determined in the best interest<br />

of the County. Pasco County participates in the National Flood Insurance Program, administered through FEMA. All finished floor<br />